Case Summary (BLD) | | | 1/12/2009 | | DONE |
|
|
|
|
Second Notice BLD | 4/23/2008 | 4/23/2008 | 6/4/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/28/2008 | 4/23/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/28/2008 | | DONE |
|
|
|
|
BLD-Final | 3/26/2008 | 3/26/2008 | 3/26/2008 | A | PASS |
Tom Arcoraci
|
|
|
Please call me before you come out. I am waiting for Troy to sign off the fire life safety before you can final the entire project. Thank you,
Todd Phone #: ###-#### Internet Inspection Request from: Todd Kurns
|
FIRE-Final Inspection | 3/26/2008 | 3/26/2008 | 3/26/2008 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Other | 1/23/2008 | 1/24/2008 | 1/24/2008 | A | PASS |
Jim Sly
|
|
|
Tom,
Just wanted to do an acoustical ceiling inspection........ Grid OK
Thanks,
Todd Phone #: ###-#### Internet Inspection Request from: Todd Kurns
|
BLD-Framing/Rough-in | 11/1/2007 | 11/2/2007 | 11/2/2007 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Todd Kurns
|
Issue & PRINT to be Invoiced | | | 10/2/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/20/2007 | | 9/27/2007 | | PASS |
|
|
|
(9-24-07) Looked at the pictures included in an E-mail from the Architect's representative. Called the rep. to discuss the pictures. The pictures don't tell the whole story. Asked for an as built roofing plan to verify that no bearing walls have been removed. (9-27-07) A roof plan and a note from the Structural Engineer was provided. The drawings were approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/27/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/27/2007 | | DONE |
|
|
|
t/c w dwaine carver at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/27/2007 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/29/2007 | | 9/27/2007 | | PASS |
|
|
|
9/27/2007 07:33:49 CJW - activity updated through activity BLDA022 from case BLD07-01556.
|
Routing - FIRE | 9/17/2007 | | 9/20/2007 | | PASS |
|
|
|
Attached updated fire code review comments to plans.
|
Routing - PLAN CHECK | 8/21/2007 | | 9/17/2007 | | FAIL |
|
|
|
Started the resubmittal review. Requested engineering for the 11'-9.5" opening was not provided. Called the Architect's office and ask for a resolution. Waiting for the resolution.
|
Plan resubmittals received | | | 9/12/2007 | | |
|
|
|
received transmittal from trout arch & plan review response -"1" (3 pages)& structural calcs (16 pages)--& "3" sets of plans including cover sheet, A2.1, A2.2, A2.3, A5.2, A9.5, M3.O, E2.OL, E2.OP, E2.OS, E3.O, E3.1, E3.2, & E3.5--plans taken to Carl Westfall
|
Routing - FIRE | 8/20/2007 | | 8/21/2007 | | FAIL |
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 8/21/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/2/2007 | | 8/20/2007 | | FAIL |
|
|
|
The IBC plan review was started on August 10, 2007 and was finished on August 20, 2007. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 6/29/2007 | | 7/2/2007 | | PASS |
|
|
|
|
Routing PW Sewer Rating | 7/2/2007 | | 7/2/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 6/18/2007 | | 6/29/2007 | | DONE |
|
|
|
6/29/2007 11:30:02 MYS - activity updated through activity BLDA172 from case BLD07-01556.
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2007 | | DONE |
|
|
|
|
Application received | | | 6/15/2007 | | |
|
|
|
|