(VISSER BUILDING CO., LLC) (SUITE #120) New 1,424 sq.ft. office tenant space and 443 sq. ft. of core restroom and hallway in existing shell building done under BLD01-01576 per approved plans on file. Work to include new one-hour rated tenant demising walls, two new building core accessible restrooms and hallway, new interior walls and doors, interior finish, new suspended ceiling, new mechanical work, new plumbing work, and new electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is NOT fire sprinklered. (PC#0628-02) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes9/20/20029/20/20028/10/2004 DONE
DOC - Permit Finaled8/5/20048/5/20048/5/2004PPASS
DetailsJim Sly
Finaled by inspector at 8/5/2004 4:29:52 PM
DOC - Permit Finaled8/5/20048/5/20048/5/2004PPASS
DetailsJim Sly
Finaled by inspector at 8/5/2004 4:31:06 PM
BLD-Aging Inspection8/2/20048/2/20048/2/2004 PASS
DetailsJim Sly
Fire passed and Electr passed...no futher corrections......Permit Expired...going to final out. 8/5/2004 4:29:45 PM
BLD-Aging Inspection8/2/20048/2/20048/2/2004 PASS
DetailsJim Sly
BLD-Final4/29/20034/30/20034/30/2003AFAIL
DetailsJim Sly
###-#### chip Need Electr final. 4/30/2003 10:06:29 AM
Code Occupancy Approval  4/30/2003 PASS
Inspected for final - all conditions met. Pass
FIRE-Final Inspection12/10/200212/11/200212/11/2002PPASS
DetailsTroy Cobbley
Fire life/safety finaled. Structural inspector to please verify that the "door to remain unlocked during business hours" stickers are installed on both doors 12/11/2002 2:05:10 PM
BLD-Final12/10/200212/11/200212/11/2002PPASS
DetailsJim Sly
CHIP\\LATE IF POSSIBLE; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung OK for Temp Occ. Need all signatures for Perm within 90 days of this notice. 12/11/2002 4:37:39 PM
BLD-Final12/10/200212/11/200212/11/2002PPASS
DetailsJim Sly
CHIP\\LATE IF POSSIBLE; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung OK for Temp Occ. Need all signatures for Perm within 90 days of this notice. 12/11/2002 4:37:39 PM
BLD-Framing/Rough-in12/4/200212/4/200212/4/2002PPART
DetailsSteven Webb
ceiling grid ###-#### Need to inspect that lights are fastened. 12/4/2002 2:56:58 PM
BLD-Framing/Rough-in11/13/200211/14/200211/14/2002APASS
DetailsJim Sly
###-####
Issue PAID IN FULL permit  10/30/2002  
Plan assigned to (JCB)9/24/2002 10/28/2002 PASS
DetailsJason Blais
10/28/2002 15:29:07 JCB - activity updated through activity BLDA022 from case BLD02-02323.
Routing - PLAN CHECK10/9/2002 10/28/2002 PASS
Permit and plans approved and taken to front desk.
Plan resubmittals received  10/28/2002 DONE
Received two copies of revised sheets A2, A3. One copy of response letter. Routed to Jason B. kmm
Plan resubmittals received  10/28/2002  
New Certificate of Value provided.
PLANS/APPL TAKEN TO FRONT DESK  10/28/2002 PASS
Inspection Record Card- Bld  10/28/2002 DONE
Print Occupancy Form  10/28/2002 DONE
Telephone call  10/28/2002 DONE
PERMIT READY AND FEES DUE
Plan resubmittals received  10/24/2002 DONE
Resubmittals A0, A1, A2, A3, M1, P1, E1 and E2 received and forwarded to Jason B.
Plan Review Completed(1st rev)  10/9/2002 FAIL
Routing - FIRE10/7/2002 10/9/2002 PASS
Plan resubmittals requested  10/7/2002  
Plan resubmittals and written response required for further review.
Routing - PLAN CHECK10/2/2002 10/7/2002 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans routed to Fire Dept.
Routing - PUBLIC WORKS9/24/2002 10/2/2002 PASS
Plans ACCEPTED BY PLAN TECH  9/23/2002 DONE
Application received  9/20/2002  
Recd Pcfee & Taken To Pln CK  9/20/2002 DONE