Permit Information
Permit NumberBLD01-00737
StatusFinaled
Name HILTON GARDEN INN
Site Address 7699 W SPECTRUM ST
Project NameHILTON GARDEN INN-BLDG C
Customer Number 
ePlanReviewNo
Description
( Section 3 of 3 East Section) * Two, two hour area separation walls will divide this four story, 137 unit hotel into three separate buildings. This section contains 64units. All construction is per the approved plans, attached comment list and CABO/ANSI A117.1. Refer to 01-00729 an 01-00736 for other portions of this building. NOTE: This building if fully fire sprinklered for story increase. CUP01-00009 PC#250-01 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes3/23/20013/23/20018/21/2002 DONE
BLD-Final8/16/20028/16/20028/16/2002 DONE
Final - approved for perm. occ. per Russ Owen
Permanent occupancy UNPAID FEE  8/16/2002 DONE
Perm. Occ. Cert. #9300 issued 8-16-02 to the Hilton Garden Inn, sec. 3 of 3 east section.
Permanent Occupancy 8/15/20028/15/2002 DONE
Details
BLD-Final8/15/20028/15/20028/15/2002PPART
DetailsRuss Owen
FIRE-Final Inspection8/12/20028/12/20028/12/2002APASS
DetailsTroy Cobbley
fire life safety finaled
FIRE-Final Inspection8/12/20028/12/20028/12/2002APASS
DetailsTroy Cobbley
fire life safety finaled
BLD-Final6/25/20026/25/20026/25/2002PPART
DetailsRuss Owen
Grid ceiling in conference room. 6/25/2002 3:23:19 PM
BLD-Final6/18/20026/18/20026/18/2002PPART
DetailsRuss Owen
ok for a temporary oc pending fire/life safety, has pending corrections for a permanent oc. 6/18/2002 5:08:25 PM
FIRE-Final Inspection6/18/20026/18/20026/18/2002PPART
DetailsTroy Cobbley
Fire alarm and fire life/safety finaled. Fire sprinkler given temp for the window sprinklers per Dave Miller.
Temporary occupancy  6/18/2002 DONE
Temp. Occ. Cert. #4830 issued 6-18-02 to the Hilton Garden Inn, east section.
BLD-Final6/14/20026/17/20026/17/2002PCANC
DetailsRuss Owen
###-####
BLD-Final6/14/20026/14/20026/14/2002AFAIL
DetailsRuss Owen
Scheduled by Inspector: 407 On 6/14/2002 10:29:54 AM c/n posted. 6/14/2002 4:42:18 PM
   6/14/2002 DONE
DetailsRita DeYoung
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
   6/14/2002 DONE
DetailsRita DeYoung
Parcel Tag Notes: PLAN MODIFICATION ( BLD01-00729) No inspection for rear of meeting rooms. Elevation change to include roof lantern. May cancel parcel tag when Plan Modification is issued. If any questions please contact Mike Phillips. KMM Reason for OverRide:
BLD-Framing/Rough-in3/29/20023/29/20023/29/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/29/2002 12:03:22 PM
BLD-Framing/Rough-in3/18/20023/18/20023/18/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/18/2002 12:12:01 PM
BLD-Framing/Rough-in3/6/20023/7/20023/7/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/6/2002 4:21:01 PM Ok to insulate mechanical room. Note(2) 1hr walls will be fured out as to accomodate electrical panels. 3/7/2002 12:07:07 PM
BLD-Framing/Rough-in3/6/20023/6/20023/6/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/6/2002 4:17:58 PM ok to drywall 2nd floor. 3/6/2002 4:20:13 PM
BLD-Framing/Rough-in3/1/20023/1/20023/1/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/1/2002 10:38:51 AM
BLD-Framing/Rough-in2/28/20022/28/20022/28/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/28/2002 4:00:33 PM
BLD-Framing/Rough-in2/22/20022/22/20022/22/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/22/2002 4:42:15 PM see notes under 01-00736. 2/22/2002 4:50:29 PM
BLD-Framing/Rough-in2/20/20022/20/20022/20/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/20/2002 3:22:41 PM Ok to complete insulation at second floor. 2/20/2002 3:26:01 PM
BLD-Framing/Rough-in2/19/20022/19/20022/19/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/19/2002 2:42:18 PM
BLD-Framing/Rough-in2/15/20022/15/20022/15/2002AFAIL
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/15/2002 11:26:50 AM Need to complete all fire stoping west of the first 2hr wall. 2/15/2002 11:32:12 AM
BLD-Framing/Rough-in2/14/20022/14/20022/14/2002ACANC
