Fee Review-notes | 8/25/2005 | 8/25/2005 | 4/5/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/2/2007 | | DONE |
|
|
|
call to allison w/ rm to check and varify fv. she stated she would call back today.
|
Telephone call | | | 4/2/2007 | | DONE |
|
|
|
call from allison w/ rm donfirming $500 value and she will fax a copy of her invoice for the job.
|
Telephone call | | | 4/2/2007 | | DONE |
|
|
|
call to pete rutherford w/ colliers to varify difference in fv amounts, left msg to call back.
|
Third Notice BLD | 8/18/2006 | 8/18/2006 | 3/5/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 7/7/2006 | 7/7/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/16/2006 | 7/7/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/16/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11025 issued 5-16-06 to Collier's International on the 3rd floor of BODO Bldg. #7.
|
BLD-Final | 5/3/2006 | 5/4/2006 | 5/4/2006 | P | PASS |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
|
FIRE-Final Inspection | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | DONE |
Forrest France
|
|
|
Duplicate inspection request already completed.
|
FIRE-Final Inspection | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | PASS |
Forrest France
|
|
|
Project related alarm and sprinkler permits have been finaled, fire life safety passed inspection.
|
Permanent Occupancy | | 5/4/2006 | 5/4/2006 | | DONE |
|
|
|
|
BLD-Final | 5/2/2006 | 5/3/2006 | 5/3/2006 | P | CANC |
Dave Hannah
|
|
|
john ###-####
|
FIRE-Final Inspection | 5/3/2006 | 5/3/2006 | 5/3/2006 | A | FAIL |
Forrest France
|
|
|
The project related sprinkler permit has not been requested for final inspection.
|
FIRE-Final Inspection | 5/2/2006 | 5/2/2006 | 5/3/2006 | P | NR |
Forrest France
|
|
|
The project related fire sprinkler permit must be finaled before life safety final approval.
|
BLD-Final | 5/2/2006 | 5/2/2006 | 5/2/2006 | P | CANC |
Dave Hannah
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Ione Coleman
|
BLD-Final | 4/25/2006 | 4/26/2006 | 4/26/2006 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Marsha Smylie need to get fire final
|
FIRE-Final Inspection | 4/25/2006 | 4/26/2006 | 4/26/2006 | A | FAIL |
Forrest France
|
|
|
Three new offices have been built at the NE corner resulting in overspaced sprinklers, and possible alarm notification issues.
|
BLD-Other | 2/9/2006 | 2/9/2006 | 2/9/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5327 extended for 90 days per Jenifer thru 5-29-06.
|
BLD-Final | 11/29/2005 | 11/29/2005 | 11/29/2005 | P | PART |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok for temp occ needs other trades to go perm and fire coulk elec conduits in floor of mop room and install glassing
|
FIRE-Final Inspection | 11/28/2005 | 11/29/2005 | 11/29/2005 | A | PART |
Forrest France
|
|
|
Fire life safety is satisfactory, final pending shell permit finals.
|
Temporary occupancy | | | 11/29/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5327 issued 11-29-05 to Colliers International.
|
BLD-Final | 11/23/2005 | 11/25/2005 | 11/25/2005 | A | CANC |
Dave Hannah
|
|
|
tony ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Final Inspection | 11/23/2005 | 11/25/2005 | 11/25/2005 | A | FAIL |
Forrest France
|
|
|
Emergency lights in three locations did not function, need to add one emergency light for the path of egress as marked on the approved plans.
|
BLD-Final | 11/22/2005 | 11/23/2005 | 11/25/2005 | A | NR |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Final | 11/21/2005 | 11/22/2005 | 11/23/2005 | P | CANC |
Dave Hannah
|
|
|
john; Phone #: ###-#### Note: late afternoon Internet Inspection Request from: Barbara Moore
|
FIRE-Final Inspection | 11/21/2005 | 11/22/2005 | 11/22/2005 | P | CANC |
Forrest France
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 11/17/2005 | 11/17/2005 | 11/17/2005 | P | PART |
Jim Storey
|
|
|
requests first thing after lunch//ceiling inspection///john; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ceilling ok all but rated wall at stairs through penatrations ele. must be firestopped and reinsp.
