Permanent occupancy | | | 12/2/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8037 issued 12-2-99 to St. Mark's Elementary School.
|
BLD-Final | 11/30/1999 | 12/1/1999 | 12/1/1999 | A | PASS |
Jim Storey
|
|
|
Final reinspect - Cathy has the card
|
Permanent Occupancy | | 11/30/1999 | 11/30/1999 | | DONE |
|
|
|
|
INSP - Final | 8/26/1998 | 8/27/1998 | 8/27/1998 | A | PART |
Jim Storey
|
|
|
08/27/98 301 - St. Mark's relocatable classroom - Cathy FNL -OK FINAL PENDING PLUMBING
|
Temporary occupancy | | | 8/26/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3680 issued 8-26-98 to St. Mark's School for a relocatable classroom.
|
INSP - Final | 8/25/1998 | 8/25/1998 | 8/25/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 8/21/1998 | 8/21/1998 | 8/21/1998 | P | FAIL |
Joe Tawney
|
|
|
08/21/98 406 - dan ###-#### FINAL FAIL ALARM SYSTEM FD ACCESS
|
INSP-Final Inspection | 8/19/1998 | 8/20/1998 | 8/20/1998 | A | NH |
Joe Tawney
|
|
|
08/20/98 406 - DAN ###-#### NO ONE AT SITE DOORS LOCKED
|
CHANGE STATUS TO (I) | | | 8/11/1998 | | |
|
|
|
|
INSP - Foundation | 7/30/1998 | 7/30/1998 | 7/31/1998 | P | FAIL |
Tom Arcoraci
|
|
|
07/30/98 408 - early pm FOOTING POURED WITHOUT INSPECTION robert ###-####
|
Issue PAID IN FULL permit | | | 7/28/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 7/22/1998 | | 7/27/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/1998 | | PASS |
|
|
|
|
Telephone call | | | 7/27/1998 | | MESS |
|
|
|
DAVID DAVIES ###-####
|
Inspection Record Card- Bld | | | 7/27/1998 | | |
|
|
|
|
Print Occupancy Form | | | 7/27/1998 | | |
|
|
|
|
Plan assigned to (MLO) | 7/7/1998 | | 7/27/1998 | | PASS |
Mike Otto
|
|
|
|
Plan resubmittals received | | | 7/22/1998 | | |
|
|
|
RECEIVED TWO COPIES OF FOUNDATION PLANS AND DETAILS (STAMPED AND SIGNED). TWO COPIES OF PLAN REVIEW COMMENTS ADDRESSED TO MIKE O. ROUTED TO MIKE O.
|
Plan Review Completed(1st rev) | | | 7/16/1998 | | FAIL |
|
|
|
UBC issues
|
Plan resubmittals requested | | | 7/16/1998 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 7/14/1998 | | 7/16/1998 | | FAIL |
|
|
|
|
Routing - FIRE | 7/16/1998 | | 7/16/1998 | | PASS |
|
|
|
field verify alarms... may not connect to other buildings w/o plans.
|
Routing - PLUMBING | 7/9/1998 | | 7/13/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/7/1998 | | 7/9/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/8/1998 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/6/1998 | | 7/7/1998 | | |
John Menard
|
|
|
|
Plan assigned to (MYS) | 7/1/1998 | | 7/6/1998 | | |
Marlene Southard
|
|
|
|
Routing - PLANNING | 7/6/1998 | | 7/6/1998 | | PASS |
|
|
|
X-REF CAA98-0105
|
Plan routing begun/NEW & ADDTN | | | 7/6/1998 | | PEND |
|
|
|
NEED ENG. TIE DOWNS AND PLUMBING SCHEDUAL AND PIPING, BEFORE ROUTING TO P.W. AND PLUMBING.
|
Plans ACCEPTED BY PLAN CHECK | | | 7/6/1998 | | PEND |
|
|
|
CONTACTED DAVE DAVIES TO LET HIM KNOW THAT I NEED 1. ENGINEERED TIE DOWNS 2. FIXTURE SCHEDUAL AND PIPING FOR PLUMBING. 7-8-98 RECEIVED 1. ENGINEERED TIE DOWNS 2. PIPING FOR PLUMBING. PUT ON DAVES DESK TO PUT WITH PLANS WHEN BACK FROM PW 7-9-98 RECEIVED 1. DRAINAGE CALCS. PUT WITH PLANS IN PW
|
Received Certificate of Value | | | 7/2/1998 | | PASS |
|
|
|
|
Application received | | | 7/1/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/1/1998 | | |
|
|
|
|