Final | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Final | 10/5/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Daryl Spivey
|
|
|
Re-inspect floors 1-4 FINAL, Final for 9th floor. If questions call Larry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann tco ok.....floors 2-9 complete.........still need funnel drain, open w/c seat, insulation on piping and 10th floor.......also open up cabinet for floor sink.........ds
|
Final | 9/20/2017 | 9/21/2017 | 9/21/2017 | A | PART |
Bill VanDegrift
|
|
|
Final for floors 1st -4th, if you have any questions call Larry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann 1) provide funnel for floor drains receiving condensate drainage. 2) open up cabinet at floor sink in food prep area. 3) open front seats required on public toilets. 4) hook up all equipment. 5) remove splitter at mop sink faucett for chemical station. 6) provide shutoff valves for clothes washers. 7) Ice bin drains at all ice machines may not be connected to other drains. 8) caulk mop sinks 9) expose condensate terminations in planters on 2nd floor. 10) complete insulation of exposed piping. 11) install pool room rp drip cup drains. 12) install 2nd floor booster pump relief lines. 13) 1st floor mechanical room incomplete. 14) rooms 302, 325, 402, 405 and 408 incomplete.
|
Final | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | PART |
Daryl Spivey
|
|
|
Final for Floors 4th, 5th, 6th ; 7th. If questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann inspection was done on 5th, 6th, 7th and 8th floors.......4 not ready.......5th, 7th and 8th plumbing done.......6th has 3 lav countertops missing. rooms 502, 602, 702 and 802 not finished. RP's need installed on ice machines with filters.........ds
|
Plumbing Rough-in | 7/13/2017 | 7/14/2017 | 7/14/2017 | P | CANC |
Daryl Spivey
|
|
|
If there are any questions please contact Larry Johnstone at ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Inspection cancelled from web by: Stacia Haumann
|
Plumbing Rough-in | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | PART |
Daryl Spivey
|
|
|
9th ; 10th Floor, if questions call larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water ok on 9th and 10th floors west side.............ds
|
Plumbing Rough-in | 4/19/2017 | 4/20/2017 | 4/19/2017 | A | CANC |
Daryl Spivey
|
|
|
if questions call Chad @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Inspection cancelled from web by: Stacia Haumann
|
Plumbing Rough-in | 4/18/2017 | 4/19/2017 | 4/19/2017 | P | PART |
Daryl Spivey
|
|
|
Rough-In Water 9th ; 10th Floors. If questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water on 9th and 10th floors east side ok........ds
|
Plumbing Rough-in | 4/13/2017 | 4/14/2017 | 4/14/2017 | P | PART |
Daryl Spivey
|
|
|
If you have any questions please call Larry Johnstone ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann 9th and 10th floor west side waste and vent tested ok............ds
|
Plumbing Rough-in | 4/12/2017 | 4/13/2017 | 4/13/2017 | A | PART |
Dan Ediger
|
|
|
If there are any questions please contact Larry Johnstone ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann. East side DWV floors 9 and 10 ok.
|
Plumbing Rough-in | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Daryl Spivey
|
|
|
1st floor water. If questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 3/13/2017 | 3/13/2017 | 3/13/2017 | P | PART |
Daryl Spivey
|
|
|
Rough-in 7th ; 8th floors. if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water and roof drains tested 7th and 8th floors.............ds
|
Plumbing Rough-in | 3/10/2017 | 3/13/2017 | 3/13/2017 | A | NR |
Daryl Spivey
|
|
|
Rough-in 7th ; 8th floors. if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 3/10/2017 | 3/10/2017 | 3/10/2017 | P | PART |
Daryl Spivey
|
|
|
waste ; vent. If questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann W/V west side 7th and 8th floors ok............ds
|
Plumbing Rough-in | 3/8/2017 | 3/9/2017 | 3/9/2017 | A | PART |
Daryl Spivey
|
|
|
7th ; 8th Floors - if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann W/V only east side ok..........ds
|
Other | 2/8/2017 | 2/9/2017 | 2/10/2017 | A | PART |
Bill VanDegrift
|
|
|
Conferance 10:00 AM ok
|
Plumbing Rough-in | 2/10/2017 | 2/10/2017 | 2/10/2017 | P | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 6th floor water ok.............ds
|
Plumbing Rough-in | 2/9/2017 | 2/9/2017 | 2/9/2017 | A | PART |
Daryl Spivey
|
|
|
Water r/i on 5th floor ok...........ds
|
Other | 2/8/2017 | 2/9/2017 | 2/9/2017 | A | PASS |
Daryl Spivey
|
|
|
Conferance 10:00 AM suds relief
|
Other | 2/8/2017 | 2/9/2017 | 2/9/2017 | A | DONE |
Eric Strole
|
|
|
Conferance 10:00 AM-Conferance on suds relief.
|
Other | 2/8/2017 | 2/9/2017 | 2/8/2017 | A | CANC |
Dan Ediger
|
|
|
Conferance 10:00 AM
|
Plumbing Rough-in | 2/7/2017 | 2/8/2017 | 2/8/2017 | A | PART |
Eric Strole
|
|
|
Larry Phone #: ###-####-5th and 6th flr west side pass.
