Fee Review-notes | 3/23/2001 | 3/23/2001 | 8/21/2002 | | DONE |
|
|
|
|
BLD-Final | 8/16/2002 | 8/16/2002 | 8/16/2002 | | DONE |
|
|
|
Final - approved for perm. occ. per Russ Owen
|
Permanent occupancy UNPAID FEE | | | 8/16/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9300 issued 8-16-02 to the Hilton Garden Inn, sec. 3 of 3 east section.
|
Permanent Occupancy | | 8/15/2002 | 8/15/2002 | | DONE |
|
|
|
|
BLD-Final | 8/15/2002 | 8/15/2002 | 8/15/2002 | P | PART |
Russ Owen
|
|
|
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
FIRE-Final Inspection | 8/12/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
BLD-Final | 6/25/2002 | 6/25/2002 | 6/25/2002 | P | PART |
Russ Owen
|
|
|
Grid ceiling in conference room. 6/25/2002 3:23:19 PM
|
BLD-Final | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Russ Owen
|
|
|
ok for a temporary oc pending fire/life safety, has pending corrections for a permanent oc. 6/18/2002 5:08:25 PM
|
FIRE-Final Inspection | 6/18/2002 | 6/18/2002 | 6/18/2002 | P | PART |
Troy Cobbley
|
|
|
Fire alarm and fire life/safety finaled. Fire sprinkler given temp for the window sprinklers per Dave Miller.
|
Temporary occupancy | | | 6/18/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4830 issued 6-18-02 to the Hilton Garden Inn, east section.
|
BLD-Final | 6/14/2002 | 6/17/2002 | 6/17/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 6/14/2002 10:29:54 AM c/n posted. 6/14/2002 4:42:18 PM
|
| | | 6/14/2002 | | DONE |
Rita DeYoung
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
| | | 6/14/2002 | | DONE |
Rita DeYoung
|
|
|
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
|
BLD-Framing/Rough-in | 3/29/2002 | 3/29/2002 | 3/29/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/29/2002 12:03:22 PM
|
BLD-Framing/Rough-in | 3/18/2002 | 3/18/2002 | 3/18/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/18/2002 12:12:01 PM
|
BLD-Framing/Rough-in | 3/6/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/6/2002 4:21:01 PM Ok to insulate mechanical room. Note(2) 1hr walls will be fured out as to accomodate electrical panels. 3/7/2002 12:07:07 PM
|
BLD-Framing/Rough-in | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/6/2002 4:17:58 PM ok to drywall 2nd floor. 3/6/2002 4:20:13 PM
|
BLD-Framing/Rough-in | 3/1/2002 | 3/1/2002 | 3/1/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/1/2002 10:38:51 AM
|
BLD-Framing/Rough-in | 2/28/2002 | 2/28/2002 | 2/28/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/28/2002 4:00:33 PM
|
BLD-Framing/Rough-in | 2/22/2002 | 2/22/2002 | 2/22/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/22/2002 4:42:15 PM see notes under 01-00736. 2/22/2002 4:50:29 PM
|
BLD-Framing/Rough-in | 2/20/2002 | 2/20/2002 | 2/20/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/20/2002 3:22:41 PM Ok to complete insulation at second floor. 2/20/2002 3:26:01 PM
|
BLD-Framing/Rough-in | 2/19/2002 | 2/19/2002 | 2/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/19/2002 2:42:18 PM
|
BLD-Framing/Rough-in | 2/15/2002 | 2/15/2002 | 2/15/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/15/2002 11:26:50 AM Need to complete all fire stoping west of the first 2hr wall. 2/15/2002 11:32:12 AM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/14/2002 | 2/14/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/14/2002 4:54:36 PM
|
BLD-Framing/Rough-in | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/13/2002 3:48:54 PM
|
BLD-Framing/Rough-in | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | NR |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/12/2002 12:13:18 PM See bld01-00737 for notes. 2/12/2002 4:21:45 PM
|
BLD-Framing/Rough-in | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/8/2002 11:19:48 AM see notes under 01-00736. 2/8/2002 4:14:19 PM
|
BLD-Framing/Rough-in | 2/7/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/7/2002 8:09:11 AM See note on bld01-00737 for comments this day. 2/7/2002 4:57:20 PM
|
BLD-Framing/Rough-in | 2/5/2002 | 2/5/2002 | 2/5/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/5/2002 4:27:55 PM see bld01-00729 2/5/2002 4:31:53 PM
