Final | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Matt Wrobel
|
|
|
|
Final | 8/6/2019 | 8/7/2019 | 8/7/2019 | A | CANC |
Matt Wrobel
|
|
|
Please call when on the way. Thank you. Phone #: ###-#### Inspection requested via web by Jennifer Alcala
|
Water and/or Sewer | 8/1/2019 | 8/2/2019 | 8/2/2019 | P | PART |
Matt Wrobel
|
|
|
Please call Johnny when on the way ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jennifer Alcala water service ok to cover entire length
|
Water and/or Sewer | 7/31/2019 | 8/2/2019 | 8/1/2019 | A | CANC |
Matt Wrobel
|
|
|
Please call Johnny when on the way ###-####. Thank you, Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala Inspection cancelled from web by: Jennifer Alcala
|
Final | 7/24/2019 | 7/24/2019 | 7/24/2019 | P | PART |
Matt Wrobel
|
|
|
Final ready for boys and girls bathroom. Please call Johnny when on the way ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Jennifer Alcala bathrooms pass 7-24
|
Final | 7/23/2019 | 7/24/2019 | 7/24/2019 | A | CANC |
Matt Wrobel
|
|
|
Final inspection for the boys and girls bathrooms. Please call Johnny when on the way ###-####. Thank you, Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala Inspection cancelled from web by: Jennifer Alcala
|
Plumbing Rough-in | 7/2/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Matt Wrobel
|
|
|
Please call Johnny with questions ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jennifer Alcala
|
Other | 6/11/2019 | 6/18/2019 | 6/18/2019 | A | PART |
Matt Wrobel
|
|
|
Please call Brian when on the way ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jennifer Alcala consult
|
Other | 6/11/2019 | 6/12/2019 | 6/11/2019 | A | CANC |
Matt Wrobel
|
|
|
Conference: Please call Brian ###-#### when on the way. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala Inspection cancelled from web by: Jennifer Alcala
|