Letter of compliance | | | 8/4/2000 | | DONE |
|
|
|
Letter of Compliance #18534 issued 8-4-00.
|
INSP-Final Inspection | 6/4/1999 | 6/7/1999 | 6/7/1999 | A | PASS |
Rick Jackson
|
|
|
Joe ###-#### occ approved
|
INSP-Final Inspection | 4/8/1999 | 4/9/1999 | 4/9/1999 | P | FAIL |
Rick Jackson
|
|
|
###-#### JOE exit sign not installed
|
INSP-Final Inspection | 3/23/1999 | 3/24/1999 | 3/24/1999 | A | FAIL |
Rick Jackson
|
|
|
###-#### JOE//FINAL FIRE FAB 1X detector released door hold open but door hardware not complete
|
INSP - Final | 3/23/1999 | 3/24/1999 | 3/24/1999 | A | FAIL |
Jim Storey
|
|
|
03/24/99 301 - n/r
|
INSP-Final Inspection | 3/22/1999 | 3/23/1939 | 3/22/1999 | P | |
Rick Jackson
|
|
|
joe ###-####
|
INSP - Framing/Rough-in | 3/22/1999 | 3/23/1939 | 3/22/1999 | P | |
Jim Storey
|
|
|
joe ###-####
|
INSP - Framing/Rough-in | 3/18/1999 | 3/19/1999 | 3/19/1999 | A | CANC |
Jim Storey
|
|
|
03/19/99 301 - ###-#### JOE//RI FRAMING FAB 1X joe called and cancled
|
INSP-Final Inspection | 3/18/1999 | 3/19/1999 | 3/19/1999 | A | NR |
Rick Jackson
|
|
|
03/19/99 409 - ###-#### JOE//FINAL FIRE FAB 1X door hold open not ready with detection
|
INSP - Framing/Rough-in | 3/17/1999 | 3/18/1999 | 3/18/1999 | A | PASS |
Jim Storey
|
|
|
03/18/99 301 - FRST-OPENING PROTECTION OK
|
INSP - Framing/Rough-in | 3/10/1999 | 3/11/1999 | 3/11/1999 | A | PASS |
Jim Storey
|
|
|
03/11/99 301 - FRAM-OK FRAMING
|
90 day tracking............. | | 9/26/1997 | 12/25/1997 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 10/27/1997 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 10/16/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/1997 | | PASS |
|
|
|
|
Telephone call | | | 10/14/1997 | | |
|
|
|
CALLED DAVE PERMIT READY
|
Inspection Record Card- Bld | | | 10/14/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 10/14/1997 | | 10/14/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/14/1997 | | |
|
|
|
|
Plan assigned to (JCM) | 9/30/1997 | | 10/14/1997 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 10/8/1997 | | 10/13/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/3/1997 | | 10/8/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/8/1997 | | PASS |
|
|
|
PLANS REVIEWED AND APPROVED AS SUBMITTED WITH ATTACHED CITY COMMENT LIST.
|
Routing - PUBLIC WORKS | 9/30/1997 | | 10/1/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 9/26/1997 | | 9/30/1997 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 9/30/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 9/30/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 9/30/1997 | | PASS |
|
|
|
|
Application received | | | 9/26/1997 | | |
|
|
|
|