(F) Reprint permit | | | 7/18/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/18/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 3/12/2002 | | DONE |
|
|
|
Letter of Compliance #22306 issued 3-12-02.
|
BLD-Final | 3/11/2002 | 3/11/2002 | 3/11/2002 | P | PASS |
Jim Storey
|
|
|
final ok 3/11/2002 3:02:04 PM
|
Fee Review-notes | 7/11/2000 | 7/11/2000 | 1/30/2002 | | DONE |
|
|
|
|
Temporary occupancy | | | 12/26/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4690 issued 12-26-01 to Micron Technology, Inc.
|
BLD-Final | 11/10/2001 | 11/10/2001 | 11/10/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by Inspector: 301 On 11/10/2001 8:32:31 AM final ok upon special insp. for cat walk for out standing special insp. defecinaces/ pending plm sign off for perm oc. 11/10/2001 10:17:00 AM
|
FIRE-Final Inspection | 11/13/2001 | 11/10/2001 | 11/10/2001 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/13/2001 7:25:42 AM okay to occupy bldg 24D only
|
(F) Reprint permit | | | 10/31/2001 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 10/21/2001 | | DONE |
|
|
|
FINAL SIGNED OFF, WILL HOLD LAST BUILDING IF ALL CONDITIONS OF DR NOT MET.
|
(F) Reprint permit | | | 8/3/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/22/2000 | | DONE |
|
|
|
Received two copies of drawings S3.4, S4.5, A2.2.1, A2.6.10, S2.1.6, A2.1.6, A2.4.2, A2.4.4, A6.2, A6.6. Routed to Jim Storey. KMM
|
(F) Reprint permit | | | 10/16/2000 | | DONE |
|
|
|
|
Routing Off Site - A.C.H.D | 10/13/2000 | 10/13/2000 | 10/13/2000 | | DONE |
|
|
|
okay'd by Penelopie at ACHD per Amanda
|
Issue & PRINT permit | | | 10/13/2000 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 7/14/2000 | | 10/11/2000 | | PASS |
John Menard
|
|
|
10/11/00 08:36:55 JCM - activity updated through activity BLDA022 from case BLD00-01988.
|
Routing - PLAN CHECK | 9/8/2000 | | 10/11/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/11/2000 | | DONE |
|
|
|
e-mailed and told to bring in ACHD certificate
|
Routing Off Site - STRUCTURAL | 9/22/2000 | | 10/10/2000 | | PASS |
|
|
|
SENT PLANS TO CONSULTANTING ENGINEER VIA PDQ. 9/22/00 DAR
RECEIVED AND E-MAIL FROM THE CONSULTING ENGINEER APPROVING THE RESUBMITTALS. JCM
|
Plan Reviewer's activity | | | 10/10/2000 | | PASS |
|
|
|
REVIEWED AND APPROVED RESUBMITTALS WITH ADDED REDLINES AND ATTACHED UPDATED PLAN REVIEW COMMENT LIST. JCM
|
Plan resubmittals received | | | 9/15/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ER+HDR, BOB BOWEN THREE SETS OF SHEETS A2.2.5,A6.2, . 9/15/00 DAR
|
Plan resubmittals received | | | 9/14/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ER+HDR FROM MICRON , 3 SETS OF STRUCTURAL DRAWINGS, FORWARDED SAME TO JOHN MENARD. 9/14/00 DAR
|
Plan resubmittals requested | | | 9/11/2000 | | |
|
|
|
MAILED BOB BOWEN AT ER+HDR A LETTER REQUESTING ADDITIONAL REVISIONS. I ALSO E-MAILED FRANK KVAPIL AT MICRON WITH AN ATTACHED COPY OF THE LETTER. JCM
|
Routing - PUBLIC WORKS | 8/31/2000 | | 9/7/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/5/2000 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/5/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BOB BOWEN, ER+HDR, 3 SETS OF A SHEETS, S SHEETS, P SHEETS, FORWARDED SAME TO JOHN MENARD. 9/5/00 DAR
|
Routing - PLAN CHECK | 8/18/2000 | | 8/31/2000 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/14/2000 | | 8/22/2000 | | FAIL |
|
|
|
SENT REVISED PLANS AND FAXED RESUBMITTALS TO THE CONSULTING STRUCTURAL ENGINEER. JCM RECEIVED ADDITIONAL REVIEW COMMENTS FROM THE CONSULTING STRUCTURAL ENGINEER. JCM
|
Plan resubmittals requested | | | 8/22/2000 | | |
|
|
|
FAXED FRANK KVAPIL AT MICRON A COPY OF THE COMMENT LIST FROM THE CONSULTING ENGINEER ON THE FIRST RESUBMITTALS, ADDITIONAL REVISIONS ARE REQUIRED. JCM
|
Routing - FIRE | 8/15/2000 | 8/18/2000 | 8/18/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 8/18/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 8/15/2000 | | |
|
|
|
MAILED THE ARCHITECT OFRECORD A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
|
Routing - PLAN CHECK | 7/28/2000 | | 8/15/2000 | | |
|
|
|
|
Plan resubmittals received | | | 8/11/2000 | | |
|
|
|
received review stru drawing for hdr. cover letter response letter comments -8/11/2000 pe
|
Plan resubmittals requested | | | 8/7/2000 | | |
|
|
|
FAXED FRANK KVAPIL A COPY OF THE COMMENT LIST FROM THE CONSULTING ENGINEER REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 7/17/2000 | | 8/7/2000 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM RECEIVED AN E-MAIL FROM THE CONSULTING ENGINEER INDICATING THAT REVISIONS WOULD BE REQUIRED.
|
Routing - PLAN CHECK | 7/25/2000 | | 7/26/2000 | | |
|
|
|
|
Routing - PLUMBING | 7/26/2000 | | 7/26/2000 | | PASS |
|
|
|
this is for roof drainage system and services from just inside the building to 5' exterior per plans and 97 upc
|
Routing - PLUMBING | 7/19/2000 | | 7/25/2000 | | FAIL |
|
|
|
please provide a complete set of plumbing plans for review, s.w.v., system sizes and location, potable water system size and location, and all chemical and industrial waste systems associated with this project.
|
Received Certificate of Value | | | 7/19/2000 | | DONE |
|
|
|
RECEIVED REVISED CERT. OF VALUE * PROJECT VALUE $1,549,026 ELECT. $100,000 PLUMB. $164,650 MECH. AND FIRE SPRINKLER N/A. KMM
|
Routing - PLANNING | 7/17/2000 | | 7/19/2000 | | PASS |
|
|
|
Approve per DRH00-72
|
Plan routing begun/NEW & ADDTN | | | 7/17/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/17/2000 | | 7/17/2000 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN APPROVAL PER BRIAN M. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 7/14/2000 | | PEND |
|
|
|
|
Received Certificate of Value | | | 7/12/2000 | | PEND |
|
|
|
REQUIRES PLUMB. VALUE. CONTACTED FRANK OF THIS NEED. KMM
|
Application received | | | 7/11/2000 | | |
|
|
|
|