Permanent Occupancy | | | 4/7/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/4/2011 | | |
|
|
|
|
Case Summary (BLD) | | | 10/3/2011 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/5/1999 | | DONE |
|
|
|
|
Letter of compliance | | | 7/21/1999 | | PASS |
|
|
|
letter of comp. issued to iceworld-rink tenant as per bob 7/21/99-l/c #17883
|
INSP - Final | 7/20/1999 | 7/20/1999 | 7/20/1999 | P | PASS |
Russ Owen
|
|
|
07/20/99 407 - this has been approved at prior date,has several permits.
|
INSP-Final Inspection | 7/20/1999 | 7/20/1999 | 7/20/1999 | P | PASS |
Rick Jackson
|
|
|
phil ###-#### occ approved
|
Code Occupancy Approval | | | 7/15/1999 | | PASS |
|
|
|
ALL CONDITIONS OF DRH97-0236 HAVE BEEN MET SO FINAL OCCUPANCY SIGNED OFF, ALSO I RELEASED THE BOND.
|
Fee Review-notes | 11/25/1998 | | 3/31/1999 | | MESS |
|
|
|
Linda there are some big differences in values here.
|
INSP - Final | 3/10/1999 | 3/11/1999 | 3/11/1999 | A | FAIL |
Russ Owen
|
|
|
03/11/99 407 - phil ###-####
|
INSP - Final | 3/4/1999 | 3/4/1999 | 3/4/1999 | A | FAIL |
Russ Owen
|
|
|
CORRECTIONS.
|
INSP-Final Inspection | 2/25/1999 | 2/26/1999 | 2/26/1999 | A | NR |
Jim Storey
|
|
|
02/26/99 301 - 407 is not able to do this today. NO PLAN ON SITE OR SIGN
|
Code Occupancy Approval | | | 1/6/1999 | | FAIL |
|
|
|
ALL REQUIREMENTS HAVE NOT BEEN COMPLETED, A BOND FOR $304,474 HAS BEEN POSTED WITH CATHY AND TEMPORARY SIGNED FOR. REQUEST TO REDUCE BOND, LOTS OF WORK HAS BEEN COMPLETED AND FAXED OVER A NEW BID TO COMPLETE, MOST WORK INVOLVES LANDSCAPE, AFTER SITE INSPECTION NEW BONDING AMOUNT OF $91,177 OKED.(01/06/99)
|
INSP-Final Inspection | 12/4/1998 | 12/4/1998 | 12/4/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for 2nd floor; c/n issued
|
INSP-Final Inspection | 12/3/1998 | 12/3/1998 | 12/3/1998 | A | PART |
Rick Jackson
|
|
|
walk through to check for completion and status for final occupancy
|
SUPER- Supervisor's review | 12/1/1998 | 12/1/1998 | 12/1/1998 | | |
|
|
|
Handrails not on second exit stair out of second floor. matting not completed. Handrail web not done. Won't be ready for final today.
|
INSP-Final Inspection | 12/1/1998 | 12/1/1998 | 12/1/1998 | P | PART |
Rick Jackson
|
|
|
checked progress for final
|
INSP-Final Inspection | 11/30/1998 | 11/30/1998 | 11/30/1998 | P | PART |
Rick Jackson
|
|
|
checked progress for final occ with George Slane
|
INSP-Final Inspection | 11/25/1998 | 11/25/1998 | 11/25/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for first floor only
|
INSP - Final | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PART |
|
|
|
/ / 333 - PROFIT WITH PHIL
|
INSP - Final | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PART |
|
|
|
/ / 333 - PROFIT WITH PHIL
|
Temporary occupancy | | | 11/25/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3748 issued 11-25-98 to Iceworld for the 2nd floor only.
|
INSP-Final Inspection | 11/24/1998 | 11/24/1998 | 11/24/1998 | P | FAIL |
Rick Jackson
|
|
|
patrick ###-#### fn fire alarms not ready, construction still in progress
|
SUPER- Supervisor's review | 11/23/1998 | 11/21/1998 | 11/21/1998 | | |
|
|
|
checked removal of barricades and stakes along sidewalk which were to be removed saturday am. ok good job super did what he said he would do.
|
INSP-Final Inspection | 11/20/1998 | 11/20/1998 | 11/20/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for rink "a" for the weekend
|
Print Occupancy Form | | | 11/20/1998 | | |
|
|
|
|
Temporary occupancy | | | 11/20/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3747 issued 11-20-98 to Iceworld for the "north" rink only.
|
INSP-Sprinkler Rough-in/Hydro | 11/19/1998 | 11/19/1998 | 11/19/1998 | P | FAIL |
Rick Jackson
|
|
|
window sprinklers have heads within 6 feet
|
INSP-Final Inspection | 11/18/1998 | 11/18/1998 | 11/18/1998 | P | FAIL |
Rick Jackson
|
|
|
rink "a" occ request met with project manager to discuss requirements for opening; all items on c/n will be ready?
