BLD-Final | 1/26/2006 | 1/27/2006 | 1/27/2006 | A | PASS |
Jim Storey
|
|
|
Val; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
DOC - Permit Finaled | 1/27/2006 | 1/27/2006 | 1/27/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/4/2005 | 10/4/2005 | 10/5/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/4/2005 at 10:02:56 AM. Contact: ###-####.
|
BLD-Energy code compliance | 9/30/2005 | 10/4/2005 | 10/4/2005 | A | NR |
Mike Jordan
|
|
|
val; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs mech. ri inspection before proceeding.
|
BLD-Framing/Rough-in | 9/29/2005 | 9/30/2005 | 9/30/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/29/2005 at 5:27:32 PM. Contact: ###-####.truss bracing/ truss bc cut/ fire blk/ ok to insulate after mech aproval.
|
BLD-Footing | 8/12/2005 | 8/15/2005 | 8/15/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/12/2005 at 11:11:53 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 8/10/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/9/2005 | | DONE |
|
|
|
lft vm with speciality homes ###-#### that permit and fees are ready to be picked up no eros renewal
|
Telephone call | | | 8/9/2005 | | DONE |
|
|
|
Spoke with Val Hill and told him that permit is ready, fees & that RP lic is expired. He said took class in April to renew. I found test and check that says he only paid $50 instead of $55 so he will write new check for lic when he comes in to pick up permit///8/9/05 2:35pm BAS
|
Plan assigned to (SRZ) | 8/5/2005 | 8/5/2005 | 8/8/2005 | | PASS |
|
|
|
8/8/2005 16:21:52 SRZ - activity updated through activity BLDA022 from case BLD05-01772.
|
Routing - Erosion and Sediment | 8/5/2005 | | 8/8/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 8/8/2005 | | 8/8/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2005 | | DONE |
|
|
|
ONE SET RED-LINED
|
Plan assigned to (SAM) | 6/30/2005 | 6/30/2005 | 8/5/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/5/2005 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/5/2005 | | PASS |
|
|
|
Building Permit pending Erosion Sediment Control requirements and release. (SRZ)
|
Routing - Erosion and Sediment | 7/29/2005 | | 7/29/2005 | | FAIL |
|
|
|
ESC plan failed. No plan or waiver request submitted.
|
Routing - PLAN CHECK | 7/12/2005 | | 7/29/2005 | | PASS |
|
|
|
Routed for ESC on 7/19/2005 at 09:35.
|
Routing - PUBLIC WORKS | 7/12/2005 | | 7/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 7/11/2005 | | 7/11/2005 | | PASS |
|
|
|
update record 7/26/05 - passed planning per site plan approved as noted 7/11/05 per discussion with applicant. eeg.
|
Application received | | | 6/30/2005 | | |
|
|
|
|
Routing - PLANNING | 7/1/2005 | | | | FAIL |
|
|
|
7/1/05 routed to Susan Riggs per cfh02-00031. eeg received back from Susan - reviewed 7/07/05 held for wing walls within the side yard setback. called applicant.eeg.
|