Final | 11/28/2018 | 11/28/2018 | 11/28/2018 | A | PASS |
Matt Wrobel
|
|
|
Final on Garage permit. Phone #: ###-#### Inspection requested via web by Preston Langdon corrections made
|
Final | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PART |
Dan Ediger
|
|
|
Re-inspection for ejector pump correction. Phone #: ###-#### Inspection requested via web by Preston Langdon. ejector valve and tempering valve ok
|
Final | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PART |
Dan Ediger
|
|
|
Basement/Ejector Add a second shut-off valve to the basement ejector
|
PLM-Aging Inspection | 11/8/2018 | 11/8/2018 | 11/8/2018 | | CANC |
Eric Strole
|
|
|
|
PLM-Aging Inspection | 8/9/2018 | 8/9/2018 | 8/9/2018 | | CANC |
Eric Strole
|
|
|
|
PLM-Aging Inspection | 5/10/2018 | 5/10/2018 | 5/10/2018 | | PEND |
Daryl Spivey
|
|
|
|
Groundwork | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | PASS |
Daryl Spivey
|
|
|
Sub rough area drains and vents Phone #: ###-#### Inspection requested via web by Preston Langdon
|
Groundwork | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PART |
Bill VanDegrift
|
|
|
Area drain partial sub rough, West side of garage Phone #: ###-#### Inspection requested via web by Preston Langdon basement parking area drains, two on the west side and the trench drain at the bottom of the ramp test ok.
|
Groundwork | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by Preston Langdon waste and vent from flammable int to pump station tested ok...........ds
|
Groundwork | 9/1/2017 | 9/5/2017 | 9/5/2017 | A | PASS |
Daryl Spivey
|
|
|
Verify 24hr test on Flammable Liquid Interceptor Phone #: ###-#### Inspection requested via web by Preston Langdon
|
Groundwork | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PART |
Daryl Spivey
|
|
|
Preston Flammable tank test start 24 hr test.........ds
|
Groundwork | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | NR |
Daryl Spivey
|
|
|
Flammable Liquid Interceptor Phone #: ###-#### Inspection requested via web by Preston Langdon
|