CHANGE STATUS TO (D) | | | 8/19/1996 | | DONE |
|
|
|
|
INSP - Final | 4/4/1996 | 4/5/1996 | 4/5/1996 | P | PASS |
Carl Dependahl
|
|
|
04/05/96 340 - FINAL REINSPECT. OK
|
INSP - Letter of compliance | 4/5/1996 | 4/5/1996 | 4/5/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 10691
|
INSP - Letter of compliance | 4/5/1996 | 4/5/1996 | 4/5/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - LC 10691
|
INSP - Final | 4/3/1996 | 4/4/1996 | 4/4/1996 | A | FAIL |
Carl Dependahl
|
|
|
04/03/96 340 -
|
INSP - Framing/Rough-in | 1/29/1996 | 1/29/1996 | 1/29/1996 | | PASS |
|
|
|
/ / 333 - FRAM-OK FRAMING
|
INSP - Energy code compliance | 1/29/1996 | 1/29/1996 | 1/29/1996 | P | PASS |
|
|
|
01/29/96 333 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 1/29/1996 | 1/29/1996 | 1/29/1996 | | PASS |
|
|
|
/ / 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 1/26/1996 | 1/26/1996 | 1/26/1996 | P | FAIL |
|
|
|
/ / 338 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OK TO INSULATE
|
Issue PAID IN FULL permit | | | 1/2/1996 | | |
|
|
|
|
Plan Received by (DJO) | 12/5/1995 | | 12/11/1995 | | PASS |
Dan Overy
|
|
|
12/11/95 08:16:53 335 - this action updated by action script from <<>> in Case No. BLD95-2100
|
INSP - Foundation | 12/5/1995 | 12/5/1995 | 12/5/1995 | | PASS |
|
|
|
/ / 333 - FDN -OK FOUNDATION
|
INSP - Foundation | 12/5/1995 | 12/5/1995 | 12/5/1995 | | PASS |
|
|
|
/ / 333 - FDN -OK FOUNDATION
|
INSP - Footings | 12/4/1995 | 12/5/1995 | 12/5/1995 | A | PASS |
|
|
|
12/04/95 333 - FTG -OK FOOTING
|
Inspection Record Card- Bld | | | 12/5/1995 | | |
|
|
|
|
Permit taken to Permit Desk | | | 12/5/1995 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | | | 12/5/1995 | | PASS |
|
|
|
12/05/95 10:53:24 DJO - this action updated by action script from <<>> in Case No. BLD95-2100
|
Print Pending Permit.LaserJet4 | | | 12/5/1995 | | |
|
|
|
|
Dwelling recd. by Plan Check | | | 12/1/1995 | | |
|
|
|
|
Plan Reviewer's Copy of Permit | | | 12/1/1995 | | |
|
|
|
|
Application received | | | 11/28/1995 | | |
|
|
|
|