Card not on site to sign | 1/24/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Daryl Spivey
|
|
|
|
Final | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Daryl Spivey
|
|
|
If questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann no occ. card on site...........ds
|
Final | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | PART |
Daryl Spivey
|
|
|
Partial Final - If questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann kitchen area not ready yet..........all other areas ok for occupancy..........ds
|
Roof Drains | 11/16/2018 | 11/19/2018 | 11/19/2018 | A | PASS |
Dan Ediger
|
|
|
rough-in roof drains. if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann Final Roof connection
|
Plumbing Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Daryl Spivey
|
|
|
Gas test inspections transfer to mech permit
|
Plumbing Rough-in | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann all waste and water tested in bld............ds
|
Plumbing Rough-in | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann partial water............ds
|
Plumbing Rough-in | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann 1st floor restroom and 5 sinks and D/F on 2nd floor tested ok.........All waste and vent on 2nd floor completed..........ds
|
Pressure Test | 10/15/2018 | 10/15/2018 | 10/15/2018 | A | PART |
Daryl Spivey
|
|
|
60 lb test on Gas to meter location...........partial only..........ds
|
Plumbing Rough-in | 10/12/2018 | 10/15/2018 | 10/15/2018 | A | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann partial gas line test...........tested 60 lbs ok.......ds
|
Plumbing Rough-in | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | CANC |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Roof Drains | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | PASS |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann roof drains north side tested ok.......ds
|
Plumbing Rough-in | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann Kitchen waste and water tested ok..........partial gas at 60 lbs from meter to mech room ok........ds
|
Plumbing Rough-in | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann roof drains and bathroom 1st floor tested ok........ds
|
Plumbing Rough-in | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann upstairs bathroom tested ok..............ds
|
Roof Drains | 9/4/2018 | 9/4/2018 | 9/4/2018 | P | PART |
Daryl Spivey
|
|
|
inside roof drain inspection. if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann north end roof drains tested ok............ds
|
Plumbing Rough-in | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann 2nd fl partial..........classroom sinks and d/f tested water and waste.............ds
|
Plumbing Rough-in | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann west side vent and roof drains tested ok for cover............ds
|
Plumbing Rough-in | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PART |
Bill VanDegrift
|
|
|
if questions call Glen @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann north half of area B 1st floor ok, couldn't find plans to sign off on, update at next inspection if available.
|
Roof Drains | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | PART |
Bill VanDegrift
|
|
|
rough-in roof drains - if questions call Glen @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann roof drains south side test ok
|
Plumbing Rough-in | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann south side of south corridor up thru second floor tested water and waste.........ds
|
Groundwork | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Daryl Spivey
|
|
|
G/I 24 hr test
|
Groundwork | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Daryl Spivey
|
|
|
Underground Plumbing ; Grease Interceptor inspection. If questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumannground work kitchen area ok......g/w complete. start 24 hr test on G/I..........ds
|
Water and/or Sewer | 3/15/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Daryl Spivey
|
|
|
Water Service to Building - if questions call Glen @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann water tested ok.........ds
|
Water and/or Sewer | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | CANC |
Daryl Spivey
|
|
|
water service to building. if questions call Glen @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Inspection cancelled from web by: Stacia Haumann
|
Groundwork | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann sanitary in kitchen tested,.......ds
|
Groundwork | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan..g/w complete except for kitchen .......ds
|
Groundwork | 3/2/2018 | 3/5/2018 | 3/5/2018 | A | PART |
Daryl Spivey
|
|
|
If questions, please call Jim Little Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on lan.......ds
|
Groundwork | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Glen at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan...........ds
|
Groundwork | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan.............ds
|
Groundwork | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan..........ds
|
Groundwork | 2/12/2018 | 2/12/2018 | 2/12/2018 | P | PART |
Daryl Spivey
|
|
|
If there are any questions please contact Glen B. at ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan.....ds
|
Groundwork | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann marked on plan........ds
|
Groundwork | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PART |
Daryl Spivey
|
|
|
if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann southeast branch marked on plan........ds
|
Groundwork | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PART |
Daryl Spivey
|
|
|
LATE PM (the later the better) if questions please call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann main trunk tested ok......ds
|
Groundwork | 11/21/2017 | 11/22/2017 | 11/22/2017 | A | PASS |
Daryl Spivey
|
|
|
Underground (Lift Station) - if questions call Glen @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|