PLM-Aging Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | | PASS |
Daryl Spivey
|
|
|
|
DOC - Permit Finaled | 12/4/2017 | 12/4/2017 | 12/4/2017 | P | PASS |
Daryl Spivey
|
|
|
g/w and water and sewer services completed..........ds
|
Plumbing Rough-in | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Daryl Spivey
|
|
|
Partial inspection for cover Phone #: ###-#### Inspection requested via web by Jason Lattimer waste stack tested by mech room for electrical conduits.will be tested again later.........ds
|
Water and/or Sewer | 8/30/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Daryl Spivey
|
|
|
Water main tie-in Phone #: ###-#### Inspection requested via web by Jason Lattimer water service tested ok from meter in...........ds
|
Water and/or Sewer | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | CANC |
Daryl Spivey
|
|
|
Tie in to meters Phone #: ###-#### >> Inspection requested via web by Jason Lattimer Inspection cancelled from web by: Jason Lattimer
|
Other | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Daryl Spivey
|
|
|
Consultation Inspection requested via web by wes Ritchie
|
Water and/or Sewer | 5/30/2017 | 5/30/2017 | 5/30/2017 | P | PASS |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie water serice tested ok.........ds
|
Groundwork | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PASS |
Daryl Spivey
|
|
|
Ground work complete........ds
|
Roof Drains | 5/11/2017 | 5/11/2017 | 5/11/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie roof drains in ground work tested ok.......ds
|
Groundwork | 5/10/2017 | 5/10/2017 | 5/10/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie partial SS and roof drains...........ds
|
Groundwork | 5/9/2017 | 5/9/2017 | 5/9/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie as marked on plan.....SS and GR........ds
|
Groundwork | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie roof drain partial ok...........ds
|
Groundwork | 4/27/2017 | 4/27/2017 | 4/27/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie water service stubbed in ........tested ok......ds
|
Groundwork | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie SS and grease partial marked on plan.........ds
|
Groundwork | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie sanitary marked on plan...........ds
|
Plumbing Rough-in | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie marked on plan ......partial grease,sewer and drainfor elevator pump........ds
|
Groundwork | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by wes Ritchie partial on sanitary.....marked on plans........ds
|
Groundwork | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | PASS |
Daryl Spivey
|
|
|
Make us the last stop of your day please Phone #: ###-#### Inspection requested via web by wes Ritchie sanitary and roof drains tested ok........ds
|
Groundwork | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | CANC |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie
|
Other | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie conference only.........ds
|
Groundwork | 4/3/2017 | 4/3/2017 | 4/3/2017 | P | PART |
Daryl Spivey
|
|
|
Inspection requested via web by wes Ritchie marked on plan........ds
|
Water and/or Sewer | 3/31/2017 | 3/31/2017 | 3/31/2017 | P | PART |
Dan Ediger
|
|
|
Phone #: ###-#### Inspection requested via web by wes Ritchie. Part of grease. building exit to the riser room. ok to cover
|
Other | 3/29/2017 | 3/30/2017 | 3/30/2017 | P | DONE |
Daryl Spivey
|
|
|
Would like a consultation at job site please see jason or robert Phone #: ###-#### Inspection requested via web by wes Ritchie Discussed suds relief, G/I installation and general inspection requirements......ds
|