90 day tracking............. | | 5/1/1998 | 7/30/1998 | | PEND |
|
|
|
|
INSP - Final | 7/21/1998 | 7/23/1998 | 7/23/1998 | A | PASS |
Jim Storey
|
|
|
07/22/98 301 - RON ISAACS AT ###-#### FOR FN INSP. LEAVE LETTER OF COMPL FNL -OK FINAL l/c for mech screen
|
INSP - Framing/Rough-in | 6/22/1998 | 6/23/1998 | 6/23/1998 | A | PASS |
|
|
|
06/23/98 333 - FRAM-OK FRAMING
|
Issue PAID IN FULL permit | | | 6/8/1998 | | |
|
|
|
|
Telephone call | | | 6/8/1998 | | PASS |
|
|
|
talked to ronald issac to verify plans are ready
|
Inspection Record Card- Bld | | | 6/5/1998 | | |
|
|
|
|
Plan assigned to (JML) | 5/4/1998 | | 6/3/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/3/1998 | | PAS |
|
|
|
approved
|
Plan resubmittals received | | | 6/3/1998 | | PEND |
|
|
|
RECEIVED RESUBS FROM DENNIS SUNBERG. FORWARDED SAME TO JOHN LEVIEN.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/3/1998 | | 6/3/1998 | | PASS |
|
|
|
|
Meeting | | | 5/28/1998 | | FAIL |
|
|
|
I met with Dennis Sunberg the arch to address the plan reveiw findings. Dennis will provide further information.
|
Routing - PLAN CHECK | 5/11/1998 | | 5/22/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 5/4/1998 | | 5/11/1998 | | PASS |
|
|
|
approved per czc98-0048. Condition 1a does apply for mechanical screening; however, signage is not allowed on screening structure unless the plans are revised per condition 1a.
|
Plan routing begun/TENANTS | | | 5/4/1998 | | |
|
|
|
Route to PLANNING then PLAN CHECK.
|
Plan assigned to (MYS) | 5/1/1998 | | 5/4/1998 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/1998 | | PEND |
|
|
|
|
Application received | | | 4/30/1998 | | |
|
|
|
|