Second Notice | | 10/28/2012 | 11/14/2012 | | DONE |
|
|
|
|
First Notice | | 9/28/2012 | 10/18/2012 | | DONE |
|
|
|
mailed
|
BLD-Final | 9/17/2012 | 9/18/2012 | 9/18/2012 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-#### no elec permit needed on this project.
|
FIRE-Final Inspection | 9/17/2012 | 9/18/2012 | 9/18/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety passed inspection- tenant to remove the " 703" address numbers above the west exit door prior to final.
|
Permanent Occupancy | | | 9/18/2012 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 9/17/2012 | 9/17/2012 | 9/17/2012 | P | NR |
Forrest France
|
|
|
|
FIRE-Conference | 9/12/2012 | 9/13/2012 | 9/13/2012 | P | DONE |
Forrest France
|
|
|
On site conference with tenant regarding fire sprinkler coverage and NFPA 13 requirements.
|
BLD-Wall Bracing | 9/5/2012 | 9/6/2012 | 9/6/2012 | P | CANC |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Dave Hannah
|
|
|
|
Permit Ready to Issue | | | 8/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 8/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 8/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | 8/2/2012 | | 8/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/27/2012 | | 8/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/2/2012 | | 8/15/2012 | | FAIL |
Tim L. Woodard
|
|
|
Refer to change marks on the drawings.
|
1st review completed | | | 8/15/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 8/2/2012 | | 8/7/2012 | | PASS |
Scott Arellano
|
|
|
Plans are approved. A separate fire sprinker permit will be required to extend fire sprinkler protection below the new staircase.
|
Payment Received | | | 8/2/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 8/2/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/31/2012 | | FAIL |
Tim L. Woodard
|
|
|
Brandon;
Please upload the Minor Tenant Improvement Checklist into the documents folder. The items that are missing that I can see at this point are structural calculations, a registered design proffesional form, and compliance with the "Upload Submittal Guide" (Specifically the required Stamping area). Please review the checklist and the Upload Submittal Guide and resubmit the drawings.
Thank you,
Tim Woodard
(208) 384 3817
twoodard@cityofboise.org
|
Application received | | | 7/30/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 30 2012 2:14PM
|