INSP - Letter of compliance | 1/26/1998 | 1/26/1998 | 1/26/1998 | | PASS |
Tom Arcoraci
|
|
|
/ / 409 -
|
INSP - Final | 1/22/1998 | 1/26/1998 | 1/26/1998 | P | PASS |
Tom Arcoraci
|
|
|
01/26/98 409 - someone will be there dean ###-####
|
INSP - Letter of compliance | 1/26/1998 | 1/26/1998 | 1/26/1998 | | PASS |
Tom Arcoraci
|
|
|
/ / 409 -
|
INSP - Energy code compliance | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | PASS |
Jim Sly
|
|
|
01/06/98 316 -
|
INSP - Framing/Rough-in | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | PASS |
Jim Sly
|
|
|
01/06/98 316 - REINSPECTION
|
INSP - Framing/Rough-in | 1/2/1998 | 1/5/1998 | 1/5/1998 | A | FAIL |
Jim Sly
|
|
|
01/02/98 316 - C/N...Need approv plans ..verify shear bracing...
|
INSP - Footings | 12/9/1997 | 12/10/1997 | 12/10/1997 | A | FAIL |
Jim Sly
|
|
|
12/09/97 316 - Footing and walls poured W/O inspection..No plans on site
|
Issue PAID IN FULL permit | | | 12/4/1997 | | |
|
|
|
|
Telephone call | | | 12/3/1997 | | |
|
|
|
called and left message on recorder
|
Inspection Record Card- Bld | | | 12/3/1997 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 12/2/1997 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 12/2/1997 | | PASS |
|
|
|
CONTRACTOR SUBMITTED ROOF FRAME AND CHANGE AT WING WALL LOCATION.
|
Print Pending Permit.LaserJet4 | | | 12/2/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/2/1997 | | PEND |
|
|
|
CALLED DEAN BORUP. WILL SUBMIT REVISIONS FOR GARAGE WING WALLS OR PROVIDE ENG. ROOF FRAME LAYOUT NEEDED.
|
Plan assigned to (DJO) | 11/19/1997 | | 12/2/1997 | | PASS |
Dan Overy
|
|
|
12/02/97 16:02:13 DJO - this action updated by action script from <<>> in Case No. BLD97-3476
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 11/20/1997 | | 11/20/1997 | | PASS |
|
|
|
APPROVED BY RW.
|
Routing - PUBLIC WORKS | 11/19/1997 | | 11/20/1997 | | PASS |
|
|
|
|
Application received | | | 11/19/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 11/20/1997 | | | | PEND |
|
|
|
|