Permit Information
Permit NumberBLD04-01076
StatusFinaled
Name UNICO PROPERTIES
Site Address 101 S CAPITOL BLVD
Project NameUS BANK-PARKING LOT
Customer Number 
ePlanReviewNo
Description
(US BANK - PARKING LOT RESURFACE & NEW ATTENDANT BOOTH) To resurface the existing parking lot, renovate some of the concrete curbing, landscaping and parking lot lighting and to demo the existing parking attendant's booth and construct a new 6'-10" x 8'-4", one story, metal, prebuilt attendant booth. Deferred Submittals - Structural Calculations and Details. The structural calculations and anchoring details for the attendant's booth are being deferred so that the parking lot and landscaping work can begin. The required deferred submittals include the structural calculations for the building vertical and lateral loads, as well as, all structural calculations for the required building attachments to the concrete foundation. These deferred structural items must be submitted to the Boise City Building Department Plan Review Staff for review and approval prior to receiving a final approval for the booth. All construction per the approved plans and attached comment list. CVA04-00002 AND DRH04-00081/#04-316/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  7/2/2013 DONE
Third Notice BLD6/14/20066/14/20062/21/2007 DONE
Second Notice has not been responded to.
Second Notice BLD5/25/20065/25/20066/14/2006 DONE
First Notice has not been responded to.
First Notice4/24/20064/24/20065/25/2006 DONE
DetailsDave Hannah
BLD-Aging Inspection4/24/20064/24/20064/24/2006 PASS
DetailsDave Hannah
DOC - Permit Finaled4/24/20064/24/20064/24/2006PPASS
DetailsDave Hannah
FIRE-Final Inspection10/19/200510/20/200510/20/2005AFAIL
DetailsForrest France
Provide one 2A10BC fire ext. with current inspection tag, provide approved door hardware at exit door as discussed.
FIRE-Final Inspection10/19/200510/19/200510/19/2005PCANC
DetailsForrest France
No time for inspection, will reschedule for tomorrow.
FIRE-Final Inspection10/19/200510/19/200510/19/2005PCANC
DetailsForrest France
Code Occupancy Approval10/17/200510/17/200510/17/2005APASS
DetailsWm. Michael Meloy
Compliance met.
Case Summary (BLD)  12/6/2004  
BLD-Aging Inspection10/19/200410/19/200410/19/2004 PASS
DetailsDave Hannah
exp on01/05/05 10/25/2004 9:14:00 AM
Plan Reviewer's activity  7/28/2004 PASS
I have reviewed and approved the structural calculations and drawing for the attendent booth. These items were required as a deferred submittal as a part of an agreement for an early release of the building permit. The calculations where done using the 1997 UBC; however, I approved it because the building and loads are very small and the wind loads used are equivalent to those in the 2000 IBC. JCM
Plan resubmittals received  7/27/2004  
Received a copy of the required structural calculations for the attendant booth that were allowed to be submitted as a deferred submittal. JCM
Issue PAID IN FULL permit  7/9/2004 DONE
Routing - PLAN CHECK6/18/2004 7/7/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  7/7/2004 DONE
Inspection Record Card- Bld  7/7/2004 DONE
Print Occupancy Form  7/7/2004 DONE
Permit Ready to Issue  7/7/2004 DONE
Telephone call  7/7/2004 DONE
permit ready and fee due
Plan assigned to (JCM)6/1/2004 7/7/2004 PASS
DetailsJohn Menard
7/7/2004 10:57:32 JCM - activity updated through activity BLDA022 from case BLD04-01076.
Routing - FIRE6/15/2004 6/18/2004 PASS
approved subject to plan annotations (door hardware and PFE) and satisfactory field inspection. No written review comments.
Plan Review Completed(1st rev)  6/18/2004 FAIL
failed plan check.
Routing - PLAN CHECK6/8/2004 6/15/2004 FAIL
Plan resubmittals requested  6/15/2004 DONE
Mailed the architect a letter requesting additional infomation need to review the proposed new structure. JCM
Routing - Erosion and Sediment6/7/2004 6/8/2004 PASS
ESC waiver approved with conditons attached to plans.
Routing - PLANNING6/1/2004 6/3/2004 PASS
CVA04-00002 Susan Riggs Pending DR
DRH04-00081 Sarah Schafer

Approved per DRH04-81.
Routing - PUBLIC WORKS5/20/2004 5/27/2004 PASS
Application received  5/19/2004  
Plans ACCEPTED BY PLAN TECH  5/19/2004 PASS