Case Summary (BLD) | | | 6/24/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/24/2016 | | DONE |
|
|
|
|
Fee Review-notes | 4/8/1999 | | 8/23/1999 | | |
|
|
|
RM HAS A T& M
|
Permanent occupancy | | | 8/3/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7861 issued 8-3-99 to IXC Communications, Inc.
|
INSP - Final | 7/27/1999 | 7/28/1999 | 7/28/1999 | A | PASS |
|
|
|
07/28/99 338 - signed the perm col of the occ req card
|
Permanent Occupancy | | 7/27/1999 | 7/27/1999 | | DONE |
|
|
|
|
INSP-Final Inspection | 7/23/1999 | 7/23/1999 | 7/23/1999 | A | PASS |
Rick Jackson
|
|
|
alarms tested okay - occ approved
|
Code Occupancy Approval | | | 7/23/1999 | | |
|
|
|
final occupancy requested by Walter ###-####
|
Code Occupancy Approval | | | 6/16/1999 | | |
|
|
|
Final Occupancy requested by Walter Falash ###-####
|
INSP - Framing/Rough-in | 4/20/1999 | 4/20/1999 | 4/21/1999 | P | PART |
|
|
|
04/20/99 338 - made ok r-bar placed
|
INSP - Framing/Rough-in | 4/13/1999 | 4/15/1999 | 4/15/1999 | P | PART |
|
|
|
04/15/99 338 - made ok for seizmic
|
INSP-Supply line flush | 4/13/1999 | 4/13/1999 | 4/13/1999 | P | PASS |
Rick Jackson
|
|
|
Eric ###-#### retest of flow with Bill from united Water
|
INSP-Supply line flush | 4/13/1999 | 4/13/1999 | 4/13/1999 | A | FAIL |
Rick Jackson
|
|
|
iron deposits/red water from flow
|
INSP - Framing/Rough-in | 4/8/1999 | 4/8/1999 | 4/8/1999 | | PART |
|
|
|
04/07/99 338 - made ok to cover behind othr insp
|
Issue PAID IN FULL permit | | | 3/31/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/1999 | | |
|
|
|
|
Telephone call | | | 3/30/1999 | | PASS |
|
|
|
talked to jennifer to verify plans are ready
|
Print Occupancy Form | | | 3/30/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/1999 | | PASS |
|
|
|
Plans approved as noted and attached by Fire & Building Depts. Processing for issuance of prmti.
|
Plan assigned to (DRS) | 3/20/1999 | | 3/30/1999 | | PASS |
Dan Stuart
|
|
|
03/30/99 13:30:41 DRS - this action updated by action script from <<>> in Case No. BLD99-0734
|
Routing - PLAN CHECK | 3/30/1999 | | 3/30/1999 | | PASS |
|
|
|
Processing for issuance of permit.
|
Plan Review Completed(1st rev) | | | 3/29/1999 | | FAIL |
|
|
|
ubc issue
|
Routing - FIRE | 3/26/1999 | | 3/29/1999 | | PASS |
|
|
|
need Battery Room Design and Fire alarm design before installing
|
Routing - PUBLIC WORKS | 3/25/1999 | | 3/26/1999 | | PASS |
|
|
|
Sent to public works for Bill Colson. DAR 3/25/99
|
Routing - PLANNING | 3/22/1999 | | 3/25/1999 | | PASS |
|
|
|
ref. CZC99-29: Signed off but still need to resolve building colors, generator housing color, color and material for fence slats. Approved the use of mulch and shrubs in the right-of-way landscaping (modified condition 3). Faxed memo to applicants advising them of what is yet to be done. - M. Hall, 3/25/99.
|
Plan resubmittals received | | | 3/24/1999 | | |
|
|
|
Received resubmittals from Bob Ross. Entered into plans & returned to Public Works for continued review.
|
Print Pending Permit.LaserJet4 | | | 3/20/1999 | | PEND |
|
|
|
|
Plan assigned to (MYS) | 3/18/1999 | | 3/20/1999 | | |
Marlene Southard
|
|
|
|
Routing - PLAN CHECK | 3/20/1999 | | 3/20/1999 | | PEND |
|
|
|
PRELIMINARY REVIEW FINISHED. ROUTING TO OTHER AGENCIES.
|
Plan resubmittals requested | | | 3/20/1999 | | PEND |
|
|
|
PRELIMINARY PLAN REVIEW NOTED CLARIFICATIONS & ADDITIONAL PLANS MODIFICATIONS NEEDED PRIOR TO ISSUANCE OF A PERMIT. COPY TO ARCHITECT FOR RESPONSE.
|
Plans ACCEPTED BY PLAN TECH | | | 3/19/1999 | | PEND |
|
|
|
|
Application received | | | 3/18/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/18/1999 | | |
|
|
|
|
Meeting | | | 3/18/1999 | | |
|
|
|
MEETING WITH BOB rOSS TO REVIEW PROPOSED PLANS FOR REMODEL OF EXISTING BUILIDNG FOR USE AS TELECOMMUNICATIONS CENTER. REVIEWED PROPOSAL & COMMENTED THAT ACCESSIBILITY REQUIREMENTS WOULD NEED TO BE MET FOR OFFICE, MAIN ENTRY AND RESTROOM. REVIEWED TUBE STEEL POST & UNISTRUT SUBSTRUCTURE TO SUPPORT EQUIPMENT CABLES & LIGHT FIXTURES. ACCEPTED PLANS FOR PROCESSING AS DESK PERMIT.
|