Letter of compliance | | | 10/7/2003 | | DONE |
|
|
|
letter of Compliance # 24124 issued 10-7-03.
|
BLD-Final | 10/2/2003 | 10/3/2003 | 10/3/2003 | A | CANC |
Tony Young
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Darla Downs
out of time, resceduled for pm 10/3/2003 11:57:13 AM
|
FIRE-Final Inspection | 10/2/2003 | 10/3/2003 | 10/3/2003 | A | PASS |
Rick Jackson
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Final | 10/3/2003 | 10/3/2003 | 10/3/2003 | P | PASS |
Tony Young
|
|
|
bill phone# ###-####
|
DOC - Permit Finaled | 10/3/2003 | 10/3/2003 | 10/3/2003 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 10/3/2003 2:14:21 PM
|
BLD-Framing/Rough-in | 9/12/2003 | 9/15/2003 | 9/15/2003 | P | PASS |
Tom Arcoraci
|
|
|
bill- ###-####
|
Issue PAID IN FULL permit | | | 9/3/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/2/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/2/2003 | | DONE |
|
|
|
permit ready and fees due
|
Permit Ready to Issue | | | 9/2/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2003 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 7/24/2003 | | 8/29/2003 | | PASS |
Carl Westfall
|
|
|
8/29/2003 15:39:46 CJW - activity updated through activity BLDA022 from case BLD03-01780.
|
Routing - FIRE | 8/22/2003 | | 8/28/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/25/2003 | | 8/22/2003 | | PASS |
|
|
|
IBC plan review started August 21, 2003 and finished the next day. The drawings were approved with clarifications. See the plan review report.
|
Routing - PUBLIC WORKS | 7/24/2003 | | 7/25/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/23/2003 | | PEND |
|
|
|
Received letter for lighting compliance. No lighing compliance encorporated into plans. kmm
|
Application received | | | 7/22/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2003 | | DONE |
|
|
|
|
Fee Review-notes | 7/22/2003 | 7/22/2003 | | | |
|
|
|
|
Routing - PLAN CHECK | 8/29/2003 | | | | |
|
|
|
|