Case Summary (BLD) | | | 3/11/2014 | | DONE |
|
|
|
|
BLD-Aging Inspection | 3/29/2004 | 3/29/2004 | 3/29/2004 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 3/29/2004 | 3/29/2004 | 3/29/2004 | A | PASS |
Dave Hannah
|
|
|
Expired by inspector at 3/29/2004 8:07:34 AM
|
BLD-Final | 3/6/2003 | 3/7/2003 | 3/7/2003 | A | PASS |
Dave Hannah
|
|
|
Mike ###-#### - perfers 1st thing in the a.m. - 7:30 would be good - call 1st ok for perm occ 3/7/2003 9:16:01 AM
|
Letter of compliance | | | 3/7/2003 | | DONE |
|
|
|
Letter of Compliance #22832 issued 3-7-03.
|
FIRE-Final Inspection | 2/14/2003 | 2/14/2003 | 2/14/2003 | A | PASS |
Rick Jackson
|
|
|
|
Issue PAID IN FULL permit | | | 12/3/2002 | | |
|
|
|
|
Telephone call | | | 11/7/2002 | | DONE |
|
|
|
CALLED 11-7-02
|
Inspection Record Card- Bld | | | 11/7/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/7/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/30/2002 | | 11/6/2002 | | PASS |
|
|
|
Received new sheet of elevations ASI85.3 showing accessible sink controls & reach ranges and accessible counter section in Hall. To permit desk to issue.
|
Plan assigned to (DRS) | 10/15/2002 | | 11/6/2002 | | PASS |
Dan Stuart
|
|
|
11/6/2002 15:47:35 DRS - activity updated through activity BLDA022 from case BLD02-02517.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2002 | | PASS |
|
|
|
To permit desk for issue.
|
Plan resubmittals received | | | 11/5/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets ASI85.1, ASI85.2, ASI85.3, with transmittal letter. Routed to Dan Stuart.
|
Telephone call | | | 11/5/2002 | | DONE |
|
|
|
Called Steve Tourney to discuss plan re-submittal of 11/4/02. Plans did not indicate the accessible elevations for sinks, controls & work counter. Told Steve these items needed to be addressed before I could finish the plan review and approve for permit. He does not agree with the accessibility requirements but will resubmit and address Tim Hogland for code question.
|
Plan resubmittals received | | | 11/4/2002 | | DONE |
|
|
|
Received two copies of resubmittal sheets ASI.85.1, ASI85.2, ASI85.3, with cover letter. Routed to Dan Stuart.
|
Routing - FIRE | 10/25/2002 | | 10/30/2002 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/28/2002 | | DONE |
|
|
|
Received one copy of revised sheetsA1.0 and floor plan. One copy of letter to Dan. Routed to Dan S.
|
Routing - PLAN CHECK | 10/21/2002 | | 10/25/2002 | | FAIL |
|
|
|
Resubmittals required to address accessibility for the remodeled areas. List of corrections & clarifications required faxed and mailed to architect for repsonse. Plans forwarded to fire code analyst for review.
|
Routing - PLUMBING | 10/17/2002 | | 10/21/2002 | | PASS |
|
|
|
1. may require premise backflow and thermal expansion protection 2. if plaster casting to be done, that sink will require plaster trap. 3. water heater may require pan with drain effective 11/1/02
|
Routing - PUBLIC WORKS | 10/15/2002 | | 10/17/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/15/2002 | | DONE |
|
|
|
Client informed about mech. and plumb. kmm
|
First Notice | 10/14/2002 | 10/14/2002 | 10/14/2002 | | DONE |
|
|
|
|
Application received | | | 10/14/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/14/2002 | | |
|
|
|
|