First Notice | 1/21/2011 | 1/21/2011 | 2/4/2011 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Jim Sly
|
|
|
Gene Phone #: ###-####
|
DOC - Permit Finaled | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 1/13/2011 | 1/13/2011 | 1/19/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 1/13/2011 | 1/13/2011 | 1/14/2011 | P | PART |
Jim Storey
|
|
|
gene - final for Focus rooms Phone #: ###-#### need wall fintsh listing to meet class c--- 200/450 not clear as to fd loaction or plan.
|
BLD-Framing/Rough-in | 12/17/2010 | 12/17/2010 | 12/21/2010 | P | PART |
Jim Sly
|
|
|
gene - ceiling grid for cover Phone #: ###-#### Select focus rooms OK.
|
BLD-Framing/Rough-in | 11/12/2010 | 11/12/2010 | 11/12/2010 | P | PART |
Jim Sly
|
|
|
Brian Phone #: ###-#### Bldg 1 2nd floor Rooms 121 thru 127 OK
|
BLD-Framing/Rough-in | 11/5/2010 | 11/8/2010 | 11/8/2010 | A | PART |
Jim Sly
|
|
|
gene Phone #: ###-#### Rooms #'s 101 012 103 and 104.......OK
|
Issue PAID IN FULL permit | | | 11/4/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/27/2010 | | DONE |
|
|
|
left vm for scott wendell at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/27/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 10/4/2010 | 10/4/2010 | 10/26/2010 | | PASS |
Dan Stuart
|
|
|
|
Plan resubmittals received | | | 10/26/2010 | | PASS |
|
|
|
SKA #001 & #002 & SKM #001 received and added to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2010 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/21/2010 | | 10/25/2010 | | PASS |
Dan Stuart
|
|
|
Resubmittals from architect, SKA #001 & #002 & SKM-#001 entered into plans and scanned and added to BLD. Plans to permit desk to issue.
|
1st review completed | | | 10/21/2010 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - FIRE | 10/20/2010 | | 10/21/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals requested | | | 10/20/2010 | | DONE |
|
|
|
Copy of plan review e-mailed to architect.
|
Routing - PLAN CHECK | 10/5/2010 | | 10/20/2010 | | FAIL |
Dan Stuart
|
|
|
Copy of plan review e-mailed to architect. Plan routed to fire code analyst for review.
|
Telephone call | | | 10/18/2010 | | DONE |
|
|
|
Called Bruce Dahlstrom, Gensler Arch to discuss what seismic design category was to be used, design details for the suspended ceiling grid system based on design notes, plan details and appropriate CISCA guide to be applied based on ceiling deadload and SDC declared. I will send details for determing requirements per ASCE 7-05, CISCA 0-2 & CISCA 3-4 once design requirements and SDC is determined.
|
Plan Reviewer's activity | | | 10/18/2010 | | DONE |
|
|
|
Sent e-mail to Bruce Dahlstrom with data to determine SDC & CISCA requirements for ACT grid system; question on correct ESR report for adhesive anchors for concrete. copied Scott Wendell, LCA and Sidney Scarboro @ Gensler Arch.
|
Application received | | 10/4/2010 | 10/5/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/4/2010 | | PASS |
Tim L. Woodard
|
|
|
|