Final | 9/19/2019 | 9/20/2019 | 9/20/2019 | A | PASS |
Matt Wrobel
|
|
|
Originally planned for afternoon inspection on 9/19 Phone #: ###-#### Inspection requested via web by Mark Fischer
|
Plumbing Rough-in | 6/18/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Matt Wrobel
|
|
|
Inspect rough-in plumbing. If possible please come to the house later in the afternoon around 4pm. Please call Mark Stevens at ###-#### 30 mins before arriving if possible. Inspection requested via web by Mark Fischer
|
Groundwork | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Matt Wrobel
|
|
|
Check groundwork - Need the OK to Cover for concrete Phone #: ###-#### Inspection requested via web by Mark Fischer
|
Groundwork | 4/4/2019 | 4/5/2019 | 4/5/2019 | P | PART |
Matt Wrobel
|
|
|
A new pre-inspection inspection prior to gluing all of the drain system. Made all of the needed updates to the system. If possible to have the time for inspection between 1-3pm again. Phone #: ###-#### Inspection requested via web by Mark Fischer
|
Plumbing Rough-in | 4/1/2019 | 4/2/2019 | 4/2/2019 | P | NR |
Matt Wrobel
|
|
|
The house will not be open. I have a window between 1-3pm that I can leave work to meet with the inspector. If he can please call me when he is 15min away from going to the house I can make it from Micron. This is a pre-inspection inspection. I have all of the plumbing roughed-in and the drain/venting system setup but not glued. I wanted to run through it with the inspector to make sure I haven''t missed any items or I need to make changes before gluing. Phone #: ###-#### Inspection requested via web by Mark Fischer
|