BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final - approved/L.C.
|
Letter of compliance | | | 6/13/2002 | | DONE |
|
|
|
Letter of Compliance #22537 issued 6-13-02.
|
Temporary occupancy | | | 1/30/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4713 issued 1-30-02 to the Renaissance @ Liberty Lake Apts. parking garage.
|
FIRE-Final Inspection | 12/7/2001 | 12/10/2001 | 12/10/2001 | A | PASS |
Troy Cobbley
|
|
|
Life/safety finaled. Curb painting and signage will be done at project completion 12/10/2001 8:50:48 AM
|
BLD-Final | 12/7/2001 | 12/10/2001 | 12/10/2001 | P | PART |
Tom Arcoraci
|
|
|
###-#### jeff ok for temp 12/10/2001 12:50:33 PM
|
BLD-Final | 11/19/2001 | 11/20/2001 | 11/20/2001 | A | NR |
Tom Arcoraci
|
|
|
fn mick-- ###-#### will recall when card is signed by others 11/20/2001 10:10:08 AM
|
Print Occupancy Form | | | 10/10/2001 | | DONE |
|
|
|
|
BLD-Wall cover | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 09:23:58. Contact: ###-####.
|
BLD-Aging Inspection | 9/14/2001 | 9/14/2001 | 9/14/2001 | | PART |
Tom Arcoraci
|
|
|
wip 9/16/2001 10:00:50 PM
|
BLD-Footing | 7/11/2001 | 7/12/2001 | 7/12/2001 | A | PASS |
Tom Arcoraci
|
|
|
John ###-#### slab
|
BLD-Footing | 5/24/2001 | 5/25/2001 | 5/25/2001 | A | PASS |
Dave Hannah
|
|
|
larry ###-####
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:41:07 CJW - activity updated through activity BLDA022 from case BLD00-03080.
|
Plan Reviewer's activity | | | 2/24/2001 | | PASS |
|
|
|
Approved after resubmittal review.
|
Routing - FIRE | 2/14/2001 | 2/20/2001 | 2/21/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/23/2000 | 10/23/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Reviewer's activity | | | 10/14/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started October 14, 2000 and finished October 16, 2000. A response from the architect was required. See the conditions list.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Plan Reviewer's activity | | | | | |
|
|
|
See permit BLD00-02250 for routing information.
|