|
BLD-Conference | 2/4/2002 | 2/4/2002 | 2/4/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 2/4/2002 12:11:13 PM seee notes under 01-00736. 2/4/2002 1:01:13 PM
|
BLD-Conference | 2/1/2002 | 2/1/2002 | 2/1/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 408 On 2/1/2002 11:38:09 AM. This day I posted another c/n for the same items as yester day. IE: shear nailing not done ,2 hr wall corrections not, done,st 22 strap, misc, fire caulking. Note at this time work has rapidly been progressing. 2/1/2002 6:00:15 PM
|
BLD-Framing/Rough-in | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PART |
Russ Owen
|
|
|
rich- ###-#### fr insp Posted a c/nat the site. 1/31/2002 2:07:59 PM
|
BLD-Framing/Rough-in | 1/28/2002 | 1/29/2002 | 1/29/2002 | P | PART |
Russ Owen
|
|
|
###-#### fourth floor walls ok to insulate except for 2 hr area sep walls and electrical room. 1/30/2002 9:15:07 AM
|
BLD-Framing/Rough-in | 1/25/2002 | 1/28/2002 | 1/28/2002 | A | PART |
Russ Owen
|
|
|
###-#### n 1/28/2002 11:06:36 AM Went over roof trusses at 4 th floor there are correction to be made .a. w 1/28/2002 1:23:23 PM
|
BLD-Framing/Rough-in | 1/25/2002 | 1/25/2002 | 1/25/2002 | P | PART |
Russ Owen
|
|
|
###-#### ok to insulate upper floor dividing walls except for 2 hr area sep walls. amlmmmm 1/25/2002 4:52:08 PM
|
BLD-Framing/Rough-in | 1/18/2002 | 1/22/2002 | 1/22/2002 | A | PART |
Russ Owen
|
|
|
###-####. need to clairify mbr connection to steel beam and interior shear wall nailing. 1/22/2002 4:25:49 PM
|
BLD-Framing/Rough-in | 1/11/2002 | 1/11/2002 | 1/11/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/11/2002 12:02:26 PM Ok to insulate east side interior walls between rooms only first and second floors only,as to have shear walls applied after insulation. 1/11/2002 12:07:31 PM
|
BLD-Conference | 1/9/2002 | 1/10/2002 | 1/10/2002 | A | PART |
Russ Owen
|
|
|
###-####.Went over fire stoping with cont and hilti rep. 1/10/2002 11:20:20 AM
|
BLD-Framing/Rough-in | 1/7/2002 | 1/8/2002 | 1/8/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/7/2002 6:05:41 PM . need new details for penetrations . 1/8/2002 12:00:33 PM
|
BLD-Framing/Rough-in | 1/7/2002 | 1/7/2002 | 1/7/2002 | P | PART |
Russ Owen
|
|
|
###-#### 3 floor shear behind tubs east of 2 hr area sep wall. 1/7/2002 6:02:53 PM
|
BLD-Framing/Rough-in | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | PART |
Russ Owen
|
|
|
###-#### . Informed contractor that all floor ceiling assemblies are required to be fire stoped at the top plates and florr line ,plumbing ele and conduit etc to maintain 1 hr fire resistive construction. bettween floors. no c/n posted. They will contact rep for product used and recall when ready. 1/3/2002 5:18:00 PM 1/4/2002 4:47:54 PM
|
BLD-Framing/Rough-in | 12/19/2001 | 12/20/2001 | 12/20/2001 | A | PART |
Russ Owen
|
|
|
###-#### RICH. 12/20/2001 4:55:01 PM. 12/20/2001 4:55:38 PMc/n posted. 12/20/2001 4:57:01 PM
|
BLD-Framing/Rough-in | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | PART |
Russ Owen
|
|
|
rich ###-####
|
BLD-Framing/Rough-in | 12/14/2001 | 12/14/2001 | 12/14/2001 | P | PART |
Russ Owen
|
|
|
RICH ###-####. lower floor top half of east corridor. 12/14/2001 3:47:30 PM
|
BLD-Conference | 12/6/2001 | 12/6/2001 | 12/6/2001 | P | PART |
Russ Owen
|
|
|
###-####. went over penetration with electrician, also hds have now been placed in walls at east stair tower. 12/7/2001 11:11:43 AM
|
BLD-Framing/Rough-in | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 15:42:23. Contact: . shear ok north and south 1-3 floors east side and 1-3 floors north west side 11/21/2001 10:25:39 AM 11/21/2001 10:26:25 AM
|
BLD-Framing/Rough-in | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | CANC |
Tom Arcoraci
|
|
|
###-#### CLAY SHEER NAIL will recall for am 11/20/2001 3:24:54 PM
|
Plan Reviewer's activity | | | 11/7/2001 | | |
|
|
|
Architect replaced. New architect is Russell Colburn
|
BLD-Framing/Rough-in | 10/24/2001 | 10/24/2001 | 10/24/2001 | P | FAIL |
Russ Owen
|
|
|
