Final | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Daryl Spivey
|
|
|
HENRY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Final | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | FAIL |
Dan Ediger
|
|
|
HENRY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER 1. Install all plumbing fixtures and plumbing complete prior to scheduling a final. 2. The ADA wc require flush handles on the accessable side. 3. Floor drains must be flush and sealed. 4. The upstairs men's floor drain is missing.
|
Final | 9/27/2018 | 10/1/2018 | 10/1/2018 | A | CANC |
Dan Ediger
|
|
|
HENRY IS THE JOB CONTACT ###-#### Phone #: ###-#### >> Inspection requested via web by BECCA DUMMER Inspection cancelled from web by: BECCA DUMMER
|
Final | 9/27/2018 | 9/28/2018 | 9/27/2018 | A | CANC |
Dan Ediger
|
|
|
HENRY IS THE JOB CONTACT ###-#### Phone #: ###-#### >> Inspection requested via web by BECCA DUMMER Inspection cancelled from web by: BECCA DUMMER
|
Plumbing Rough-in | 7/30/2018 | 7/31/2018 | 7/31/2018 | P | PART |
Dan Ediger
|
|
|
ANDY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Waiting on approved design for pvc pipes in plenum
|
Plumbing Rough-in | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | CANC |
Dan Ediger
|
|
|
HVAC review scheduled for this afternoon. Piping test passed. HVAC under redesign.
|
Plumbing Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PART |
Dan Ediger
|
|
|
ANDY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Plumbing Rough-in | 7/13/2018 | 7/16/2018 | 7/16/2018 | A | FAIL |
Dan Ediger
|
|
|
ANDY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER.. No access to an approved set of plans. The water and waste test pressure are passed to the south half of the bulilding and ok to pull the test. Approved to cover on side of the walls. Call for re-inspection with access to a stamped set of plans.
|
Roof Drains | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Dan Ediger
|
|
|
ANDY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Groundwork | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PART |
Dan Ediger
|
|
|
PHIL IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. water service into the building ok. recall after the connection outside of the building to the water service
|
Groundwork | 3/21/2018 | 3/22/2018 | 3/22/2018 | P | PART |
Dan Ediger
|
|
|
ROB IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER. Ground work ok to cover. Test roof drain leaders and schedule
|
Groundwork | 3/20/2018 | 3/21/2018 | 3/21/2018 | P | NR |
Dan Ediger
|
|
|
ROB IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
Groundwork | 3/20/2018 | 3/21/2018 | 3/20/2018 | A | CANC |
Dan Ediger
|
|
|
ROB IS THE JOB CONTACT ###-#### Phone #: ###-#### >> Inspection requested via web by BECCA DUMMER Inspection cancelled from web by: BECCA DUMMER
|