Fee Review-notes | 7/8/2003 | 7/8/2003 | 7/8/2003 | | DONE |
|
|
|
Additional value from subcontractor.
|
Case Summary (BLD) | | | 3/26/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/18/2003 | | |
|
|
|
|
PubWorks Occupancy Approval | 8/28/2002 | 8/28/2002 | 8/28/2002 | | DONE |
|
|
|
Per B.Murphy 8/28/02, project complete.
|
Case Summary (BLD) | | | 5/23/2002 | | |
|
|
|
|
Fee Review-notes | 5/3/2001 | 5/3/2001 | 1/29/2002 | | DONE |
|
|
|
|
BLD-Final | 7/12/2001 | 7/16/2001 | 7/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 16:55:23. Contact: ###-####. OK FOR PERM OCC 7/15/2001 10:35:53 PM
|
Permanent Occupancy | | 7/16/2001 | 7/16/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/16/2001 | | |
|
|
|
Perm. Occ. Cert. #8765 issued 7-16-01 to Simplot Ind., Inc.
|
FIRE-Final Inspection | 7/12/2001 | 7/13/2001 | 7/13/2001 | P | PASS |
Joe Tawney
|
|
|
Reinsp OK for permanant occupancy 7/13/2001 3:28:09 PM
|
Code Occupancy Approval | | | 7/11/2001 | | PASS |
|
|
|
DRH01-00074 required revised plan to be submitted showing paving/landscaping. Told them they needed to pave a 20' access drive to building after speaking with Tempra WIlson and Paul Krommenhoek. Next day Tempra & Paul discussed with Craig and told him that it did not need to be done. Called both Tempra & Paul and confirmed that they approved as is - even though contrary to cond. #1 of approval.
|
Code Occupancy Approval | | | 7/10/2001 | | FAIL |
|
|
|
Still need to submit plans to DR and provide for paved access to structure.
|
FIRE-Final Inspection | 7/3/2001 | 7/5/2001 | 7/5/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued 7/5/2001 1:18:49 PM
|
Code Occupancy Approval | | | 7/2/2001 | | FAIL |
|
|
|
Inspection failed. Plans NOT submitted for approval to DR Analyst Paul K. and no paved access provided to building.
|
FIRE-Final Inspection | 6/22/2001 | 6/22/2001 | 6/22/2001 | P | CANC |
Rick Jackson
|
|
|
FIRE FN KIRK ###-####
|
BLD-Footing | 6/5/2001 | 6/6/2001 | 6/6/2001 | P | PASS |
Tom Arcoraci
|
|
|
FT INSP KURT ###-####
|
(F) Reprint permit | | | 6/6/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/5/2001 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Issue PAID IN FULL permit | | | 6/5/2001 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 5/4/2001 | | 6/4/2001 | | PASS |
Mike Otto
|
|
|
6/4/2001 14:24:08 MLO - activity updated through activity BLDA022 from case BLD01-01163.
|
Routing Off Site - STRUCTURAL | 5/24/2001 | | 6/4/2001 | | PASS |
|
|
|
Sent resubmittals to consulting structural engineer via PDQ. 5/24/01 DAR
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/30/2001 | | 5/31/2001 | | PASS |
|
|
|
Brian Murphy is ready for plans. 5/29/01 DAR
|
Routing - FIRE | 5/24/2001 | | 5/30/2001 | | PASS |
|
|
|
|
Additional plans submitted | | | 5/24/2001 | | DONE |
|
|
|
Received structural caculations and water flow information from Kurt, Custom steel structures. forwarded same to Mike Otto. 5/24/01 DAR
|
Plan resubmittals requested | | | 5/21/2001 | | FAIL |
|
|
|
STRUCTURAL CORRECTIONS SENT TO ARCHITECT.
|
Routing Off Site - STRUCTURAL | 5/4/2001 | | 5/21/2001 | | FAIL |
|
|
|
Sent plans to structural engineering consultant via PDQ. 5/4/01 DAR
|
Routing - FIRE | 5/11/2001 | 5/15/2001 | 5/14/2001 | | FAIL |
Bill Alexander
|
|
|
Lack hydrant location/s, flows, commodity classification, elevation of storage, type of storage system employing.
|
Plan Review Completed(1st rev) | | | 5/14/2001 | | FAIL |
|
|
|
plans returned to plan review
|
Routing - PLAN CHECK | 5/10/2001 | | 5/11/2001 | | PASS |
|
|
|
ok pending structural review structural approval 6/4/2001
|
Routing - PUBLIC WORKS | 5/4/2001 | | 5/10/2001 | | FAIL |
|
|
|
Needs letter from Dean Briggs - Requires drainage plan. per Brian M. KMM
|
Routing - PLANNING | 5/10/2001 | | 5/10/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/4/2001 | | DONE |
|
|
|
|
Application received | | | 5/3/2001 | | |
|
|
|
|