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/14/2002 4:54:36 PM
BLD-Framing/Rough-in2/13/20022/13/20022/13/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/13/2002 3:48:54 PM
BLD-Framing/Rough-in2/12/20022/12/20022/12/2002PNR
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/12/2002 12:13:18 PM See bld01-00737 for notes. 2/12/2002 4:21:45 PM
BLD-Framing/Rough-in2/8/20022/8/20022/8/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/8/2002 11:19:48 AM see notes under 01-00736. 2/8/2002 4:14:19 PM
BLD-Framing/Rough-in2/7/20022/7/20022/7/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/7/2002 8:09:11 AM See note on bld01-00737 for comments this day. 2/7/2002 4:57:20 PM
BLD-Framing/Rough-in2/5/20022/5/20022/5/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/5/2002 4:27:55 PM see bld01-00729 2/5/2002 4:31:53 PM
BLD-Conference2/4/20022/4/20022/4/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 2/4/2002 12:11:13 PM seee notes under 01-00736. 2/4/2002 1:01:13 PM
BLD-Conference2/1/20022/1/20022/1/2002PFAIL
DetailsRuss Owen
Scheduled by Inspector: 408 On 2/1/2002 11:38:09 AM. This day I posted another c/n for the same items as yester day. IE: shear nailing not done ,2 hr wall corrections not, done,st 22 strap, misc, fire caulking. Note at this time work has rapidly been progressing. 2/1/2002 6:00:15 PM
BLD-Framing/Rough-in1/30/20021/30/20021/30/2002PPART
DetailsRuss Owen
rich- ###-#### fr insp Posted a c/nat the site. 1/31/2002 2:07:59 PM
BLD-Framing/Rough-in1/28/20021/29/20021/29/2002PPART
DetailsRuss Owen
###-#### fourth floor walls ok to insulate except for 2 hr area sep walls and electrical room. 1/30/2002 9:15:07 AM
BLD-Framing/Rough-in1/25/20021/28/20021/28/2002APART
DetailsRuss Owen
###-#### n 1/28/2002 11:06:36 AM Went over roof trusses at 4 th floor there are correction to be made .a. w 1/28/2002 1:23:23 PM
BLD-Framing/Rough-in1/25/20021/25/20021/25/2002PPART
DetailsRuss Owen
###-#### ok to insulate upper floor dividing walls except for 2 hr area sep walls. amlmmmm 1/25/2002 4:52:08 PM
BLD-Framing/Rough-in1/18/20021/22/20021/22/2002APART
DetailsRuss Owen
###-####. need to clairify mbr connection to steel beam and interior shear wall nailing. 1/22/2002 4:25:49 PM
BLD-Framing/Rough-in1/11/20021/11/20021/11/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 1/11/2002 12:02:26 PM Ok to insulate east side interior walls between rooms only first and second floors only,as to have shear walls applied after insulation. 1/11/2002 12:07:31 PM
BLD-Conference1/9/20021/10/20021/10/2002APART
DetailsRuss Owen
###-####.Went over fire stoping with cont and hilti rep. 1/10/2002 11:20:20 AM
BLD-Framing/Rough-in1/7/20021/8/20021/8/2002APART
DetailsRuss Owen
Scheduled by Inspector: 407 On 1/7/2002 6:05:41 PM . need new details for penetrations . 1/8/2002 12:00:33 PM
BLD-Framing/Rough-in1/7/20021/7/20021/7/2002PPART
DetailsRuss Owen
###-#### 3 floor shear behind tubs east of 2 hr area sep wall. 1/7/2002 6:02:53 PM
BLD-Framing/Rough-in1/3/20021/3/20021/3/2002PPART
DetailsRuss Owen
###-#### . Informed contractor that all floor ceiling assemblies are required to be fire stoped at the top plates and florr line ,plumbing ele and conduit etc to maintain 1 hr fire resistive construction. bettween floors. no c/n posted. They will contact rep for product used and recall when ready. 1/3/2002 5:18:00 PM 1/4/2002 4:47:54 PM
BLD-Framing/Rough-in12/19/200112/20/200112/20/2001APART
DetailsRuss Owen
###-#### RICH. 12/20/2001 4:55:01 PM. 12/20/2001 4:55:38 PMc/n posted. 12/20/2001 4:57:01 PM
BLD-Framing/Rough-in12/18/200112/18/200112/18/2001PPART
DetailsRuss Owen
rich ###-####
BLD-Framing/Rough-in12/14/200112/14/200112/14/2001PPART
DetailsRuss Owen
RICH ###-####. lower floor top half of east corridor. 12/14/2001 3:47:30 PM
BLD-Conference12/6/200112/6/200112/6/2001PPART
DetailsRuss Owen
###-####. went over penetration with electrician, also hds have now been placed in walls at east stair tower. 12/7/2001 11:11:43 AM
