Fee Review-notes | 7/14/2003 | 7/14/2003 | 7/14/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/15/2002 | 3/15/2002 | | DONE |
|
|
|
|
BLD-Final | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | PASS |
Carl Dependahl
|
|
|
fn occ- jack- ###-#### card to contractor 3/15/2002 9:01:47 AM
|
Permanent occupancy | | | 3/15/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9069 issued 3-15-02 to Turner-McAlvain Construction Office.
|
BLD-Conference | 1/30/2002 | 1/30/2002 | 1/30/2002 | P | PASS |
Carl Dependahl
|
|
|
###-####, w/ bldr re final...need shell c/o for perm. 1/30/2002 5:47:24 PM
|
FIRE-Final Inspection | 1/29/2002 | 1/29/2002 | 1/29/2002 | P | PASS |
Rick Jackson
|
|
|
fn fire jack --###-#### door hardware okay; exit signs okay; landing installed at sw exit; occ approved 1/29/2002 3:18:06 PM
|
FIRE-Final Inspection | 1/24/2002 | 1/25/2002 | 1/25/2002 | A | FAIL |
Rick Jackson
|
|
|
###-#### landing; door hardware; exit signs 1/25/2002 11:12:12 AM
|
BLD-Final | 1/24/2002 | 1/25/2002 | 1/25/2002 | P | PART |
Carl Dependahl
|
|
|
###-####...c/n, bathrooms, exit doors, other perm finals. 1/25/2002 4:06:19 PM
|
FIRE-Final Inspection | 1/25/2002 | 1/25/2002 | 1/25/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 1/25/2002 11:11:46 AM
|
BLD-Other | 1/24/2002 | 1/24/2002 | 1/24/2002 | P | PART |
Carl Dependahl
|
|
|
jack ###-#### grid ok to tile 1/24/2002 3:20:27 PM
|
Override - Parcel Holds | | | 1/24/2002 | | DONE |
Darla L Downs
|
|
|
Parcel Tag Notes: Prior to issuance of a final occupancy permit the parking structure to the east shall be completed. Per Tempra K. Wilson X3836. (11/21/2001-Carol Cherry) Reason for OverRide: inspection only
|
BLD-Framing/Rough-in | 1/15/2002 | 1/16/2002 | 1/16/2002 | A | PART |
Carl Dependahl
|
|
|
###-#### rest rm ok 1/16/2002 12:22:23 PM
|
Override - Parcel Holds | | | 1/15/2002 | | DONE |
Annett Moore
|
|
|
Parcel Tag Notes: Prior to issuance of a final occupancy permit the parking structure to the east shall be completed. Per Tempra K. Wilson X3836. (11/21/2001-Carol Cherry) Reason for OverRide:
|
BLD-Framing/Rough-in | 1/14/2002 | 1/14/2002 | 1/14/2002 | P | FAIL |
Carl Dependahl
|
|
|
###-####, walls ok, still need hvac ok'd at restrooms...elec at grid. firestop floor drains 1/14/2002 2:13:21 PM
|
Override - Parcel Holds | | | 1/14/2002 | | DONE |
Rita DeYoung
|
|
|
Parcel Tag Notes: Prior to issuance of a final occupancy permit the parking structure to the east shall be completed. Per Tempra K. Wilson X3836. (11/21/2001-Carol Cherry) Reason for OverRide:
|
Override - Parcel Holds | | | 1/14/2002 | | DONE |
Rita DeYoung
|
|
|
Parcel Tag Notes: Prior to issuance of a final occupancy permit the parking structure to the east shall be completed. Per Tempra K. Wilson X3836. (11/21/2001-Carol Cherry) Reason for OverRide:
|
BLD-Framing/Rough-in | 1/2/2002 | 1/3/2002 | 1/3/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/02/2002 at 15:58:41. Contact: . c/n, firestop plbg, glazing attachments, etc. ok to rock walls exc rest rms. 1/3/2002 6:10:49 PM
|
BLD-Framing/Rough-in | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 1/3/2002 12:23:01 PM keep c/n, met w/ glazer 1/3/2002 6:17:15 PM
|
Issue PAID IN FULL permit | | | 12/27/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/21/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/21/2001 | | DONE |
|
|
|
|
Telephone call | | | 12/21/2001 | | DONE |
|
|
|
permit ready
|
Routing - PLAN CHECK | 12/19/2001 | | 12/20/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2001 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 12/7/2001 | | 12/20/2001 | | PASS |
Carl Westfall
|
|
|
12/20/2001 13:15:21 CJW - activity updated through activity BLDA022 from case BLD01-03117.
|
Routing - FIRE | 12/18/2001 | | 12/19/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 12/19/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/13/2001 | | 12/18/2001 | | PASS |
|
|
|
UBC plan review started December 14, 2001 and finished December 18, 2001. The drawings were approved with conditions. See the conditions list.
|
Routing - PUBLIC WORKS | 12/7/2001 | | 12/13/2001 | | PASS |
|
|
|
|
First Notice | 12/3/2001 | 12/3/2001 | 12/3/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/3/2001 | | DONE |
|
|
|
1. Plans accepted by Carl Westfall.
|
Application received | | | 12/3/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/3/2001 | | |
|
|
|
|