###-#### RICH INTERIOR & EXTERIOR SHEER NAIL . Need more info on MBR hold down req for studs. c/n. 10/24/2001 3:51:31 PM
|
BLD-Framing/Rough-in | 10/19/2001 | 10/19/2001 | 10/19/2001 | P | PART |
Russ Owen
|
|
|
SHEER NAIL ###-#### RICH NEW ADDRESS OF 7699 W SPECTRUM STREET. needs to add 2nd row of nailing at the hold downs system. 10/19/2001 3:55:03 PM
|
Override - Parcel Holds | | | 10/19/2001 | | DONE |
Darla L Downs
|
|
|
Parcel Tag Notes: AS PER APRIL MILLER ADDRESS CHANGE FROM 7651 W SPECTRUM ST TO THE NEW ADDRESS OF:7699 W SPECTRUM STREET. PLEASE LET CONTRACTORS KNOW. 8/7/01-MPS
|
Case Summary (BLD) | | | 9/25/2001 | | |
|
|
|
|
BLD-Framing/Rough-in | 8/30/2001 | 8/31/2001 | 8/31/2001 | A | PART |
Russ Owen
|
|
|
###-####. looked at some interior upper section of wall shear panels only. 8/31/2001 12:30:09 PM
|
BLD-Conference | 8/3/2001 | 8/6/2001 | 8/6/2001 | A | PART |
Russ Owen
|
|
|
###-####. 2hr stair enclosure, question reg, beam into walls. pending more info. 8/6/2001 4:46:30 PM
|
BLD-Foundation | 7/9/2001 | 7/9/2001 | 7/9/2001 | P | PART |
Russ Owen
|
|
|
Rich ###-####s-i pending. 7/10/2001 11:59:50 AM
|
BLD-Foundation | 7/5/2001 | 7/5/2001 | 7/5/2001 | P | PART |
Russ Owen
|
|
|
###-####subject to s-i. 7/5/2001 3:25:19 PM
|
BLD-Footing | 6/28/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Russ Owen
|
|
|
pouring at 1:30 clay ###-####
|
BLD-Foundation | 6/28/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Russ Owen
|
|
|
clay pouring at1:30 ###-####
|
BLD-Footing | 6/26/2001 | 6/26/2001 | 6/26/2001 | P | PART |
Russ Owen
|
|
|
pouring at 2:00 Clay ###-####
|
(F) Reprint permit | | | 6/26/2001 | | DONE |
|
|
|
|
BLD-Footing | 6/25/2001 | 6/25/2001 | 6/25/2001 | P | PART |
Russ Owen
|
|
|
pour at 2:30 ###-#### 100 foot of rear east. 6/25/2001 4:16:20 PM
|
Routing - PLAN CHECK | 6/22/2001 | | 6/25/2001 | | DONE |
|
|
|
preparing for issuance. KMM
|
Print Occupancy Form | | | 6/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/25/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/25/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/25/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/25/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/25/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/23/2001 | | 6/25/2001 | | PASS |
Mike Phillips
|
|
|
6/25/2001 09:00:52 M_P - activity updated through activity BLDA022 from case BLD01-00737.
|
Routing - PUBLIC WORKS | 6/21/2001 | | 6/22/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/18/2001 | | 6/21/2001 | | DONE |
|
|
|
contacted pdq to take revised plans to outside eng.
|
Routing - PLAN CHECK | 5/18/2001 | | 6/21/2001 | | PEND |
|
|
|
Routing to P.W. and Plumbing.
|
Plan Reviewer's activity | | | 6/21/2001 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing - PLANNING | 6/1/2001 | | 6/5/2001 | | PASS |
|
|
|
Approved per DRH01-17.
|
Routing - PLUMBING | 5/25/2001 | | 5/25/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2001 | | 5/18/2001 | | FAIL |
|
|
|
Same as before. 5/18/01 DAR
|
Routing - PLAN CHECK | 5/11/2001 | | 5/18/2001 | | |
|
|
|
|
Routing - FIRE | 5/11/2001 | | 5/11/2001 | | PASS |
|
|
|
|
Routing - FIRE | 4/23/2001 | | 4/26/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/23/2001 | | 4/23/2001 | | FAIL |
|
|
|
contacted pdq to take plans out to outside eng.
|
Plan Reviewer's activity | | | 4/23/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing - PLAN CHECK | 4/16/2001 | | 4/23/2001 | | FAIL |
|
|
|
Routing to fire.
|
Routing - PLUMBING | 4/12/2001 | | 4/16/2001 | | FAIL |
|
|
|
|
Routing - PLANNING | 4/4/2001 | | 4/9/2001 | | PEND |
|
|
|
Ok for conditional use per Susan Riggs. Design Review conditions have not been met.
|
Routing - PUBLIC WORKS | 3/23/2001 | | 4/4/2001 | | FAIL |
|
|
|
Requires proof of legal land division per Jim Rich. 4/4/01 DAR
|
Plan routing begun/NEW & ADDTN | | | 3/23/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/23/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 3/23/2001 | | DONE |
|
|
|
|
Pending Assignment by MYS | 3/23/2001 | | 3/23/2001 | | DONE |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/23/2001 | | DONE |
|
|
|
|