Second Notice | | 7/19/2020 | 8/11/2020 | | DONE |
|
|
|
mailed 8-11-2020
|
First Notice | | 6/22/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Print Occupancy Form | | | 6/12/2020 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/12/2020 | | DONE |
|
|
|
|
BLD-Final | 6/2/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Mike Jordan
|
|
|
Gene *screened* Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. No fire alarm, sprinklers passed.
Gene *screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/19/2020 | 5/20/2020 | 5/20/2020 | A | PASS |
Mike Jordan
|
|
|
Screened -Gene Phone #: ###-####. Ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 5/5/2020 | 5/5/2020 | 5/6/2020 | P | NR |
Mike Jordan
|
|
|
frame // Jean Phone #: ###-####. Needs electrical and frie sprinkler rough in inspections.
|
BLD-Energy code compliance | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Mike Jordan
|
|
|
Gene Phone #: ###-####
|
BLD-Framing/Rough-in | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Mike Jordan
|
|
|
Jean *cleared* Phone #: ###-####. Interior steel stud framed walls and both sides of demissing wall.
|
Permit Ready to Issue | | | 4/17/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
CHANGE STATUS TO (ISS) | | | 4/17/2020 | | DONE |
|
|
|
plan mod approved
|
Plan assigned to (BJM) | 4/10/2020 | 4/10/2020 | 4/16/2020 | | DONE |
Brian McGowan
|
|
|
04/17- Commercial plan mod
|
Routing - PLAN CHECK | 4/16/2020 | | 4/16/2020 | | PASS |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 4/16/2020 | | DONE |
Brian McGowan
|
|
|
Please add (1) hour of Plan Review to this Plan Mod.
|
Plan Modification Accepted | | | 4/10/2020 | | DONE |
|
|
|
New tenant for spec ti is WFI Ranger. See revised title blocks and cover sheet infor related to tenant.
|
Issue PAID IN FULL permit | | | 4/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2020 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 3/31/2020 | 3/31/2020 | 4/8/2020 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2020 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
email fees to ryan@larsonarchitects.biz
Plan Mod cancelled 4/7/2020
ALL MET-
Need:
GC Form
Revised Cert of Value- per Christina 306 submitted on 4-8-2020 okay
|
Route to Impact Fee Review | 3/31/2020 | 4/3/2020 | 4/1/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
CHANGE STATUS TO (REV) | | | 3/31/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/31/2020 | | DONE |
|
|
|
Ryan Drew of Larson architects requested a resubmittal
|
Routing - FIRE | 2/12/2020 | 2/12/2020 | 3/19/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Plan assigned to (BJM) | 2/12/2020 | 2/12/2020 | 3/19/2020 | | DONE |
Brian McGowan
|
|
|
03/10- Franklin Commerce Center Vanilla T.I L-3
|
1st review completed | | | 3/19/2020 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2020 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/19/2020 | | DONE |
|
|
|
NEED GC
REV VALUES
|
Routing - PLAN CHECK | 2/12/2020 | | 3/17/2020 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Solid Waste | 2/13/2020 | | 2/18/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - MECHANICAL | 2/12/2020 | | 2/14/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 2/12/2020 | | 2/13/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - Addressing | 2/12/2020 | | 2/13/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/12/2020 | | 2/13/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - PLANNING | 2/12/2020 | | 2/12/2020 | | PASS |
David Moser
|
|
|
|
Intake Approval | | | 2/7/2020 | | PASS |
|
|
|
|
Application received | | | 2/4/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2020 2:12PM
|
Third Notice | | 8/16/2020 | | | |
|
|
|
|