Second Notice BLD | 11/7/2008 | 11/7/2008 | 11/24/2008 | | DONE |
Rita DeYoung
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/22/2008 | 11/7/2008 | | DONE |
|
|
|
|
BLD-Final | 9/22/2008 | 9/22/2008 | 9/22/2008 | P | PASS |
Mike Jordan
|
|
|
rick Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy UNPAID FEE | | | 9/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 9/16/2008 | 9/17/2008 | 9/17/2008 | P | PASS |
Troy Cobbley
|
|
|
LIfe safety passed
|
FIRE-Final Inspection | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | FAIL |
Troy Cobbley
|
|
|
The project was not ready for a final inspection yet but we verified that the smoke evacuation system operated correctly.
|
BLD-Framing/Rough-in | 9/12/2008 | 9/16/2008 | 9/16/2008 | A | PART |
Mike Jordan
|
|
|
rick - ceiling grid Phone #: ###-####. Needs to provide additional wires for diffusers and clip main runners.
|
BLD-Framing/Rough-in | 9/3/2008 | 9/4/2008 | 9/4/2008 | A | PASS |
Mike Jordan
|
|
|
Rick Phone #: ###-####. All issues resolved. Ok for cover.
|
BLD-Framing/Rough-in | 8/28/2008 | 8/29/2008 | 8/29/2008 | A | PART |
Mike Jordan
|
|
|
rick Phone #: ###-####. Framing for store front. Needs to provide welder certs, pull elec permit and get ri insp. Base plates for security gate structure not per plan, provide justification. c/n posted.
|
Plan assigned to (R_H) | 8/19/2008 | 8/19/2008 | 8/22/2008 | | PASS |
|
|
|
8/22/2008 11:08:03 RMH - activity updated through activity BLDA022 from case BLD08-01786.
|
Routing - PLAN CHECK | 8/18/2008 | | 8/22/2008 | | PASS |
Ron Hill
|
|
|
|
Routing - FIRE | | | 8/22/2008 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 8/22/2008 | | DONE |
|
|
|
|
1st review completed | | | 8/22/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
called Lee Young and told him permit is ready and fee, need GC, RCE
|
Permit Ready to Issue | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
Received Certificate of Value | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
Revised cert of value submitted by GC on pick-up: new project value is $30,500; ele $2,800; plm n/a; mech $1,750; fire sprinkler $1,800; fire alarm $1,800//8/22/08 LEG
|
Issue PAID IN FULL permit | | | 8/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/19/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
No general growth properties stamp Ron Hill agreed to take of.
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2008 | | DONE |
Darla L Downs
|
|
|
|
Application received | | 8/18/2008 | | | |
|
|
|
|