Information based on query as of Saturday, September 28, 2024.
Permit Information
Permit NumberBLD98-03931
StatusExpired
Name PIZZA HUT
Site Address 6871 W OVERLAND RD
Project NamePIZZA HUT
Customer Number 
ePlanReviewNo
Description
PIZZA HUT * TO ADD A 240 SQ.FT. PRE FABRICATED WALKIN COOLER/FREEZER UNIT ON A CONCRETE Foundation. Construction is of insulated panels. Originally this building was classified as type V-1hr construction, as V-N it is still under the basic allowable area. CZC98-0193 PC#893-98 ads
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final6/14/19996/14/19996/14/1999PFAIL
DetailsCarl Dependahl
06/14/99 340 - Eric ###-####; NEED LANDING, NOT RAMP
INSP-Final Inspection4/28/19994/29/19994/29/1999APASS
DetailsJoe Tawney
Eric ###-#### OK FOR PERMIT ITEMS ONLY
INSP - Final4/28/19994/29/19994/29/1999PFAIL
DetailsCarl Dependahl
04/29/99 340 - Eric ###-####;need landing at door & occ card
INSP - Final4/27/19994/28/19994/28/1999PFAIL
DetailsCarl Dependahl
04/28/99 340 - ERIC ###-#### THE FINAL FIRE WAS SENT OUT 4/27-MECH DONE ON 4/21 AND IT PASSED need fire
INSP-Final Inspection4/27/19994/27/19994/27/1999PNR
DetailsJoe Tawney
final NOT READY NO PLANS ON SITE
INSP - Final4/16/19994/19/19994/18/1999AFAIL
DetailsCarl Dependahl
04/19/99 340 - Scheduled by Hello!. Contact phone is [3237767].;;need m
INSP - Foundation1/29/19991/29/19991/29/1999PPART
DetailsCarl Dependahl
01/29/99 340 - CHARLIE ###-#### slab for refrig/storage ok
Issue PAID IN FULL permit  1/20/1999
Plan assigned to (ADS)1/4/1999 1/15/1999 PASS
Details
01/15/99 07:44:26 ADS - this action updated by action script from <<>> in Case No. BLD98-3931
Inspection Record Card- Bld  1/15/1999
Telephone call  1/15/1999
GREG PETERSON\###-####
Print Occupancy Form  1/15/1999
PLANS/APPL TAKEN TO FRONT DESK  1/15/1999 PASS
Routing - FIRE1/13/1999 1/14/1999 PASS
Plan Review Completed(1st rev)  1/14/1999 PASS
Routing - PLAN CHECK1/12/1999 1/13/1999 PASS
Routing - PUBLIC WORKS1/8/1999 1/12/1999 PASS
Routing - PLANNING1/4/1999 1/8/1999 PASS
approved per CZC98-0193.
Routing Off Site - C.D.H12/29/1998 1/4/1999 PASS
CONTACTED GREG PETERSON TO TAKE PLANS OUT TO CDH. KMM
Plan assigned to (JCM)12/29/1998 1/4/1999 PASS
DetailsJohn Menard
Plan routing begun/NEW & ADDTN  12/29/1998
Plan assigned to (MYS)12/28/1998 12/29/1998
DetailsMarlene Southard
Received Certificate of Value  12/29/1998 PASS
Plans ACCEPTED BY PLAN TECH  12/29/1998 PASS
Application received  12/28/1998 PASS
Recd Pcfee & Taken To Pln CK  12/28/1998
Routing - PLAN CHECK1/15/1999  
Fee Review-notes2/22/1999  
linda don't forget mech permit none pulled right now