Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/18/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/18/2004 | 5/18/2004 | | DONE |
|
|
|
|
BLD-Final | 5/18/2004 | 5/18/2004 | 5/18/2004 | | DONE |
|
|
|
Final - approved for perm. occ.
|
Permanent occupancy | | | 5/18/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10145 issued 5-18-04 to the Harriman Apartments.
|
BLD-Aging Inspection | 4/21/2004 | 4/21/2004 | 4/21/2004 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 2/13/2004 | 2/13/2004 | 2/13/2004 | | NR |
Tom Arcoraci
|
|
|
|
Temporary occupancy | | | 12/12/2003 | | DONE |
|
|
|
Temp. Occ. Cert. # 5039 issued 12-12-03 to the Harriman Apts.
|
FIRE-Final Inspection | 12/9/2003 | 12/10/2003 | 12/10/2003 | A | PASS |
Troy Cobbley
|
|
|
russ; Phone #: ###-#### Fire life safety is ok. Structural inspector to please verify that the rated doors get their tags. He said it would be done by the time you get there 12/10/2003 10:23:31 AM
|
BLD-Final | 12/9/2003 | 12/10/2003 | 12/10/2003 | P | PART |
Tom Arcoraci
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ needs over head hazard protection installed 12/10/2003 12:42:19 PM
|
Code Occupancy Approval Temp | | | 12/10/2003 | | DONE |
|
|
|
BOND IN PLACE TEMP SIGNED OFF
|
FIRE-Final Inspection | 12/1/2003 | 12/1/2003 | 12/1/2003 | P | FAIL |
Rick Jackson
|
|
|
Russ; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes need rated doors and closures 12/1/2003 3:55:03 PM
|
Print Occupancy Form | | | 11/17/2003 | | DONE |
|
|
|
|
BLD-Energy code compliance | 10/22/2003 | 10/23/2003 | 10/23/2003 | P | PASS |
Tom Arcoraci
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 10/23/2003 | 10/23/2003 | 10/23/2003 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/21/2003 | 10/22/2003 | 10/22/2003 | A | CANC |
Tom Arcoraci
|
|
|
###-####
|
BLD-Framing/Rough-in | 10/22/2003 | 10/22/2003 | 10/22/2003 | P | FAIL |
Tom Arcoraci
|
|
|
cn issued 10/22/2003 3:19:02 PM
|
Plan resubmittals received | | | 9/2/2003 | | DONE |
|
|
|
Received two copies of revised sheets A1.0, A2.0 & A3.0. Routed to Mike P. kmm
|
BLD-Footing | 8/18/2003 | 8/19/2003 | 8/19/2003 | A | PART |
Tom Arcoraci
|
|
|
###-#### pending ok for 10 ft ok 8/19/2003 10:10:43 AM
|
Plan assigned to (M_P) | 3/18/2003 | 3/18/2003 | 8/18/2003 | | PASS |
Mike Phillips
|
|
|
8/18/2003 11:40:50 M_P - activity updated through activity BLDA022 from case BLD03-00507.
|
Routing - PLAN CHECK | 8/15/2003 | | 8/18/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/18/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/18/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/18/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/18/2003 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 8/14/2003 | | 8/15/2003 | | PASS |
|
|
|
Lot 1 of Concord Commons Subdivision.
|
Routing - PLAN CHECK | 6/16/2003 | | 8/14/2003 | | |
|
|
|
|
Plan resubmittals received | | | 7/3/2003 | | DONE |
|
|
|
Received two copies of revised sheets A2.0, A2.1, A4.0, A4.1, A4.2, A8.0, A8.1, A9.0, A10.1 and one copy of cover letter. Routed to Mike P. kmm
|
Routing - PLAN CHECK | 5/6/2003 | | 6/16/2003 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan resubmittals received | | | 5/29/2003 | | DONE |
|
|
|
Received transmittal from Tamura with two sets of A2.0, A2.1, A3.0, A4.1, A4.2, A8.0, A9.0, A10.1, M1.0, P1.0, P2.0, and taken to Mike P.
|
Routing - PUBLIC WORKS | 5/6/2003 | | 5/6/2003 | | PASS |
|
|
|
|
Routing - FIRE | 4/29/2003 | | 5/5/2003 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 5/5/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/30/2003 | | DONE |
|
|
|
United Water letter and fax transmittal sheet to Sam R.
|
Override - Parcel Holds | | | 4/29/2003 | | |
|
|
|
|
Print permit w/o conditions | | | 4/29/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 4/3/2003 | | 4/29/2003 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be resubmitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 4/11/2003 | | DONE |
|
|
|
Received two sets of resubmittal sheets A2.0, A2.1, (1) structural calculations, and transmittal. Routed to Mike Phillips.
|
Plan resubmittals received | | | 4/11/2003 | | DONE |
|
|
|
Received two copies of resubmittal sheet A1.0. Routed to Mike Phillips.
|
Routing Off Site -Energy | 3/26/2003 | | 4/3/2003 | | PASS |
|
|
|
Ron O.
|
Routing - PLUMBING | 4/1/2003 | | 4/3/2003 | | PASS |
|
|
|
1. detail 4 sht p2.0sshows one inch water from backflow to units. one inch is not large enough to serve a 4-plex 2. water heaters will require heat trap nipples
|
Routing - PLANNING | 3/31/2003 | | 4/1/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 3/28/2003 | | 3/31/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 3/26/2003 | | 3/28/2003 | | FAIL |
|
|
|
Requires drainage plan.
|
Plan resubmittals received | | | 3/25/2003 | | DONE |
|
|
|
Received four sets of resubmittal sheets A0 and A0.2 (Energy Compliance), (2) sets of ESC Prepared Plans, (1) revised Certificate of Value, ESC narrative for Lots 5 & 7, and transmittal. Attached to plans.
|
Routing - PLANNING Land Div | 3/18/2003 | | 3/24/2003 | | FAIL |
|
|
|
DO NOT ISSUE UNTIL CONCORD COMMONS SUBDIVISION IS RECORDED
|
Plans ACCEPTED BY PLAN TECH | | | 3/18/2003 | | DONE |
|
|
|
1. Faxed applicant that Energy Compliance Plan and 18 x 24 ESC Plan is required.
|
Telephone call | | | 3/18/2003 | | DONE |
|
|
|
Left message for Elizabeth Cooper, structural calculations are under the 1997 UBC, the 2000 IBC are required.
|
Application received | | | 3/13/2003 | | |
|
|
|
|