Letter of compliance | | | 2/23/1999 | | PASS |
|
|
|
Letter of Compliance issued 2-23-99.
|
INSP - Final | 12/17/1998 | 12/17/1998 | 12/17/1998 | | PASS |
Jim Storey
|
|
|
12/16/98 301 - FNL -OK FINAL
|
INSP - Final | 12/15/1998 | 12/15/1998 | 12/15/1998 | P | FAIL |
Jim Storey
|
|
|
12/15/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 11/23/1998 | 11/24/1998 | 11/24/1998 | A | PASS |
Jim Storey
|
|
|
11/24/98 301 - russ called and said to pass job he was on a mech insp. a
|
INSP - Foundation | 9/23/1998 | 9/24/1998 | 9/24/1998 | A | PART |
Russ Owen
|
|
|
09/24/98 407 - footings poured before inspection,set backs ok.
|
Inspection Record Card- Bld | | | 9/3/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/2/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/1998 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 8/19/1998 | | 9/2/1998 | | PASS |
Dan Overy
|
|
|
09/02/98 13:59:35 DJO - this action updated by action script from <<>> in Case No. BLD98-2535
|
Plans ACCEPTED BY PLAN CHECK | | | 9/1/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/19/1998 | | 8/24/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 8/24/1998 | | 8/24/1998 | | PASS |
|
|
|
|
Application received | | | 8/19/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 8/24/1998 | | | | PEND |
|
|
|
|