BLD-Final | 11/14/2005 | 11/15/2005 | 11/15/2005 | A | PASS |
Tom Arcoraci
|
|
|
ed ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Energy code compliance | 8/1/2005 | 8/2/2005 | 8/2/2005 | A | PASS |
Tom Arcoraci
|
|
|
ed; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/27/2005 | 7/27/2005 | 7/27/2005 | P | PASS |
Tom Arcoraci
|
|
|
ed; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Foundation | 4/29/2005 | 5/2/2005 | 5/2/2005 | A | PASS |
Tom Arcoraci
|
|
|
manuel; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 4/28/2005 | 4/29/2005 | 4/29/2005 | A | PART |
Tom Arcoraci
|
|
|
MANUEL; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Plan assigned to (SAM) | 4/6/2005 | 4/6/2005 | 4/27/2005 | | PASS |
|
|
|
4/27/2005 11:07:43 SRZ - activity updated through activity BLDA022 from case BLD05-00902.
|
Routing - PLAN CHECK | 4/19/2005 | | 4/27/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 4/27/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2005 | | DONE |
|
|
|
ONLY ONE SET RED-LINED DUE TO EXCESSIVE RED-LINING.
(SRZ)
|
Permit Ready to Issue | | | 4/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2005 | | DONE |
|
|
|
called spoke to Ed Altman told him permit is ready and fees, said he will be in today 4/27/05 12:00pm LEM
|
Inspection Record Card- Bld | | | 4/27/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/27/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2005 | | 4/19/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 4/6/2005 | | 4/18/2005 | | PASS |
|
|
|
3 site plans on one sheet without distinction - need clarity! lot 10 - chimney shall not extend more than 24" into setback. Front porch columns shall sit completely within front 15' setback - eave may extend 24"
|
Application received | | | 4/6/2005 | | |
|
|
|
|