Permanent Occupancy | | 3/13/1997 | 3/13/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/13/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6808 issued 3-13-97 to the Pizza Hut.
|
INSP - Final | 3/12/1997 | 3/12/1997 | 3/12/1997 | | PASS |
|
|
|
/ / 333 - card signed for perm
|
INSP - Final | 3/10/1997 | 3/11/1997 | 3/10/1997 | P | NR |
|
|
|
03/11/97 333 - FINAL FOR C/O mech not signed ì
|
Routing for occupancy | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
|
|
|
Art Yingling insp. - meets compliance w/DR-32-96/CU-1196 Signed Final Occ.
|
INSP - Temporary occupancy | | | 1/10/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3340 issued 1-8-97 to the Pizza Hut.
|
INSP - Final | 1/2/1997 | 1/7/1997 | 1/7/1997 | A | PASS |
|
|
|
01/07/97 333 - card signed for temp OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Final | 1/6/1997 | 1/7/1997 | 1/7/1997 | A | PASS |
|
|
|
address posted, fe installed, elec cond covered
|
INSP - Temporary occupancy | 1/6/1997 | 1/7/1997 | 1/7/1997 | | PASS |
|
|
|
Art Yingling inspected - Bonded for landscaping & sprinkler system $10,250.00 - Temp. Occ. signed
|
INSP - Partial final | 1/6/1997 | 1/7/1997 | 1/7/1997 | P | CANC |
Carl Dependahl
|
|
|
01/07/97 340 - FOR T/O GIVEN TO 342
|
INSP - Final | 12/30/1996 | 12/31/1996 | 12/31/1996 | A | FAIL |
|
|
|
12/31/96 333 - OTH-OTHER AGENCIES NOT APPROVED CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 12/26/1996 | 12/26/1996 | 12/26/1996 | P | FAIL |
|
|
|
need fire extinguisher, address, cover exposed elec conductors
|
INSP - Ceiling grid | 12/18/1996 | 12/19/1996 | 12/18/1996 | A | PART |
Wes Worcester
|
|
|
given to Allen and all was done except slack wires to lights
|
INSP - Framing/Rough-in | 12/9/1996 | 12/9/1996 | 12/9/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Carpentry | 12/2/1996 | 12/2/1996 | 12/2/1996 | P | PASS |
Wes Worcester
|
|
|
shr nailing ok
|
INSP - Framing/Rough-in | 11/27/1996 | 12/2/1996 | 12/2/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Conference | 12/2/1996 | 12/2/1996 | 12/2/1996 | P | PASS |
Wes Worcester
|
|
|
bcec does not apply, go forth w/insulation after other inspections and call for frame when done w/insulation
|
INSP - Foundation | 10/21/1996 | 10/22/1996 | 10/22/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Footings | 10/18/1996 | 10/18/1996 | 10/18/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Footings | 10/15/1996 | 10/16/1996 | 10/16/1996 | A | PART |
Wes Worcester
|
|
|
10/16/96 342 - FOOTING REBAR ì
|
INSP - Footings | 10/15/1996 | 10/15/1996 | 10/15/1996 | P | FAIL |
Wes Worcester
|
|
|
10/15/96 342 - cover, plan, spec insp not on site
|
(F) Reprint permit | | | 10/7/1996 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/4/1996 | | |
|
|
|
|
Telephone call | | | 8/2/1996 | | |
|
|
|
DAVID MOE/9:46
|
ISSUE OCCUPANCY FORM | | | 7/31/1996 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/31/1996 | | |
|
|
|
|
Permit taken to Permit Desk | | | 7/30/1996 | | PASS |
|
|
|
PLANS GIVEN TO DAR FOR FORWARDING TO FRONT DESK. MO
|
Plan Reviewer's Copy of Permit | | | 7/30/1996 | | PASS |
|
|
|
|
Received Certificate of Value | | | 7/29/1996 | | PASS |
|
|
|
CERTIFICATE OF VALUE RECEIVED FROM DAIVD MOE OF C.M. COMPANY.
|
Plan resubmittals received | | | 6/28/1996 | | PASS |
|
|
|
resubmittal for cold box receieved and approved.
|
Plan Received by (M_O) | 6/17/1996 | | 6/28/1996 | | PASS |
|
|
|
plan check corrections mailed and faxed to architect and sent to fire 6-18-96. MO
|
Waiting for Cert. of Value | | | 6/28/1996 | | PASS |
|
|
|
CALLED DAIVD AT CM COMPANY FOR FINAL CERTIFICATE OF VALUE.
|
Routing Off Site - STRUCTURAL | 6/6/1996 | | 6/21/1996 | | PASS |
|
|
|
PACKAGE #3 RETURNED AND REVIEWED BY ATWOOD HINZMAN AND JONES.
