Letter of compliance | | | 12/23/1999 | | DONE |
|
|
|
Letter of Compliance #18214 issued 12-23-99.
|
BLD-Final | 12/20/1999 | 12/20/1999 | 12/20/1999 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/20/1999 at 08:50:36. Contact: ###-####. Rec'd spec. insp. Reports.
|
BLD-Final | 12/16/1999 | 12/17/1999 | 12/17/1999 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/16/1999 at 13:57:07. Contact: ###-####. Struct. Appears ok; no plbg?
|
FIRE-Final Inspection | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 16:37:00. Contact: ###-####. Reisnp. Ok for certificate of completion.
|
BLD-Final | 12/9/1999 | 12/10/1999 | 12/10/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 16:38:22. Contact: ###-####. Need plmg. Ok, etc. keep C/N.
|
FIRE-Final Inspection | 12/8/1999 | 12/9/1999 | 12/9/1999 | P | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/08/1999 at 15:57:49. Contact: ###-####. Final fail access signs C/N issued.
|
Code Occupancy Approval | | | 12/8/1999 | | PASS |
|
|
|
Complies with DRH99-0007 - pass
|
BLD-Wall cover | 11/16/1999 | 11/17/1999 | 11/17/1999 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/16/1999 at 10:54:10. Contact: ###-####. Ok to cover North wall (1hr) keep C/N.
|
BLD-Wall cover | 11/12/1999 | 11/15/1999 | 11/15/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/12/1999 at 10:26:23. Contact: ###-####. C/N: frame issues, other signatures, etc.
|
BLD-Final | 11/1/1999 | 11/1/1999 | 11/1/1999 | P | FAIL |
Carl Dependahl
|
|
|
LETTER OF COMPLIANCE FOR SHELL AND CORE KEITH ###-#### Need other insp. N/R
|
FIRE-Final Inspection | 10/27/1999 | 10/28/1999 | 10/28/1999 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/27/1999 at 10:57:46. Contact: ###-####. Conf. Concerning sign off of shell bldg.
|
INSP - Framing/Rough-in | 8/23/1999 | 8/24/1999 | 8/24/1999 | A | PART |
Carl Dependahl
|
|
|
08/24/99 340 - roof deck ok to cover!. Contact phone is [4248171].
|
INSP - Framing/Rough-in | 8/18/1999 | 8/20/1999 | 8/20/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/20/99 340 - ken-superintendent--###-#### off fr r/i not onsite, left
|
INSP - Framing/Rough-in | 8/7/1999 | 8/9/1999 | 8/9/1999 | A | PART |
Carl Dependahl
|
|
|
08/09/99 340 - east shear walls ok; part no. side gyp ok for 1 hr. Hello
|
INSP - Framing/Rough-in | 8/6/1999 | 8/6/1999 | 8/6/1999 | P | PART |
Carl Dependahl
|
|
|
08/06/99 340 - NO SIDE SHEAR OKScheduled by Hello!. Contact phone is [4
|
INSP - Framing/Rough-in | 8/5/1999 | 8/5/1999 | 8/5/1999 | P | PART |
Carl Dependahl
|
|
|
08/05/99 340 - shear walls at so side & int ok Contact phone is [4248171
|
INSP - Framing/Rough-in | 8/3/1999 | 8/4/1999 | 8/4/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/04/99 340 - need nailing at shear walls; recall
|
Plan resubmittals received | | | 7/16/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, BEN JANSEN, FORWARDED SAME TO CARL DEPENDAHL. DAR 7/16/99
|
INSP - Foundation | 6/23/1999 | 6/24/1999 | 6/24/1999 | P | PART |
Carl Dependahl
|
|
|
06/24/99 340 - ###-####//FOUNDATION; part, walls ok
|
INSP - Foundation | 6/23/1999 | 6/23/1999 | 6/23/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - PART ONLY; CONF W/ CONTRACTOR.
