Final | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Daryl Spivey
|
|
|
Good morning Daryl. I will have this ready to go at 1 if that works for you thank you. Phone #: ###-#### Inspection requested via web by Brian Watson
|
Plumbing Rough-in | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | PASS |
Daryl Spivey
|
|
|
Daryl, I will have this ready for you at 830 if that works. Phone #: ###-#### Inspection requested via web by Brian Watson piping to ejector and water tie in to main tested ok...........ds
|
Plumbing Rough-in | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | PASS |
Daryl Spivey
|
|
|
Daryl I will have this ready at 1 for you thanks. rough-in on bar wall. Phone #: ###-#### Inspection requested via web by Brian Watson
|
Plumbing Rough-in | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | PART |
Daryl Spivey
|
|
|
Daryl I will have this ready for you at 11:30 if that works. Thank you Phone #: ###-#### Inspection requested via web by Brian Watson ok to cover areas except bar......not framed yet........ds
|