|
INSP - Miscellaneous | | | 6/20/1996 | | PEND |
|
|
|
structural resubmittal faxed and mailed back to Attwood- Hinzman-Jones for review. 6-20-96 MO
|
INSP - Miscellaneous | | | 6/20/1996 | | PEND |
|
|
|
FAXED AND SENT COPY OF RESPONSE TO ARCHITECT REGARDING WALK-IN COLLER PROVIEDED IN RESUBMITTAL PACKAGE RECEIVED ON 6-20-96.
|
Plan resubmittals received | | | 6/20/1996 | | PEND |
|
|
|
PLAN RESUBMITTALS RECEIVED FOR BUILDING AND STRUCTURAL PLAN CHECK COMMENTS. PREMANUFACTURED WALK-IN BOX UNACCEPTALBE AS SUBMITTED.
|
Routing - FIRE | 6/18/1996 | | 6/19/1996 | | PASS |
|
|
|
|
Unassigned to Plan Reviewer | 5/23/1996 | | 6/17/1996 | | PEND |
|
|
|
|
Routing - PLANNING | 6/14/1996 | | 6/17/1996 | | PASS |
|
|
|
PACKAGE #2 RESUBMITTAL FOR P&Z. TEMPRA WILSON REQUESTING EXTERIOR ELEVATIONS. X-ref: CU-11-96,DR-32-96. Approved by RLB & TKW.
|
Plan resubmittals received | | | 6/17/1996 | | PASS |
|
|
|
RESUBMITTALS RECEIVED FOR PACKAGE #2. ROUTED TO P&Z TO TEMPRA WILSON
|
Plan resubmittals received | | | 6/14/1996 | | PEND |
|
|
|
SENT TO TEMPRA WILSON AS REQUESTED 6-14-96 FOR PACKAGE #1
|
Routing - PLUMBING | 6/11/1996 | | 6/13/1996 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PUBLIC WORKS | 6/12/1996 | | 6/12/1996 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/6/1996 | | 6/7/1996 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN. PACKAGE 2
|
Routing - ELECTRICAL | 6/6/1996 | | 6/7/1996 | | PASS |
|
|
|
PACKAGE 1 PLUMB. ELEC. MECH. FIRE PC. WILL FIELD REVIEW .6/7/96 DAR
|
Routing - PLANNING | 6/3/1996 | | 6/6/1996 | | PASS |
|
|
|
PACKAGE 2 CDH, PW, P&Z Design Review staff need revised plans per DR conditions. Reviewed by RLB & TKW.
|
Routing - MECHANICAL | 5/30/1996 | | 6/6/1996 | | PASS |
|
|
|
PACKAGE 1 PLUMB. ELEC. MECH. FIRE PC.
|
Routing Off Site - A.C.H.D | 5/23/1996 | | 5/31/1996 | | PASS |
|
|
|
PACKAGE 4 ACHD. CONTACTED STRITE AT ###-####
|
Routing Off Site - C.D.H | 5/24/1996 | | 5/31/1996 | | PASS |
|
|
|
PACKAGE 2 CDH, PW, P&Z. CONTACTED BILLY RAE STRITE AT ###-#### FOR CDH PICKUP.
|
Routing Off Site - STRUCTURAL | 5/24/1996 | | 5/30/1996 | | FAIL |
|
|
|
PACKAGE 3 TO ATWOOD HINZMAN JONES VIA PDQ RETURNED BY ATWOOD HINZMAN JONES REQUESTED UPDATED ENGINEERING. GAVE PLANS TO BOB FOR ACTION.
|
Routing - PLUMBING | 5/24/1996 | | 5/29/1996 | | FAIL |
|
|
|
PACKAGE 1 PLUMB. ELEC. MECH. FIRE PC.
|
Plan routing begun/NEW & ADDTN | | | 5/24/1996 | | PASS |
|
|
|
|
GAY'S RECEIPT FOR PARTIAL PAY | | | 5/23/1996 | | |
|
|
|
|
Application received | | | 5/23/1996 | | |
|
|
|
|
Routing - BUILDING | 6/6/1996 | | | | PEND |
|
|
|
PACKAGE 4 TO PC O6-06-96
|
Routing - BUILDING | 6/11/1996 | | | | PEND |
|
|
|
PACKAGE #2
|
Routing - BUILDING | 6/7/1996 | | | | PEND |
|
|
|
package #1
|
Routing - BUILDING | 6/13/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 6/13/1996 | | | | PASS |
|
|
|
|
Routing - BUILDING | 6/14/1996 | | | | PEND |
|
|
|
PACKAGE #3 RETURNED AND REVIEWED FROM ENGINEERING
|
Routing - BUILDING | 6/19/1996 | | | | PEND |
|
|
|
|
Routing - BUILDING | 6/18/1996 | | | | PEND |
|
|
|
|