Final | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Eric Strole
|
|
|
lock box code 1976 or 1967 cant remember Phone #: ###-#### Inspection requested via web by Jeffrey Hankins
|
Plumbing Rough-in | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Matt Wrobel
|
|
|
box code 1967 Phone #: ###-#### Inspection requested via web by Jeffrey Hankins all items addressed rough pass ok to cover
|
Plumbing Rough-in | 10/22/2019 | 10/23/2019 | 10/23/2019 | P | FAIL |
Dan Ediger
|
|
|
call jeff with any questions Phone #: ###-#### Inspection requested via web by Jeffrey Hankins 1. Hard pipe the t&p. Must remove the flex. 2. Install a shut-off valve on the cold side of the water heater. 3. Pex pipe cannot be installed within 18" of the water heater. 4. Must use a shielded band on the dwv within the building.
|