|
SUPER- Supervisor's review | 11/17/1998 | 11/17/1998 | 11/17/1998 | | |
|
|
|
reviewed remainder of corrections. finish alarm and duct detector requirements. final on site meeting tomorrow for temp occ for one rink. ok
|
SUPER- Supervisor's review | 11/16/1998 | 11/16/1998 | 11/16/1998 | | |
|
|
|
final walkthrough for temp on north rink, doors on storage rooms to meet compliance with occupancy wall. should be ok, penitration protection completed.
|
SUPER- Supervisor's review | 11/13/1998 | 11/13/1998 | 11/13/1998 | | |
|
|
|
Pre final walkthrough. alarms not ready sprinkler not ready. Penitration protection in progrss. work continuing
|
SUPER- Supervisor's review | 11/10/1998 | 11/10/1998 | 11/10/1998 | | |
|
|
|
FlOyd Varley, Dave Lightfoot, Russ Owen, GS toured facility, checking damper and detector locations. Also alarm system. work will not be completed this week and due to profit meeting they are changing opening date to thankgiving.
|
INSP-Conference | 11/10/1998 | 11/10/1998 | 11/10/1998 | A | PART |
Rick Jackson
|
|
|
3 hour wall penetrations for dampers; corridor on 2nd floor dampers
|
INSP - Framing/Rough-in | 11/6/1998 | 11/6/1998 | 11/6/1998 | P | PART |
Russ Owen
|
|
|
went out to check progress,exterior flat work not yet done,they are in process of wanting to open rink west rink.
|
INSP-Conference | 10/26/1998 | 10/26/1998 | 10/26/1998 | A | PART |
Rick Jackson
|
|
|
profit for partial opening on 11/13. gave requirements to contractor
|
SUPER- Supervisor's review | 10/5/1998 | 10/5/1998 | 10/5/1998 | | |
|
|
|
hydro test one and one half hours.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/1998 | 10/5/1998 | 10/5/1998 | A | PART |
Rick Jackson
|
|
|
sprinkler piping not installed in new spaces
|
Plan assigned to (JCM) | 6/30/1998 | | 7/23/1998 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/1998 | | |
|
|
|
|
Telephone call | | | 7/23/1998 | | |
|
|
|
CALLED NANCY AT ###-####
|
Print Occupancy Form | | | 7/23/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 7/22/1998 | | 7/23/1998 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 7/23/1998 | | |
|
|
|
|
Routing - FIRE | 7/13/1998 | | 7/22/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/17/1998 | | |
|
|
|
RECEIVED 3 COPIES OF BLEACHER DRAWINGS AND APPEAL LETTER FOR FOLDING PANEL PARTITIONS. ROUTED TO JOHN M. KMM
|
Routing - PLAN CHECK | 6/25/1998 | | 7/13/1998 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 7/10/1998 | | PEND |
|
|
|
MAILED CHERYL PEARSE A REQUEST FOR ADDITIONAL CORRECTION SUBMITTALS.
|
Plan resubmittals received | | | 7/6/1998 | | PEND |
|
|
|
RERECEIVED RESUBMITALS FROM CHERYL PEARSE OF HUMMEL ARCHITECTS, FORWARED SAME TO JOHN MENARD.
|
Plan Review Completed(1st rev) | | | 6/24/1998 | | FAIL |
|
|
|
UBC and UFC issues
|
Routing - FIRE | 6/22/1998 | | 6/24/1998 | | FAIL |
|
|
|
need info on refer, smoke dampers missing, refer mach room not fully separated, exiting problem as noted by menard. minor changes to alarms requested for delayed submit
|
Plan resubmittals received | | | 6/23/1998 | | PEND |
|
|
|
RECEIVED STRUCTURAL CACULATION FOR CONCRETE BLEACHERS FROM HUMMEL ARCHITECTS, FORWARDED SAME TO JOHN MENARD
|
Plan resubmittals requested | | | 6/19/1998 | | PEND |
|
|
|
MAILED CHERYL PEARSE AT HUMMEL ARCHITECTS A COPY OF THE PRELIMINARY PLAN REVIEW REQUESTING REVISIONS.
|
Routing - PUBLIC WORKS | 5/29/1998 | | 6/4/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 5/27/1998 | | 5/29/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/29/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/29/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/27/1998 | | 5/27/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/27/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/27/1998 | | PEND |
|
|
|
FAXED GARY HIMES FOR A SIGNED CERT. OF VALUE.
|
Application received | | | 5/27/1998 | | |
|
|
|
|
Routing - PLUMBING | 6/5/1998 | | 6/5/1997 | | PASS |
|
|
|
|
SUPER- Supervisor's review | 11/16/1998 | 11/16/1998 | | | |
|
|
|
|