|
BLD-Framing/Rough-in | 11/14/2005 | 11/14/2005 | 11/15/2005 | P | PART |
Dave Hannah
|
|
|
celing insp -- jon; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover se area after fire sprinkler rough in ok to set perm tiles
|
BLD-Energy code compliance | 10/24/2005 | 10/25/2005 | 10/26/2005 | P | PASS |
Dave Hannah
|
|
|
john; Phone #: ###-#### Note: fire calking also Internet Inspection Request from: Cathy Chiles ok to cover atrium
|
BLD-Other | 10/20/2005 | 10/21/2005 | 10/24/2005 | A | PART |
Dave Hannah
|
|
|
fire caulking of the electrical conduit inside the walls please////pete; Phone #: ###-#### Internet Inspection Request from: Barbara Moore all floor penatrations fire protected ok to cover
|
BLD-Energy code compliance | 10/17/2005 | 10/18/2005 | 10/18/2005 | P | PASS |
Dave Hannah
|
|
|
JOHN; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Energy code compliance | 10/14/2005 | 10/17/2005 | 10/18/2005 | P | CANC |
Dave Hannah
|
|
|
insp for insulation and vapor barrier//john; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Energy code compliance | 10/13/2005 | 10/14/2005 | 10/17/2005 | P | CANC |
Dave Hannah
|
|
|
john Note: right after lunch if possible; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 10/12/2005 | 10/13/2005 | 10/14/2005 | A | PART |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 10/13/2005 | 10/13/2005 | 10/14/2005 | P | PASS |
Dave Hannah
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to insulate and cover int walls
|
BLD-Framing/Rough-in | 10/10/2005 | 10/11/2005 | 10/12/2005 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/10/2005 at 1:46:35 PM. Contact: ###-####. john needs plumb and elec r/is
|
Inspection Record Card- Bld | | | 10/7/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2005 | | DONE |
|
|
|
left mess for pete conlon at ###-#### & trent koci at ###-####
|
Issue PAID IN FULL permit | | | 10/7/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/6/2005 | | 10/6/2005 | | PASS |
|
|
|
10/6/2005 14:32:00 CJW - activity updated through activity BLDA022 from case BLD05-02358.
|
Routing - PLAN CHECK | 9/22/2005 | | 10/6/2005 | | PASS |
|
|
|
(9-29-05) The 2nd IBC plan review was completed. One item was not resolved. The Architect was E-mailed a revised copy of the Plan Review Report. (10-6-05) Drawings approved after review of submitted structural drawings and calculations.
|
Plan resubmittals received | | | 10/6/2005 | | |
|
|
|
Received (2) copies of sheet S2.4. Routed to Carl W.
|
Routing - PUBLIC WORKS | 10/6/2005 | | 10/6/2005 | | DONE |
|
|
|
Sent back for re-calculation of sewer fees.
|
Routing - PLAN CHECK | 10/6/2005 | | 10/6/2005 | | SONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/3/2005 | | DONE |
|
|
|
Authorized a Partial Permit to be issued.
|
Early Start Permit | | | 10/3/2005 | | |
|
|
|
|
Telephone call | | | 10/3/2005 | | DONE |
|
|
|
left mess for pete conlon at ###-#### that early start is ready
|
Routing - FIRE | 9/8/2005 | | 9/22/2005 | | PASS |
|
|
|
Faxed comments to architect.
|
1st review completed | | | 9/22/2005 | | FAIL |
|
|
|
Fail plan check.
|
Plan resubmittals received | | | 9/20/2005 | | DONE |
|
|
|
Received 1 Transmittal Letter,1 Memo ,& 2 Copys of sheetes A-1,A-4,A-5,A-7,M-1,M-2,P-1,E-1,E-2,E-3 Taken to Carl W.
|
Routing - PLAN CHECK | 8/31/2005 | | 9/8/2005 | | FAIL |
|
|
|
The IBC plan review was started on September 7, 2005 and was finished the next day. Revised drawings were required. See the plan review report.
|
Pending Assignment by MYS | 8/25/2005 | | 9/6/2005 | | DONE |
|
|
|
9/6/2005 10:34:26 MYS - activity updated through activity BLDA172 from case BLD05-02358.
|
Routing - PUBLIC WORKS | 8/31/2005 | | 8/31/2005 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 8/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2005 | | |
|
|
|
|
Application received | | | 8/25/2005 | | |
|
|
|
|