Information based on query as of Friday, September 27, 2024.
Permit Information
Permit NumberBLD13-01203
StatusIssued
Name RA SCHULTZ AND COMPANY
Site Address 251 E FRONT ST Unit: 400
Project NameOne Front Buildin
Customer Number 
ePlanReviewYes
Description
(US Ecology)(SUITE 400) Permit to make 2 tenant spaces created under BLD09-01833 and BLD09-01834 back into one suite. Scope of work to include; minor demolition and creating 2 new ADA shower rooms and 1 ADA changing room, removal of walls and doors and repair. Mechanical and electrical work and construction within existing office space to accommodate new tenant all per the approved plans. Interior finishes shall comply with IBC chapter 8. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: a separate permit is required prior to occupying this building. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/27/20136/28/20137/3/2013APART
DetailsDave Hannah
Thanks Matt, Phone #: ###-#### >> Inspection requested via web by Richard Schultzok for temp occ needs to finish installing glass
FIRE-Final Inspection6/26/20136/27/20136/27/2013APASS
DetailsForrest France
Fire life safety inspection passed.
FIRE-Conference6/26/20136/26/20136/26/2013ADONE
DetailsForrest France
Regarding project related FIR trade work
BLD-Framing/Rough-in6/12/20136/13/20136/13/2013APASS
DetailsDave Hannah
Thanks Matt, Phone #: ###-#### >> Inspection requested via web by Richard Schultz
FIRE-Sprinkler Rough-in6/12/20136/12/20136/12/2013APART
DetailsForrest France
Fire sprinkler mods okay to cover at the drop ceilings 4th floor.
Telephone call  6/4/2013 DONE
DetailsChristina Prado
Emailed Lisa fees due once cert of value and gc form were submitted
Permit Ready to Issue  6/4/2013 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  6/4/2013 DONE
DetailsTisha Gallop
Print Occupancy Form  6/4/2013 DONE
DetailsTisha Gallop
Routing - PLAN CHECK5/29/2013 5/29/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  5/29/2013 DONE
Plan assigned to (AJS)5/15/2013 5/29/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed / Due 5/29 Level 2 TI E plan
Routing - FIRE5/15/2013 5/24/2013 FAIL
DetailsTim Frost
e-plan review
Routing - PLAN CHECK5/24/2013 5/24/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see comments in e plan review
Routing - FIRE  5/24/2013 PASS
DetailsTim Frost
1st review completed  5/24/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see e plan review comments
Routing - Addressing5/15/2013 5/17/2013 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS5/15/2013 5/16/2013 PASS
DetailsBeverly Mountain
Routing PW Sewer Rating5/16/2013 5/16/2013 PASS
DetailsConnie Baumgartner
Intake Approval  5/15/2013 PASS
DetailsTim L. Woodard
Payment Received  5/14/2013 DONE
Payment received via Govolutions
Application received  5/14/2013 DONE
Application submitted via PDS Online on May 14 2013 2:21PM