Fee Review-notes | 10/7/1999 | 10/7/1999 | 5/5/2000 | | DONE |
|
|
|
|
BLD-Final | 9/16/1999 | 9/17/1999 | 9/20/1999 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 09/16/1999 at 11:17:44. Contact: ###-####. #16465
|
CHANGE STATUS TO (D) | | | 9/20/1999 | | DONE |
|
|
|
Letter of Compliance #16465 issued 9-20-99 by Perry Paine.
|
FIRE-Final Inspection | 9/15/1999 | 9/16/1999 | 9/16/1999 | A | PASS |
Joe Tawney
|
|
|
OK FOR CERT OF COMPLETION
|
Receive PAYMENT IN FULL | | | 9/2/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 6/24/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/21/1999 | | PASS |
|
|
|
Approved as noted and attached.
|
Routing - PLAN CHECK | 6/21/1999 | | 6/21/1999 | | PASS |
|
|
|
Approved as noted and attached.
|
Print Occupancy Form | | | 6/21/1999 | | |
|
|
|
|
Plan assigned to (DRS) | 6/18/1999 | | 6/21/1999 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/1999 | | PASS |
|
|
|
Routing to permit desk to process for permit.
|
Inspection Record Card- Bld | | | 6/21/1999 | | |
|
|
|
|
Application received | | | 6/18/1999 | | |
|
|
|
|
Meeting | | | 6/18/1999 | | |
|
|
|
Met with Curtis Weedop, SLRMC Construction to review scope of project. Determined could be processed as a desk permit.
|