Fee Review-notes | 7/22/1998 | | 3/15/1999 | | DONE |
|
|
|
ADDITIONAL VALUE PER LETTER FROM MULVANNY PARTNERSHIP THAT ELECT VALUE WENT UP LH
|
Permanent occupancy | | | 2/19/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7645 issued 2-19-99 to Costco Wholesale.
|
Permanent Occupancy | | 2/2/1999 | 2/2/1999 | | DONE |
|
|
|
|
INSP - Final | 12/9/1998 | 12/9/1998 | 12/9/1998 | | PASS |
|
|
|
12/09/98 338 - madeok for occ.
|
SUPER- Supervisor's review | 12/8/1998 | 12/8/1998 | 12/8/1998 | | |
|
|
|
site review and timetable for compliance for high pile storage due today.
|
SUPER- Supervisor's review | 12/7/1998 | 12/7/1998 | 12/7/1998 | | |
|
|
|
lowering stock in progress, also cutting platic covering from accross mechandise to all water to penitrate plallots. 3 inch seperation between palots ok.
|
SUPER- Supervisor's review | 12/7/1998 | 12/4/1998 | 12/4/1998 | | |
|
|
|
floyd varley joe tawney bill alexander and myself met with manager and told him to start lowering stock height in racks to 20 feet per thier approved drawings. We will check monday to see how it is comming.
|
INSP-Conference | 12/4/1998 | 12/4/1998 | 12/4/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH STORE MGR & GEORGE,FLOYD,& BILL ON HIGH PILED STOR
|
SUPER- Supervisor's review | 12/3/1998 | 12/2/1998 | 12/2/1998 | | |
|
|
|
floyd varley and i reviewed site for overheight high piled storage. engineered design was approved at their request for 20 feet height. They are storing in excess of 20 feet and have notice to reduce to allowed height limit.
|
INSP-Final Inspection | 11/23/1998 | 11/23/1998 | 11/23/1998 | P | FAIL |
Rick Jackson
|
|
|
DALE ###-#### all items from 406's c/n wern't completed
|
Code Occupancy Approval | | | 11/23/1998 | | |
|
|
|
Final Occupancy requested by Dale-###-####
|
Code Occupancy Approval | | | 11/23/1998 | | PASS |
|
|
|
Meets compliance with CUP97-0118 - Signed Final on Occupancy Card
|
INSP-Conference | 10/27/1998 | 10/27/1998 | 10/27/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - conf with Dale contr to deliver correction notices from 10/2
|
INSP - Final | 10/23/1998 | 10/26/1998 | 10/26/1998 | P | NR |
|
|
|
10/26/98 338 - MADE OK FOR STR TEMP BUT OTHER AGENCIES NOT APPROVED YET.
|
INSP-Final Inspection | 10/23/1998 | 10/26/1998 | 10/26/1998 | A | FAIL |
Joe Tawney
|
|
|
10/26/98 406 - DALE ###-#### FINAL FAIL SPKLR SYSTEM ISSUES EXIT DOOR EMERG LIGHTS FIRE EXT ACCESS ì
|
INSP-Sprinkler Rough-in/Hydro | 10/16/1998 | 10/16/1998 | 10/16/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST FOR WHSE EXPANSION SW CORNER
|
INSP-Sprinkler Rough-in/Hydro | 10/8/1998 | 10/8/1998 | 10/8/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ROUGH IN OF SMALL ROOMS NEAR LOADING DOCK
|
INSP - Framing/Rough-in | 10/6/1998 | 10/7/1998 | 10/7/1998 | P | PART |
|
|
|
10/07/98 338 - made ok to cover
|
INSP - Framing/Rough-in | 10/1/1998 | 10/2/1998 | 10/5/1998 | A | PART |
|
|
|
10/05/98 338 - made ok to cover roof
|
INSP - Framing/Rough-in | 10/2/1998 | 10/2/1998 | 10/2/1998 | | PART |
|
|
|
10/02/98 338 - MADE OK TO DRY IN AND COVER ROOF NAILING MADE OK
|
INSP - Framing/Rough-in | 9/16/1998 | 9/16/1998 | 9/16/1998 | P | PART |
|
|
|
09/17/98 338 - made ok to cover with ele div approval
|
INSP - Framing/Rough-in | 9/16/1998 | 9/16/1998 | 9/16/1998 | P | FAIL |
Carl Dependahl
|
|
|
338 area; Costco. Framing at new office area. Need seismic & bracing at ceiling grid & partitions. no resubmittal req'd. c/n
|
INSP - Framing/Rough-in | 9/3/1998 | 9/3/1998 | 9/3/1998 | P | PART |
|
|
|
09/03/98 338 - made ok to cover wth eleapproval
|
