Code Occupancy Approval | | | 3/18/1998 | | PASS |
|
|
|
Inspected for Final - meets compliance w/ DR-93-96 (CU-44-96). Executed Bond Releae CAM.
|
INSP-Final Inspection | 3/4/1998 | 3/6/1998 | 3/6/1998 | A | PASS |
Joe Tawney
|
|
|
03/06/98 406 - YOU SCHEDULED THIS WITH TIM FOR 9:00--TIM ###-#### BEEP 0 FINAL OK FOR CERT OF COMPLETION
|
Routing for occupancy | 12/18/1997 | | 12/17/1997 | | PEND |
|
|
|
Bond posted: $14,450.00 12/16/97. CU-44-96, DR-93-96.
|
INSP - Final | 12/9/1997 | 12/11/1997 | 12/11/1997 | A | PART |
|
|
|
12/11/97 338 - c/n not left on jobsite
|
INSP-Final Inspection | 12/9/1997 | 12/9/1997 | 12/9/1997 | P | PART |
Rick Jackson
|
|
|
site work parking/excavation permit. signed temp occ. will have to review fire lane markings after construction trailers, etc are out.
|
Print Occupancy Form | | | 12/4/1997 | | |
|
|
|
|
INSP - Footings | 8/8/1997 | 8/11/1997 | 8/11/1997 | A | NR |
|
|
|
08/11/97 336 -
|
INSP - Footings | 8/5/1997 | 8/5/1997 | 8/5/1997 | P | NR |
|
|
|
08/05/97 338 - TRASH ENCLOSURES met contractor
|
(F) Reprint permit | | | 4/28/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/28/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/23/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/1997 | | PASS |
|
|
|
PERMIT AND CERTIFICATE OF VALUE TAKEN TO THE FRONT DESK FOR SITE IMPROVEMENT PERMIT ONLY.
|
Inspection Record Card- Bld | | | 4/23/1997 | | |
|
|
|
|
Telephone call | | | 4/23/1997 | | |
|
|
|
TOLD AMY PERMIT IS READY
|
Application received | | | 4/23/1997 | | |
|
|
|
|
Print Occupancy Form | | | 4/23/1997 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|