Fee Review-notes | 12/15/2000 | 12/15/2000 | 11/9/2001 | | DONE |
|
|
|
|
BLD-Final | 7/12/2001 | 7/13/2001 | 7/13/2001 | A | PASS |
Carl Dependahl
|
|
|
###-####
|
Permanent Occupancy | | 7/13/2001 | 7/13/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/13/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8761 issued 7-13-01 to United Way of Treasure Valley.
|
BLD-Aging Inspection | 6/18/2001 | 6/18/2001 | 6/18/2001 | | PASS |
Carl Dependahl
|
|
|
need all shell items 6/18/2001 9:16:12 AM
|
BLD-Final | 4/16/2001 | 4/16/2001 | 4/16/2001 | P | NR |
Carl Dependahl
|
|
|
###-####, need shell finalled prior to c/o...may extend temp if need 1 time 4/16/2001 3:25:45 PM
|
BLD-Final | 3/13/2001 | 3/13/2001 | 3/13/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####, complete draft stops; ok for t/o 3/13/2001 6:19:25 PM
|
FIRE-Final Inspection | 3/13/2001 | 3/13/2001 | 3/13/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/13/2001 11:53:16 AM
|
FIRE-Final Inspection | 3/12/2001 | 3/12/2001 | 3/12/2001 | A | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/12/2001 8:23:44 AM need sprinkler plans
|
BLD-Conference | 3/8/2001 | 3/8/2001 | 3/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/8/2001 9:21:20 AM need 1hr ext wall at east; complete gyp at 1hr stairs
|
BLD-Conference | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PASS |
Carl Dependahl
|
|
|
571--0990...c/n re gyp at 1hr stairs 3/6/2001 4:06:48 PM
|
BLD-Final | 3/5/2001 | 3/5/2001 | 3/5/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####, not final 3/5/2001 6:04:42 PM
|
BLD-Framing/Rough-in | 3/5/2001 | 3/5/2001 | 3/5/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/5/2001 6:06:07 PM part, ok to tile perimeters, pend other insps. Add seismic braces as needed at all rooms over 144 sf.
|
BLD-Framing/Rough-in | 2/23/2001 | 2/23/2001 | 2/23/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/23/2001 11:16:19 AM KEEP C/N...COMPLETE DRAFT STOP PER DISCUSSION
|
BLD-Conference | 2/21/2001 | 2/21/2001 | 2/21/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/21/2001 4:46:19 PM need seal draft stop
|
BLD-Conference | 1/29/2001 | 1/29/2001 | 1/29/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 09:33:28. Contact: ###-####. w/ arch & contractors...re c/n. add draft stop, complete gyp at stairs 1/29/2001 3:59:43 PM
|
BLD-Framing/Rough-in | 1/25/2001 | 1/25/2001 | 1/25/2001 | P | FAIL |
Carl Dependahl
|
|
|
united way 1st floor carl ###-#### & tom-- ###-####, c/n fireblocks, draft stops at floor clg; ok to cover steel stud framing only. need complete gyp at stairs. 1/25/2001 4:16:09 PM
|
Issue PAID IN FULL permit | | | 1/16/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 12/19/2000 | | 1/11/2001 | | PASS |
Mike Phillips
|
|
|
1/11/2001 10:05:14 MYS - activity updated through activity BLDA022 from case BLD00-03639.
|
Routing - PLAN CHECK | 1/10/2001 | | 1/11/2001 | | PASS |
|
|
|
Signed on behalf of Mike Philllips and took to permit desk for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2001 | | DONE |
|
|
|
Issued on behalf of Mike Phillips.
|
Inspection Record Card- Bld | | | 1/11/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/11/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2001 | | DONE |
|
|
|
|
Routing - FIRE | | | 1/10/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/10/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/5/2001 | | PEND |
|
|
|
Waiting for others to approved prior to issuance of permit.
|
Routing - PLAN CHECK | 12/20/2000 | | 1/5/2001 | | PEND |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 1/4/2001 | | DONE |
|
|
|
Plan resubmittals received from Tamura and associates, two sets of A-2.0, A-6.0, A-7.0 and A-10.0, forwarded same to Mike Phillips 1/4/01 DAR
|
Routing - PUBLIC WORKS | 12/19/2000 | | 12/20/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 12/19/2000 | | 12/19/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/15/2000 | | DONE |
|
|
|
|
Application received | | | 12/15/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/15/2000 | | DONE |
|
|
|
|