INSP - Framing/Rough-in | 8/31/1998 | 9/1/1998 | 9/1/1998 | A | PASS |
|
|
|
CEILING GRID OPTIACAL / ###-####
|
INSP - Framing/Rough-in | | | 9/1/1998 | | PART |
|
|
|
09/01/98 338 - CEILING GRID OPTIACAL / ###-#### MADE OK
|
INSP - Framing/Rough-in | 8/18/1998 | 8/19/1998 | 8/19/1998 | P | PART |
|
|
|
08/19/98 338 - ok to cover with ele blessing
|
CHANGE STATUS TO (I) | | | 8/18/1998 | | |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 8/18/1998 | | |
|
|
|
|
INSP - Framing/Rough-in | 8/10/1998 | 8/10/1998 | 8/10/1998 | | PART |
|
|
|
/ / 338 - PART FRAMING AND JOB SCHEDULE WALK THROUGH
|
(F) Reprint permit | | | 8/5/1998 | | |
|
|
|
|
INSP - Framing/Rough-in | 7/28/1998 | 7/29/1998 | 7/29/1998 | P | PART |
|
|
|
07/29/98 338 - made ok to pour with sp insp approval
|
CHANGE STATUS TO (F) | | | 7/29/1998 | | |
|
|
|
|
CHANGE STATUS TO (F) | | | 7/28/1998 | | |
|
|
|
|
INSP - Foundation | 7/23/1998 | 7/23/1998 | 7/23/1998 | P | |
|
|
|
SOILS TEST THIS AFTERNOON MTI IS DOING IT
|
INSP - Foundation | 7/22/1998 | 7/22/1998 | 7/22/1998 | P | PART |
|
|
|
07/22/98 338 - made ok with sp insp approval
|
Plan resubmittals received | | | 7/20/1998 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS, CONFERRED WITH JOHN L. AN FORWARDED PLANS TO PERRY PAINE.
|
90 day tracking............. | | 4/20/1998 | 7/19/1998 | | PEND |
|
|
|
|
Issue PAID IN FULL permit | | | 6/29/1998 | | |
|
|
|
|
Telephone call | | | 6/19/1998 | | PASS |
|
|
|
TALKED TO KEN WONG AT ###-#### TO VERIFY PLANS ARE READY
|
Print Occupancy Form | | | 6/19/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/19/1998 | | |
|
|
|
|
Plan assigned to (JML) | 4/28/1998 | | 6/18/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/18/1998 | | 6/18/1998 | | PASS |
|
|
|
approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/18/1998 | | PASS |
|
|
|
approved
|
Plan resubmittals received | | | 6/17/1998 | | PEND |
|
|
|
RECEIVED RESUBS FROM KEN WONG, FORWARDED SAME TO JOHN LEVIEN.
|
Plan resubmittals received | | | 6/12/1998 | | PEND |
|
|
|
RECEIVED RESUBS FROM KEN WONG FORWARDED SAME TO JOHN LEVIEN
|
Routing - PLAN CHECK | 6/2/1998 | | 6/12/1998 | | FAIL |
|
|
|
arch. needs to address smoke vent # and placement and creation on a mezzanine area over the new restrooms. Contacted by phone will sent findings by fax.
|
Routing - PUBLIC WORKS | 6/1/1998 | | 6/1/1998 | | PASS |
|
|
|
|
Routing - FIRE | 5/18/1998 | | 5/26/1998 | | PASS |
|
|
|
|
Routing - PLUMBING | 5/7/1998 | | 5/11/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/6/1998 | | 5/7/1998 | | FAIL |
|
|
|
NEED TO TALK TO MATT M ABOUT LOADING DOCK DRAINAGE PER BRIAN M.
|
Routing - PLANNING | 4/29/1998 | | 5/5/1998 | | PASS |
|
|
|
DRH97-0231
|
Plan resubmittals received | | | 5/4/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS AND TAKEN TO JOHN L.
|
Routing - PLANNING | 4/29/1998 | | 5/1/1998 | | PASS |
|
|
|
X-REF FILE IS CUP97-0118 WHICH IS A MODIFICATION OF CU-16-88. SENT ON TOP DESIGN REVIEW X-REF DRH97-0137
|
Plan resubmittals received | | | 5/1/1998 | | PEND |
|
|
|
RECEIVED RESUBGS FROM KEN WONG, PASSED SAME TO JOHN L.
|
Plans ACCEPTED BY PLAN CHECK | | | 4/28/1998 | | PEND |
|
|
|
|
Plan assigned to (MYS) | 4/20/1998 | | 4/28/1998 | | PASS |
Marlene Southard
|
|
|
|
Application received | | | 4/20/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/20/1998 | | PEND |
|
|
|
|
INSP-Final Inspection | 1/28/1999 | 1/28/1998 | 1/28/1998 | | PASS |
|
|
|
REINSP OK FOR CERT OF COMPLETION
|
Routing - PLAN CHECK | 5/11/1998 | | 5/18/1989 | | FAIL |
|
|
|
SENDING PC FINDINGS TO ARCH BY FAX AND MAIL. NEEDS ARCH. RESUBMITTALS.
|