Permit Information
Permit NumberPLM18-03662
StatusFinaled
Name ALTA CONSTRUCTION
Site Address 2419 W FAIRVIEW AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
New: Water/Sewer Site utilities and Storm drain
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Storm Drains7/19/20197/22/20197/22/2019PPASS
DetailsDaryl Spivey
Tyler Adams Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
DOC - Permit Finaled7/22/20197/22/20197/22/2019PPASS
DetailsDaryl Spivey
Water and/or Sewer5/16/20195/17/20195/17/2019APART
DetailsMatt Wrobel
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
water service street to bldg ok to bury thrust blocks and tracer wire
Water and/or Sewer11/1/201811/2/201811/2/2018APASS
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
DOC - Permit Finaled11/2/201811/2/201811/2/2018PPASS
DetailsDaryl Spivey
Water and/or Sewer10/23/201810/24/201810/24/2018APART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum

24 hr test on G/I. ok........ds
Water and/or Sewer10/22/201810/23/201810/23/2018PPART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
G/I plumbing and start 24 hr test......ds
Water and/or Sewer10/22/201810/22/201810/22/2018PPART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
Water and/or Sewer10/1/201810/2/201810/2/2018PPART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
new sewer line for blding across 24th street to east. Boise Rescue Mission warehouse.........tested ok..........ds
Water and/or Sewer9/27/20189/27/20189/27/2018PPASS
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
DOC - Permit Finaled9/27/20189/27/20189/27/2018PPASS
DetailsDaryl Spivey
Water and/or Sewer9/19/20189/20/20189/20/2018APASS
DetailsDaryl Spivey
24 hr test on flammable int......
Water and/or Sewer9/18/20189/19/20189/19/2018APART
DetailsDaryl Spivey
Inspection requested via web by Katherine Creekbaum
start 24 hr test...........ds
Water and/or Sewer9/13/20189/17/20189/17/2018ACANC
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
Other9/17/20189/17/20189/17/2018APASS
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
conference on flammable interceptor piping........ds
Storm Drains9/10/20189/11/20189/11/2018APASS
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
west side tested ok..........ds
Storm Drains9/6/20189/7/20189/7/2018PPART
DetailsBill VanDegrift
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum storm drains east building mains ok
Water and/or Sewer8/28/20188/29/20188/29/2018APART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
waste tested to manhole..........ds
Water and/or Sewer8/27/20188/28/20188/28/2018APART
DetailsDaryl Spivey
Phone #: ###-#### Inspection requested via web by Katherine Creekbaum
marked on plan