Permit Information
Permit NumberBLD09-00468
StatusFinaled
Name EKC INC
Site Address 222 S BROADWAY AVE
Project NameMarriott
Customer Number09-005
ePlanReviewNo
Description
(MARRIOTT - Lobby Renovation) Permit is to remodel an existing hotel lobby for new furnishing, media equipment, expanded coffee bar, modified general manager's office, and new market area. Approval per approved plans on file and CZC09-00016. Work to include: demolition of existing interior non-bearing walls, construction of new interior non-bearing walls to create a market area and a newly defined general managers office, installation of new lighting, new pluming associated with coffee bar, relocating ducts and diffusers, new doors and hardware, new accessible sales and service counter, and interior finishes in compliance with chapter 8 of the 2006 IBC. New C of O is for Lobby and scope of work shown on these plans only. This is not a C of O for the entire building. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  1/26/2010 DONE
DetailsTisha Gallop
called Cecyl/EKC and told her still need Mariott Lobby FV, she said is working on it right now. Told her will need w/in 2 wks or EKC on hold. Also told her still looking for FV on other 3 permits and on 2nd third notice there, she said those are Link's and she will give the notices to him when received.
Third Notice 12/29/200912/29/2009 DONE
faxed and called
Telephone call  12/29/2009 DONE
DetailsTisha Gallop
spoke to Cecyl, she said is shorthanded is why so late and just last week finished final billing on this project so is working on final values and will get it to me as soon as possible.
Third Notice 12/9/200912/16/2009 DONE
faxed, mailed and called
Telephone call  12/16/2009 DONE
DetailsTisha Gallop
left vm in general mailbox need fv
Third Notice 11/14/200911/25/2009 DONE
faxed
Second Notice 10/26/200911/4/2009 DONE
First Notice 10/5/200910/16/2009 DONE
BLD-Final9/24/20099/25/20099/25/2009PPASS
DetailsDave Hannah
Rick Phone #: ###-#### ok for perm occ
Permanent Occupancy  9/25/2009 DONE
DetailsTisha Gallop
FIRE-Final Inspection9/24/20099/24/20099/24/2009PPASS
DetailsForrest France
Fire life safety final approved, all corrections completed.
FIRE-Final Inspection9/23/20099/23/20099/24/2009PPART
DetailsForrest France
Final pending project related fire alarm permit, remainder of C/N items are finished.
Zoning Approval9/23/20099/23/20099/23/2009 PASS
DetailsAndrea Tuning
FIRE-Final Inspection9/21/20099/22/20099/22/2009AFAIL
DetailsForrest France
Project related fire alarm permit needs requested for inspection and approval prior to building life safety, repair two exit signs at the main entry/exit doors north and south, provide missing fire extinguisher and post as discussed, repair door closure at the north set of fire doors, sprinkler coverage at the reception area is obstructed.
FIRE-Final Inspection9/14/20099/14/20099/14/2009ANR
DetailsForrest France
Pending project related FIR permit finals.
BLD-Framing/Rough-in9/9/20099/10/20099/11/2009PPASS
DetailsDave Hannah
rick - ceiling Phone #: ###-####
BLD-Other8/27/20098/28/20098/28/2009PPASS
DetailsDave Hannah
Rick- ceiling- call 30 mins prior to going for access Phone #: ###-#### ok to cover ceiling
BLD-Framing/Rough-in7/23/20097/24/20097/24/2009PPASS
DetailsDave Hannah
Rick Phone #: ###-####
BLD-Conference7/9/20097/9/20097/9/2009PPASS
DetailsDave Hannah
Rick Phone #: ###-#### looked over plans talked about wall ratings
Issue PAID IN FULL permit  5/15/2009 DONE
Print Occupancy Form  4/24/2009 DONE
Details
Telephone call  4/24/2009 DONE
Details
left vm for wade at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  4/24/2009 DONE
Details
Routing - PLAN CHECK4/10/2009 4/23/2009 PASS
DetailsTim L. Woodard
Plan assigned to (TLW)4/10/2009 4/23/2009 PASS
DetailsTim L. Woodard
4/23/2009 16:03:19 TLW - activity updated through activity BLDA022 from case BLD09-00468.
Routing - FIRE  4/23/2009 PASS
DetailsTim L. Woodard
All fire sprinkler and alarm modifications must be permitted separatly through the fire dept. Field Verify Fire Dept. requirements. TLW
1st review completed  4/23/2009 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  4/23/2009 PASS
DetailsTim L. Woodard
Case Summary (BLD)  4/23/2009 DONE
DetailsTim L. Woodard
Plan resubmittals received  4/21/2009 DONE
received 1 interior finish index,and 1 interior renovations lobby taken to Tim W.
Recd Pcfee & Taken To Pln CK  4/10/2009 DONE
Routing - PUBLIC WORKS4/10/2009 4/10/2009 PASS
DetailsBeverly Hall
Plans ACCEPTED BY PLAN TECH  4/10/2009  
I could not find (Gegory Martino or Rodrick Roche) both engineers in the Idhao Bureau of Licenses./// DLD
Application received 4/9/2009