INSP - Letter of compliance | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 16293
|
INSP - Letter of compliance | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 16293
|
INSP - Final | 11/24/1998 | 11/24/1998 | 11/24/1998 | P | PASS |
Jim Sly
|
|
|
11/24/98 316 - C/C # 16293
|
INSP - Final | 11/23/1998 | 11/23/1998 | 11/24/1998 | P | FAIL |
Tom Arcoraci
|
|
|
11/23/98 408 - walt ###-#### as late as possible
|
INSP - Framing/Rough-in | 10/5/1998 | 10/6/1998 | 10/6/1998 | A | PASS |
Jim Sly
|
|
|
10/06/98 316 - WALT ###-#### REINSPECT
|
INSP - Energy code compliance | 10/2/1998 | 10/5/1998 | 10/5/1998 | A | FAIL |
Tom Arcoraci
|
|
|
10/05/98 408 - walt ###-#### no eng ì
|
INSP - Framing/Rough-in | 10/1/1998 | 10/2/1998 | 10/5/1998 | A | FAIL |
Tom Arcoraci
|
|
|
10/02/98 408 - WALT ###-#### no letter from eng on hold down sub
|
INSP - Framing/Rough-in | 9/30/1998 | 10/1/1998 | 10/5/1998 | A | FAIL |
Jim Sly
|
|
|
10/05/98 316 - C/N....Misc engineering
|
INSP - Framing/Rough-in | 10/1/1998 | 10/1/1998 | 10/1/1998 | | FAIL |
Jim Sly
|
|
|
10/01/98 316 - C/N...Seal at floor deck, Need Eng for 42 in lieu of 22 H
|
INSP - Framing/Rough-in | 9/30/1998 | 9/30/1998 | 10/1/1998 | P | FAIL |
Tom Arcoraci
|
|
|
09/30/98 408 - walt ###-####
|
Issue PAID IN FULL permit | | | 8/25/1998 | | |
|
|
|
|
Telephone call | | | 8/25/1998 | | PASS |
|
|
|
talked to alison at ###-#### that plans are ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/24/1998 | | |
|
|
|
|
Plan assigned to (MLO) | 8/21/1998 | | 8/24/1998 | | PASS |
Mike Otto
|
|
|
08/24/98 15:03:31 MLO - this action updated by action script from <<>> in Case No. BLD98-2308
|
Telephone call | | | 8/24/1998 | | FAIL |
|
|
|
PUT IN CALL TO CONTRACTOR REGARDING ENIGNEERING FOR 18" WALL AT FRONT OF GARAGE. MLO
|
Routing - PLAN CHECK | 8/12/1998 | | 8/22/1998 | | PASS |
|
|
|
|
INSP - Foundation | 8/18/1998 | 8/19/1998 | 8/20/1998 | P | NR |
Tom Arcoraci
|
|
|
08/19/98 408 - BETWEEN 3-4 PM ###-####/ ALREADY POURED APPEARS OK
|
INSP - Conference | 8/19/1998 | 8/19/1998 | 8/19/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 - Insp of excavation for foundation....
|
Plan assigned to (DJO) | 7/31/1998 | | 8/19/1998 | | PEND |
Dan Overy
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/17/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/13/1998 | | |
|
|
|
|
Routing - PLANNING | 7/31/1998 | | 8/11/1998 | | PASS |
|
|
|
as redlined
|
Office Staff conference/action | | | 8/11/1998 | | MESS |
|
|
|
left message that e s is ready
|
Routing - PUBLIC WORKS | 8/11/1998 | | 8/11/1998 | | PASS |
|
|
|
|
Application received | | | 7/31/1998 | | |
|
|
|
|