Permanent Occupancy | | 7/17/1998 | 7/17/1998 | | DONE |
|
|
|
|
INSP - Final | 7/17/1998 | 7/17/1998 | 7/17/1998 | A | PASS |
|
|
|
|
INSP-Final Inspection | 7/16/1998 | 7/17/1998 | 7/17/1998 | A | PASS |
Rick Jackson
|
|
|
t.i. reinspect exit signs les abston ###-#### occ approved
|
Permanent occupancy | | | 7/17/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7323 issued 7-17-98 to Christian Life Ministries.
|
INSP-Final Inspection | 7/13/1998 | 7/14/1998 | 7/14/1998 | A | FAIL |
Rick Jackson
|
|
|
Les ###-#### exit signs as shown on plans
|
INSP - Final | 6/30/1998 | 7/2/1998 | 7/2/1998 | A | FAIL |
|
|
|
07/02/98 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 5/12/1998 | 5/13/1998 | 5/13/1998 | A | PASS |
|
|
|
05/13/98 333 - frame ok
|
INSP-Conference | 5/6/1998 | 5/6/1998 | 5/6/1998 | P | PASS |
|
|
|
05/06/98 333 - this is for frank/confirmed appt w/you 1:45-2:00-###-#### he will met you there/he said he talked to you/and you have an appt. with him.
|
90 day tracking............. | | 2/4/1998 | 5/5/1998 | | PEND |
|
|
|
|
INSP - Framing/Rough-in | 3/16/1998 | 3/16/1998 | 3/16/1998 | A | PART |
Carl Dependahl
|
|
|
333 area, demising walls ok, if elec ok
|
INSP - Framing/Rough-in | 3/13/1998 | 3/16/1998 | 3/16/1998 | A | FAIL |
|
|
|
03/16/98 333 - given to carl he wrote cnSCHEDULED FOR 9:30--LES ###-####
|
Issue PAID IN FULL permit | | | 2/24/1998 | | |
|
|
|
|
Plan assigned to (DRS) | 2/5/1998 | | 2/23/1998 | | PASS |
Dan Stuart
|
|
|
02/23/98 15:01:36 DRS - this action updated by action script from <<>> in Case No. BLD98-0263
|
Telephone call | | | 2/23/1998 | | |
|
|
|
Call to Lester Abston, Christian Life Ministries, inquiring about pre-plan he had with CDH concerning preparation & selling of coffee. Mr. Abston stated the church can not afford to install health dept. items at this time so the coffee service area will not be installed at this time and he understands that separate plans, etc. will be required for review by CDH, PW & Plan Review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/23/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/23/1998 | | 2/23/1998 | | PASS |
|
|
|
|
Meeting | | | 2/23/1998 | | |
|
|
|
Mr. Abston provided me with a new letter indicating he understands that the sale of on-site prepared beverages cannot be a part of this project approval and separate plans & approvals are required prior to use of the Retail/Office Area, Room 286, for such use. Letter in file. Copy given to CDH.
|
Inspection Record Card- Bld | | | 2/23/1998 | | |
|
|
|
|
Telephone call | | | 2/23/1998 | | |
|
|
|
CALLED GAVE DOLLAR AMOUNT-JENNELL
|
Telephone call | 2/23/1998 | | 2/23/1998 | | |
|
|
|
|
Print Occupancy Form | | | 2/23/1998 | | |
|
|
|
|
Plan resubmittals received | | | 2/20/1998 | | |
|
|
|
RECEIVED ONE REVISED CERT. OF VALUE. ONE COPY OF LETTER OF RESPONSE AND 3 COPIES OF PLANS. ONE COPY OF LETTER FROM ACHD. ROUTED TO DAN STAURT. KMM
|
Routing - PLAN CHECK | 2/19/1998 | | 2/20/1998 | | PEND |
|
|
|
Waiting to verify with Mr. Lester Abston concerning approval of the coffee preparation and sales at the new facility.
|
Received Certificate of Value | | | 2/20/1998 | | |
|
|
|
|
Telephone call | | | 2/19/1998 | | |
|
|
|
Call to Bart Miller to let him know I had received plans back from Public Works and needed new submittals for review to process for permit.
|
Telephone call | | | 2/19/1998 | | |
|
|
|
Call to Lester Abston, Minister, after Bart had said the plans were taken to him for resubmittal. Mr. Abston said he had brought plans in to Dave Radford this day. They evidently have not been processed yet.
|
Plan resubmittals received | | | 2/19/1998 | | |
|
|
|
Received corrected plans from Bart Miller, Architect.
|
Routing Off Site - A.C.H.D | 2/18/1998 | | 2/18/1998 | | PASS |
|
|
|
RECEIVED A LETTER FROM MARCUS GREEN (GRADING PERMIT) CONSTRUCTION CAN PROCEED. NO IMPACT FEE DUE WITH THIS PROJECT.
|
Routing - PUBLIC WORKS | 2/11/1998 | | 2/18/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/7/1998 | | 2/11/1998 | | PEND |
|
|
|
Correction list mailed to Bart Miller. Had talked with him on phone on 2-10-98.
|
Print Pending Permit.LaserJet4 | | | 2/11/1998 | | |
|
|
|
|
Plan resubmittals requested | | | 2/11/1998 | | |
|
|
|
|
Telephone call | | | 2/11/1998 | | |
|
|
|
Called and talked to Mr. Miller concerning corrections needed for review prior to issuance of building permit.
|
Print Pending Permit.LaserJet4 | | | 2/11/1998 | | PEND |
|
|
|
|
Plan assigned to (MYS) | 2/4/1998 | | 2/5/1998 | | |
Marlene Southard
|
|
|
|
Application received | | | 2/4/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 2/4/1998 | | | | PEND |
|
|
|
|