|
INSP - Foundation | 6/21/1999 | 6/22/1999 | 6/22/1999 | P | PASS |
Jim Storey
|
|
|
06/22/99 301 - footing north ok wall south ok
|
INSP - Foundation | 6/16/1999 | 6/18/1999 | 6/18/1999 | A | PART |
Jim Storey
|
|
|
06/18/99 301 - ft ok north & west lines
|
(F) Reprint permit | | | 6/17/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/16/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 5/21/1999 | | 6/4/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/4/1999 | | PASS |
|
|
|
|
Telephone call | | | 6/4/1999 | | PASS |
|
|
|
talked to ben jansen to verify plans are ready
|
Inspection Record Card- Bld | | | 6/4/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 6/2/1999 | | 6/4/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/4/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/4/1999 | | |
|
|
|
|
Plan assigned to (M_P) | 4/12/1999 | | 6/4/1999 | | PASS |
Mike Phillips
|
|
|
06/04/99 15:31:17 M_P - this action updated by action script from <<>> in Case No. BLD99-0969
|
Routing - PLAN CHECK | 5/6/1999 | | 6/2/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/1/1999 | | PEND |
|
|
|
Waiting for other to approve plans out side engineering complete.
|
Routing - PUBLIC WORKS | 5/21/1999 | | 5/21/1999 | | FAIL |
|
|
|
REQUIRES LIGHTING PLAN PER BILL COLSON. DAR 5/21/99
|
Routing - PLAN CHECK | 5/18/1999 | | 5/21/1999 | | |
|
|
|
Routing plans to Public Works for follow up review.
|
Plan resubmittals received | | | 5/20/1999 | | |
|
|
|
RECEIVED TWO COPIES OF STRUCTURAL REVISED SHEETS AND CALCULATIONS (S1.0, S1.1)
|
Routing - FIRE | 5/18/1999 | | 5/18/1999 | | PASS |
|
|
|
Provided fire flows and location acceptable by Lan Smith upon consultation 05/18/99.
|
Plan Reviewer's activity | | | 5/6/1999 | | PEND |
|
|
|
Waiting for structural comments to be approved and waiting for others to approve. Faxed structural comments to architect on 05/06/99
|
Plan Review Completed(1st rev) | | | 5/5/1999 | | FAIL |
|
|
|
UBC, UFC and PW fails
|
Routing - FIRE | 4/28/1999 | | 5/5/1999 | | FAIL |
|
|
|
not enough fire flow - requirement was understated on DRH99-0007 application for size and type of construction. 3500 required as drawn - 2500 available
|
Routing Off Site - STRUCTURAL | 4/13/1999 | | 4/28/1999 | | FAIL |
|
|
|
RECEIVED STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 4-27-99. ROUTED TO MIKE P. Requires additional comments from structural engineer to be submitted. Second review preformed by plan reviewer. Sent letter to outside engineering firm to comform plan review completed by plan reviewer in our office.
|
Plan Reviewer's activity | | | 4/27/1999 | | |
|
|
|
ROUTING TO FIRE DEPARTMENT, AWAITING COMMENTS FROM OUTSIDE ENGINEERING FIRM.
|
Routing - PLAN CHECK | 4/23/1999 | | 4/27/1999 | | |
|
|
|
ROUTING TO FIRE DEPARTMENT.
|
Routing - PLANNING | 4/21/1999 | | 4/23/1999 | | PASS |
|
|
|
x-ref. DRH99-0007 & DRh99-0048
|
Routing - PLUMBING | 4/16/1999 | | 4/21/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/13/1999 | | 4/16/1999 | | FAIL |
|
|
|
BEN JOHNSON OF BRS ###-#### WILL BE SENDING PLAN SOON. PER BILL COLSON. KMM
|
Plan assigned to (MYS) | 4/9/1999 | | 4/12/1999 | | PASS |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | 4/12/1999 | | 4/12/1999 | | |
|
|
|
|
Application received | | | 4/9/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/9/1999 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/2/1999 | | | | PASS |
|
|
|
Follow up review completed by plan reviewer.
|