(F) Reprint permit | | | 10/5/2006 | | |
|
|
|
|
BLD-Final | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | PASS |
Mike Jordan
|
|
|
ed ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 1/31/2006 | 1/31/2006 | 1/31/2006 | P | CANC |
Mike Jordan
|
|
|
brian blazer; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Energy code compliance | 1/31/2006 | 1/31/2006 | 1/31/2006 | P | PASS |
Mike Jordan
|
|
|
brian blazer; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. All framing issues have been resolved. ok to cover.
|
BLD-Energy code compliance | 1/30/2006 | 1/30/2006 | 1/30/2006 | P | FAIL |
Mike Jordan
|
|
|
Brian; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Lateral bracing not complete. Header required over opening at C1 truss bearing. Justify girder support were hangar was deleted. L brace gable end.
|
BLD-Framing/Rough-in | 1/26/2006 | 1/27/2006 | 1/27/2006 | A | PART |
Mike Jordan
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Wood trusses cut back so as to not penetrate 1hr membrane. Reveiwed truss engineering for repairs on cut trusses. Girder truss repaired incorrectly. Needs to complete lateral bracing and remove remaining wood penetrations from 1hr wall. Also noted that non rated boxes have been removed and replaced with rated 1hr boxes. ok to insulate. c/n posted.
|
BLD-Framing/Rough-in | 1/23/2006 | 1/24/2006 | 1/24/2006 | A | FAIL |
Mike Jordan
|
|
|
Scott -- call 1st before insp; requesting both Tom Arcoraci and Mike Jordan for framing insp and conference; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. mMust install rated boxes at waterline and flex gasline. B vent penetration not allowed thru laydown parapet. Membrane penetration with wood trusses not allowed. Not per plans.
|
BLD-Conference | 1/23/2006 | 1/24/2006 | 1/24/2006 | A | CANC |
Tom Arcoraci
|
|
|
Scott -- call 1st before insp; requesting both Tom Arcoraci and Mike Jordan for framing insp and conference; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | NR |
Tom Arcoraci
|
|
|
scott ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs app plans
|
BLD-Framing/Rough-in | 1/13/2006 | 1/13/2006 | 1/13/2006 | P | NR |
Mike Jordan
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. No truss engineering.
|
BLD-Framing/Rough-in | 1/10/2006 | 1/10/2006 | 1/10/2006 | P | FAIL |
Mike Jordan
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Needs to provide approved plans and truss engineering. Needs to fire caulk elec. box above fireplace.
|
BLD-Foundation | 9/12/2005 | 9/12/2005 | 9/12/2005 | P | PART |
Tom Arcoraci
|
|
|
ruben; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Inspection Record Card- Bld | | | 8/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/9/2005 | | DONE |
|
|
|
called ###-#### (pepperwood homes) and told him we have a permit ready then he hung up. Did not tell fees or get name.
|
Issue PAID IN FULL permit | | | 8/9/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/7/2005 | 7/7/2005 | 8/8/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/12/2005 | | 8/8/2005 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/8/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 8/8/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2005 | | DONE |
|
|
|
one set red-lined
|
Routing - PLANNING | 7/12/2005 | | 7/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 7/7/2005 | | 7/12/2005 | | FAIL |
|
|
|
Routed to Carl Miller per 79.6.PDR (Ada)
Failed: site plans do not match floor plans
|
Routing - PUBLIC WORKS | 7/12/2005 | | 7/12/2005 | | PASS |
|
|
|
|
Application received | | | 7/7/2005 | | |
|
|
|
|