|
Plumbing Rough-in | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 5th and 6th floors waste and vent tested as marked on plans..........ds
|
Plumbing Rough-in | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | CANC |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Inspection cancelled from web by: Stacia Haumann
|
Plumbing Rough-in | 1/31/2017 | 2/1/2017 | 2/1/2017 | P | CANC |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Inspection cancelled from web by: Stacia Haumann
|
Plumbing Rough-in | 1/25/2017 | 1/26/2017 | 1/26/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann partial 1st floor waste and vent.........ds
|
Plumbing Rough-in | 1/23/2017 | 1/23/2017 | 1/23/2017 | P | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann as marked on plans.............ds
|
Plumbing Rough-in | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 3rd floor water........needs more support in several places............ds
|
Plumbing Rough-in | 1/16/2017 | 1/17/2017 | 1/17/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water on 3rd floor partial.............ds
|
Plumbing Rough-in | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PART |
Daryl Spivey
|
|
|
if questions call larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann All rooms ok except 314, 406, 410, 413, 417 and 431..........ds
|
Plumbing Rough-in | 1/9/2017 | 1/9/2017 | 1/9/2017 | P | CANC |
Daryl Spivey
|
|
|
If questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Plumbing Rough-in | 1/6/2017 | 1/9/2017 | 1/9/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 1st floor main up to 4th floor waste and vent.........ds
|
Plumbing Rough-in | 1/5/2017 | 1/6/2017 | 1/6/2017 | A | PART |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann as marked on plans...........ds
|
Plumbing Rough-in | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | PART |
Eric Strole
|
|
|
Test on dwv 3rd and 4th flr west side of corridor except end units both flrs both sides and 3rd flr laundry pass.
|
Plumbing Rough-in | 12/27/2016 | 12/29/2016 | 12/29/2016 | A | PART |
Eric Strole
|
|
|
if questions call Larry @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-3rd and 4th flr east side of corridor dwv pass.
|
Plumbing Rough-in | 12/27/2016 | 12/27/2016 | 12/27/2016 | P | NR |
Daryl Spivey
|
|
|
if questions call Larry @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
PLM-Aging Inspection | 10/19/2016 | 10/19/2016 | 10/19/2016 | | PEND |
Daryl Spivey
|
|
|
wip
|
PLM-Aging Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PART |
Eric Strole
|
|
|
wip
|
Groundwork | 4/20/2016 | 4/21/2016 | 4/21/2016 | P | PART |
Daryl Spivey
|
|
|
if questions call Chad ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann as marked on plans..........ds
|
Groundwork | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | PART |
Jim Little
|
|
|
if questions call Chad @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann >level 1 public restroom gw ok >level 1 bar and kit grease ok
.
|
Groundwork | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PART |
Daryl Spivey
|
|
|
Please Call Mike Chapman @ ###-#### with any questions. Thank You - Holly Grago. Phone #: ###-#### Inspection requested via web by Stacia Haumann water service and grease line partial ok..........ds
|
Groundwork | 4/11/2016 | 4/12/2016 | 4/12/2016 | A | PART |
Daryl Spivey
|
|
|
Groundwork Partial any questions please call Chad @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann as marked on plans...ds
|
Groundwork | 4/1/2016 | 4/1/2016 | 4/1/2016 | P | PART |
Daryl Spivey
|
|
|
if questions call Chad @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann partial on elevator drain...........ds
|
Groundwork | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Jim Little
|
|
|
if questions call Chad at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann >next grid sec ok, marked on plans
|
Groundwork | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | PASS |
Jim Little
|
|
|
if questions call Chad @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann >10" rd ok sw corner
|
Groundwork | 3/4/2016 | 3/4/2016 | 3/4/2016 | P | NR |
Jim Little
|
|
|
if questions call Chad @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann >NR but ok'd Chad to stub 10" 90 out fnd wall for storm drain and partially bury, to be under test and inspected monday and must match App plans.
|
Groundwork | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PEND |
Eric Strole
|
|
|
Partial GW. If questions call Chad @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann-Need approved plans on site. Per Bill section complete needs to match approved plans. Told plumber need to have approved plans on site before they call in for any other inspections.
|
Groundwork | 2/26/2016 | 2/29/2016 | 2/29/2016 | P | PART |
Jim Little
|
|
|
if questions call Chad @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann >garage drains from SOG-7 grid line ok level 1 >need approved plans onsite before further inspections are completed.
|
Groundwork | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | PASS |
Daryl Spivey
|
|
|
24 hr test on G/I. Chad
|
Groundwork | 2/4/2016 | 2/5/2016 | 2/5/2016 | A | PART |
Daryl Spivey
|
|
|
Partial Ground Work for Grease Trap Phone #: ###-#### Inspection requested via web by Stacia Haumann 24 hr test start on G/I and piping out of G/I ok..........ds
|
Groundwork | 1/18/2016 | 1/19/2016 | 1/19/2016 | A | PART |
Daryl Spivey
|
|
|
partial U/G - Interceptor Tie In. If questions call Ben @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann 24 hr test on tank ok and waste and vent lines tested ok...........ds
|
Groundwork | 1/6/2016 | 1/7/2016 | 1/7/2016 | P | PART |
Daryl Spivey
|
|
|
Ben 24 hr test complete on S and O int......ds
|
Groundwork | 1/6/2016 | 1/6/2016 | 1/6/2016 | P | PART |
Daryl Spivey
|
|
|
plumbing underground. Sand/Oil separator. If questions please contact Ben @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann start 24 hr test on Sand and Oil interceptor.........ds
|