BLD-Framing/Rough-in11/20/200111/21/200111/21/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/20/2001 at 15:42:23. Contact: . shear ok north and south 1-3 floors east side and 1-3 floors north west side 11/21/2001 10:25:39 AM 11/21/2001 10:26:25 AM
BLD-Framing/Rough-in11/20/200111/20/200111/20/2001PCANC
DetailsTom Arcoraci
###-#### CLAY SHEER NAIL will recall for am 11/20/2001 3:24:54 PM
Plan Reviewer's activity  11/7/2001  
Architect replaced. New architect is Russell Colburn
BLD-Framing/Rough-in10/24/200110/24/200110/24/2001PFAIL
DetailsRuss Owen
###-#### RICH INTERIOR & EXTERIOR SHEER NAIL . Need more info on MBR hold down req for studs. c/n. 10/24/2001 3:51:31 PM
BLD-Framing/Rough-in10/19/200110/19/200110/19/2001PPART
DetailsRuss Owen
SHEER NAIL ###-#### RICH NEW ADDRESS OF 7699 W SPECTRUM STREET. needs to add 2nd row of nailing at the hold downs system. 10/19/2001 3:55:03 PM
Override - Parcel Holds  10/19/2001 DONE
DetailsDarla L Downs
Parcel Tag Notes: AS PER APRIL MILLER ADDRESS CHANGE FROM 7651 W SPECTRUM ST TO THE NEW ADDRESS OF:7699 W SPECTRUM STREET. PLEASE LET CONTRACTORS KNOW. 8/7/01-MPS
Case Summary (BLD)  9/25/2001  
BLD-Framing/Rough-in8/30/20018/31/20018/31/2001APART
DetailsRuss Owen
###-####. looked at some interior upper section of wall shear panels only. 8/31/2001 12:30:09 PM
BLD-Conference8/3/20018/6/20018/6/2001APART
DetailsRuss Owen
###-####. 2hr stair enclosure, question reg, beam into walls. pending more info. 8/6/2001 4:46:30 PM
BLD-Foundation7/9/20017/9/20017/9/2001PPART
DetailsRuss Owen
Rich ###-####s-i pending. 7/10/2001 11:59:50 AM
BLD-Foundation7/5/20017/5/20017/5/2001PPART
DetailsRuss Owen
###-####subject to s-i. 7/5/2001 3:25:19 PM
BLD-Footing6/28/20016/28/20016/28/2001PPART
DetailsRuss Owen
pouring at 1:30 clay ###-####
BLD-Foundation6/28/20016/28/20016/28/2001PPART
DetailsRuss Owen
clay pouring at1:30 ###-####
BLD-Footing6/26/20016/26/20016/26/2001PPART
DetailsRuss Owen
pouring at 2:00 Clay ###-####
(F) Reprint permit  6/26/2001 DONE
BLD-Footing6/25/20016/25/20016/25/2001PPART
DetailsRuss Owen
pour at 2:30 ###-#### 100 foot of rear east. 6/25/2001 4:16:20 PM
Routing - PLAN CHECK6/22/2001 6/25/2001 DONE
preparing for issuance. KMM
Print Occupancy Form  6/25/2001 DONE
Inspection Record Card- Bld  6/25/2001 DONE
Plan Reviewer's activity  6/25/2001 PASS
Print Pending Permit.LaserJet4  6/25/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/25/2001 DONE
Case Summary (BLD)  6/25/2001 DONE
Issue PAID IN FULL permit  6/25/2001 DONE
Plan assigned to (M_P)3/23/2001 6/25/2001 PASS
DetailsMike Phillips
6/25/2001 09:00:52 M_P - activity updated through activity BLDA022 from case BLD01-00737.
Routing - PUBLIC WORKS6/21/2001 6/22/2001 PASS
Routing Off Site - STRUCTURAL5/18/2001 6/21/2001 DONE
contacted pdq to take revised plans to outside eng.
Routing - PLAN CHECK5/18/2001 6/21/2001 PEND
Routing to P.W. and Plumbing.
Plan Reviewer's activity  6/21/2001 PEND
Waiting for others to approve prior to issuing permit.
Routing - PLANNING6/1/2001 6/5/2001 PASS
Approved per DRH01-17.
Routing - PLUMBING5/25/2001 5/25/2001 PASS
Routing - PUBLIC WORKS5/18/2001 5/18/2001 FAIL
Same as before. 5/18/01 DAR
Routing - PLAN CHECK5/11/2001 5/18/2001  
Routing - FIRE5/11/2001 5/11/2001 PASS
Routing - FIRE4/23/2001 4/26/2001 PASS
Routing Off Site - STRUCTURAL3/23/2001 4/23/2001 FAIL
contacted pdq to take plans out to outside eng.
Plan Reviewer's activity  4/23/2001 FAIL
Additional information required for further review.
Routing - PLAN CHECK4/16/2001 4/23/2001 FAIL
Routing to fire.
Routing - PLUMBING4/12/2001 4/16/2001 FAIL
Routing - PLANNING4/4/2001 4/9/2001 PEND
Ok for conditional use per Susan Riggs. Design Review conditions have not been met.
Routing - PUBLIC WORKS3/23/2001 4/4/2001 FAIL
Requires proof of legal land division per Jim Rich. 4/4/01 DAR
Plan routing begun/NEW & ADDTN  3/23/2001 DONE
Plans ACCEPTED BY PLAN TECH  3/23/2001 DONE
Received Certificate of Value  3/23/2001 DONE
Pending Assignment by MYS3/23/2001 3/23/2001 DONE
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  3/23/2001 DONE