Information based on query as of Saturday, September 28, 2024.
Permit Information
Permit NumberBLD99-00035
StatusFinaled
Name JAMESON 1991 REV TRUST "A"
Site Address 1021 S BROADWAY AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
This project encludes: the removal of interior walls to to create an open retail space, the construction of a second story (mezzanine) inside the existion space for use a storage, office and break area. Cutting new openings in existing walls, one for door to parking lot, one into the ajacent space in the building. Includes associated finish work. The mezzanine is considered a 2nd story to keep the building under the allowable area. The occupant load of the 2nd story is less than 10. If the areas use is changed and additional exit or exit access may be required. A density reduction survey has been recorded to combine the property from the north wall of the building to a line 100 ft. south. That south property line falls on an existing property line wall. This wall is on the line that was the line between lot 13 & 14. The opening in this wall in to be closed. (pc011-99) ads
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/19/1999 5/26/1999 OK
Permanent occupancy  4/28/1999 PASS
Perm. Occ. Cert. #7753 issued 4-28-99 to Newt & Harold's.
Code Occupancy Approval  4/27/1999 PASS
SOME PARKING LOT IMPROVEMENTS NOT DONE (PAINT) AND BUILDING (SOME PAINT) ACCEPTED CONTRACTORS BID OF $797 WITH OUR 10% TOTAL BOND AMOUNT IS APPROVED FOR $876, WHEN POSTED WILL SIGN OFF TEMPORARY OCCUPANCY. BOND POSTED WITH CATHY FOR THE $876, TEMPORARY OCCUPANCY SIGNED OFF. PAINTING DONE, ALL CONDITIONS HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
INSP - Final4/13/19994/14/19994/14/1999PPASS
DetailsJim Storey
04/14/99 301 - FNL -OK FINAL
Permanent Occupancy 4/14/19994/14/1999 DONE
Details
INSP - Final4/8/19994/9/19994/9/1999PPART
DetailsJim Storey
04/09/99 301 - ada not complete temp ok
INSP-Final Inspection4/6/19994/7/19994/7/1999ANR
DetailsRick Jackson
###-#### detectors not ready
INSP-Final Inspection4/7/19994/7/19994/7/1999PPASS
DetailsRick Jackson
occ approved
Code Occupancy Approval  4/7/1999
temporary occupancy requested by Mike ###-####
INSP-Final Inspection4/6/19994/6/19994/6/1999PFAIL
DetailsRick Jackson
###-#### MIKE//FIRE & LIFE SAFETY duct detectors not complete
INSP - Framing/Rough-in3/17/19993/18/19993/18/1999APART
DetailsJim Storey
03/18/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to gyp wall
Plan resubmittals received  3/4/1999
Received two copies of sheets A.8 and routed to the inspector. KMM
Plan resubmittals received  2/18/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM TROUT ARCHITECTS, FORWARDED SAME TO JIM STOREY. DAR 2/18/99
Issue PAID IN FULL permit  2/18/1999
Telephone call  2/12/1999
called permit ready
Print Occupancy Form  2/12/1999
Inspection Record Card- Bld  2/12/1999
Plan assigned to (ADS)1/11/1999 2/11/1999 PASS
Details
02/11/99 14:18:25 ADS - this action updated by action script from <<>> in Case No. BLD99-0035
Routing - PUBLIC WORKS2/10/1999 2/11/1999 FAIL
HAVE NOT RECEIVED SURVEY OF LEGAL LAND DIVISION. 2-5-99 JR.
PLANS/APPL TAKEN TO FRONT DESK  2/11/1999 PASS
Routing - PUBLIC WORKS2/11/1999 2/11/1999 PASS
Routing - PLAN CHECK2/11/1999 2/11/1999 PASS
Routing - PLAN CHECK2/11/1999 2/11/1999
to public works
Routing - PLAN CHECK2/5/1999 2/10/1999 PASS
to public works
Routing - PLANNING2/2/1999 2/5/1999 PASS
approved per CZC98-0212 (and letter in file from Trout Architects).
Routing - PUBLIC WORKS2/5/1999 2/5/1999 FAIL
REQUIRES PROOF OF LEGAL LAND DIVISION, PER JIM RICH. DAR 2/5/99
Routing - PLAN CHECK1/28/1999 2/2/1999 PEND
pending density reduction record of survey.
Plan resubmittals received  1/28/1999
RECEIVED TWO COPIES OF REVISED SHEETS S.1, A.1, A.2, A.3, A.5, A.6, A.7, WITH STRUC. CALCS. ROUTED TO ARLAN S. KMM
Routing - FIRE1/25/1999 1/27/1999 PASS
Plan Review Completed(1st rev)  1/27/1999 FAIL
ubc, planning, public works
Routing - PLAN CHECK1/21/1999 1/25/1999 FAIL
Plan resubmittals requested  1/25/1999 FAIL
plan review report faxed & mailed to architect.
Routing - PUBLIC WORKS1/20/1999 1/20/1999 FAIL
REQUIRES PROOF OF LEGAL LAND DIVISION. DAR 1/21/99
Routing - PLANNING1/11/1999 1/19/1999 FAIL
Exterior work approved under CZC98-0212; however, no interior work for new mezzanine can be done until an additional 13 parking spaces are provided.
Plan resubmittals received  1/14/1999 PEND
RECEIVED RESUBMITTALS FROM TROUT ARCHITECTS, FORWARDED SAME TO ARLAN SMITH. DAR 1/14/98
Plan Reviewer's activity  1/11/1999
This submittal appears to have several problems: Opening cannot be installed between 2 properties. Therefore, a record of survey merging all 5 pieces of property will need to be done PRIOR TO ISSUANCE OF THIS PERMIT.
Plan routing begun/TENANTS  1/11/1999
Route to PLAN CHECK, PUBLIC WORKS, PLANNING and FIRE.
Plan assigned to (MYS)1/6/1999 1/11/1999
DetailsMarlene Southard
Telephone call  1/11/1999 FAIL
Spoke with Dwaine Carver, architect. Requested density reduction & other corrections or clarifications.
Plans ACCEPTED BY PLAN TECH1/7/1999 1/7/1999 PASS
Recd Pcfee & Taken To Pln CK  1/6/1999
Application received  1/6/1999 PEND
REQUIRES RECORD DECLARATION FORM. CONTACTED DWAINE CARVER OF THIS NEED. HE WILL BE FAXING ONE OVER. KMM