Final | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero
|
Final | 6/23/2020 | 6/24/2020 | 6/24/2020 | P | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero 1st floor ok........ds
|
PLM-Aging Inspection | 6/18/2020 | 6/18/2020 | 6/18/2020 | | PASS |
Daryl Spivey
|
|
|
wip
|
Plumbing Rough-in | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero R/D's W/V and water tested ok......rough in done........ds
|
Plumbing Rough-in | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PART |
Daryl Spivey
|
|
|
water test ok..........need some more straps.......ds
|
Pressure Test | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | CANC |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero
|
Plumbing Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero W/V on west side tested ok...........ds
|
Plumbing Rough-in | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | CANC |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero rescheduled for 1/22 am
|
Plumbing Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PART |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero W/V on east side tested ok........ds
|
Groundwork | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Daryl Spivey
|
|
|
Can it be the last inspection for you
Thanks Phone #: ###-#### Inspection requested via web by julio sagrero
|
Water and/or Sewer | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Daryl Spivey
|
|
|
Only main water for the building Phone #: ###-#### Inspection requested via web by julio sagrero
|
Water and/or Sewer | 9/24/2019 | 9/25/2019 | 9/25/2019 | P | NR |
Daryl Spivey
|
|
|
Main water Phone #: ###-#### Inspection requested via web by julio sagrero
|
Groundwork | 9/19/2019 | 9/20/2019 | 9/20/2019 | A | PASS |
Daryl Spivey
|
|
|
Inspection requested via web by julio sagrero
|
Groundwork | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | NR |
Daryl Spivey
|
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero mostly a consult...........ds
|